Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Park Views Residences handover date?

Updated 12 October 2026 Park Views Residences

Short answer

Park Views Residences Tower A is listed for handover in Q4 2026, and Tower B has a registered completion date of 1 March 2027. The latest DLD inspections recorded Tower A at 95.54% complete on 8 September 2026 and Tower B at 98.84% on 6 October 2026. The two towers have separate DLD projects, so the date depends on which tower a unit is in.

Tower B registered completion date (DLD)

1 Mar 2027

DLD project register via Continental Club

Tower A construction progress

95.54%

DLD inspection, 8 Sep 2026

Tower A handover, listed

Q4 2026

Bayut; JRE; Data Habibi

Tower B construction progress

98.84%

DLD inspection, 6 Oct 2026

Park Views Residences handover date: the latest position

Park Views Residences Tower A is listed for handover in Q4 2026, and Tower B has a registered completion date of 1 March 2027. Prices, sizes and payment plans for both are on the Park Views Residences page.

Both towers are near the end of construction. Tower A was 95.54% complete at its DLD inspection on 8 September 2026. Tower B was 98.84% complete at its DLD inspection on 6 October 2026, up from 90.91% on 13 May 2026. Neither has been handed over yet.

Park Views Residences handover date by building

Each tower is a separate DLD project: Park Views Residences A (project 2630, 615 units) and Park Views Residences B (project 2576, 476 units).

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Tower A 95.54%, 8 Sep 2026 Not shown by Continental Club; 2026 per Data Habibi Q4 2026 (Bayut; JRE; Data Habibi)
Tower B 98.84%, 6 Oct 2026 1 Mar 2027 Q1 2027 (Continental Club; Data Habibi); Q4 2026 (Bayut, whole development)

How the Park Views Residences handover date has changed

Date What happened Source
1 Mar 2023 Tower B construction start recorded DLD register
16 Mar 2023 Wasl launches Tower B, 1 bedrooms from AED 1.3 million Property B News
25 Jul 2023 Tower A construction start recorded DLD register
21 Mar 2024 Wasl says all 600 Tower A units sold within 36 hours Wasl
7 Oct 2025 Tower B inspection records 71.81% DLD register
20 Feb 2026 Tower A inspection records 80.02% DLD register
13 May 2026 Tower B inspection records 90.91% DLD register
8 Sep 2026 Tower A inspection records 95.54% DLD register
6 Oct 2026 Tower B inspection records 98.84% DLD register

Wasl’s launch releases did not give a handover date for either tower. Data Habibi records an original delivery promise of Q1 2025 for Tower A, against today’s Q4 2026 target. Tower B’s registered date of 1 March 2027 is four years after its construction start. Tower A, which started almost five months later, is close behind, at 95.54% against Tower B’s 98.84%.

What the Park Views Residences handover date means for payments

The two towers carry different handover payments. Tower B was sold on 5% at booking, 55% during construction and 40% on handover (Bayut; Data Habibi). For Tower A, the DLD record shows 10% on booking, 30% during construction and 60% on handover, and Wasl’s factsheet also shows 60% on handover. On a Tower A 2 bedroom at the median DLD price of AED 2,319,777, a 60% handover payment would be about AED 1,391,900, due once the tower is completed.

What to check before relying on the Park Views Residences date

  1. Which tower the unit is in. Tower A and Tower B are separate DLD projects with different progress and dates.
  2. Tower A’s handover notice and 60% payment. With the tower at 95.54% in September 2026, the handover payment may be called within months.
  3. Tower B’s SPA date, which may follow the registered 1 March 2027 date rather than Bayut’s Q4 2026.

Questions buyers also ask

Is Park Views Residences finished?

Not yet. Tower A was 95.54% complete on 8 September 2026 and Tower B 98.84% complete on 6 October 2026 (DLD project register via Continental Club). Neither had been handed over by 11 October 2026.

When will Park Views Residences Tower A be ready?

Tower A is listed for handover in Q4 2026 (Bayut; JRE; Data Habibi). Its progress rose from 80.02% on 20 February 2026 to 95.54% on 8 September 2026.

What is the Park Views Residences Tower B completion date?

The DLD register gives Tower B a completion date of 1 March 2027, Q1 2027. Bayut's guide still lists Q4 2026 for the development as a whole.

Has the Park Views Residences handover date been delayed?

Data Habibi records an original delivery promise of Q1 2025 for Tower A and calls the current Q4 2026 target a 22 month postponement. Wasl's launch releases did not state a handover date. For Tower B, Bayut's Q4 2026 and the registered 1 March 2027 date differ by about a quarter.

Sources