When is the Park Views Residences handover date?
Short answer
Park Views Residences Tower A is listed for handover in Q4 2026, and Tower B has a registered completion date of 1 March 2027. The latest DLD inspections recorded Tower A at 95.54% complete on 8 September 2026 and Tower B at 98.84% on 6 October 2026. The two towers have separate DLD projects, so the date depends on which tower a unit is in.
Tower B registered completion date (DLD)
1 Mar 2027
DLD project register via Continental Club
Tower A construction progress
95.54%
DLD inspection, 8 Sep 2026
Tower A handover, listed
Q4 2026
Bayut; JRE; Data Habibi
Tower B construction progress
98.84%
DLD inspection, 6 Oct 2026
Park Views Residences handover date: the latest position
Park Views Residences Tower A is listed for handover in Q4 2026, and Tower B has a registered completion date of 1 March 2027. Prices, sizes and payment plans for both are on the Park Views Residences page.
Both towers are near the end of construction. Tower A was 95.54% complete at its DLD inspection on 8 September 2026. Tower B was 98.84% complete at its DLD inspection on 6 October 2026, up from 90.91% on 13 May 2026. Neither has been handed over yet.
Park Views Residences handover date by building
Each tower is a separate DLD project: Park Views Residences A (project 2630, 615 units) and Park Views Residences B (project 2576, 476 units).
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Tower A | 95.54%, 8 Sep 2026 | Not shown by Continental Club; 2026 per Data Habibi | Q4 2026 (Bayut; JRE; Data Habibi) |
| Tower B | 98.84%, 6 Oct 2026 | 1 Mar 2027 | Q1 2027 (Continental Club; Data Habibi); Q4 2026 (Bayut, whole development) |
How the Park Views Residences handover date has changed
| Date | What happened | Source |
|---|---|---|
| 1 Mar 2023 | Tower B construction start recorded | DLD register |
| 16 Mar 2023 | Wasl launches Tower B, 1 bedrooms from AED 1.3 million | Property B News |
| 25 Jul 2023 | Tower A construction start recorded | DLD register |
| 21 Mar 2024 | Wasl says all 600 Tower A units sold within 36 hours | Wasl |
| 7 Oct 2025 | Tower B inspection records 71.81% | DLD register |
| 20 Feb 2026 | Tower A inspection records 80.02% | DLD register |
| 13 May 2026 | Tower B inspection records 90.91% | DLD register |
| 8 Sep 2026 | Tower A inspection records 95.54% | DLD register |
| 6 Oct 2026 | Tower B inspection records 98.84% | DLD register |
Wasl’s launch releases did not give a handover date for either tower. Data Habibi records an original delivery promise of Q1 2025 for Tower A, against today’s Q4 2026 target. Tower B’s registered date of 1 March 2027 is four years after its construction start. Tower A, which started almost five months later, is close behind, at 95.54% against Tower B’s 98.84%.
What the Park Views Residences handover date means for payments
The two towers carry different handover payments. Tower B was sold on 5% at booking, 55% during construction and 40% on handover (Bayut; Data Habibi). For Tower A, the DLD record shows 10% on booking, 30% during construction and 60% on handover, and Wasl’s factsheet also shows 60% on handover. On a Tower A 2 bedroom at the median DLD price of AED 2,319,777, a 60% handover payment would be about AED 1,391,900, due once the tower is completed.
What to check before relying on the Park Views Residences date
- Which tower the unit is in. Tower A and Tower B are separate DLD projects with different progress and dates.
- Tower A’s handover notice and 60% payment. With the tower at 95.54% in September 2026, the handover payment may be called within months.
- Tower B’s SPA date, which may follow the registered 1 March 2027 date rather than Bayut’s Q4 2026.
Questions buyers also ask
Is Park Views Residences finished?
Not yet. Tower A was 95.54% complete on 8 September 2026 and Tower B 98.84% complete on 6 October 2026 (DLD project register via Continental Club). Neither had been handed over by 11 October 2026.
When will Park Views Residences Tower A be ready?
Tower A is listed for handover in Q4 2026 (Bayut; JRE; Data Habibi). Its progress rose from 80.02% on 20 February 2026 to 95.54% on 8 September 2026.
What is the Park Views Residences Tower B completion date?
The DLD register gives Tower B a completion date of 1 March 2027, Q1 2027. Bayut's guide still lists Q4 2026 for the development as a whole.
Has the Park Views Residences handover date been delayed?
Data Habibi records an original delivery promise of Q1 2025 for Tower A and calls the current Q4 2026 target a 22 month postponement. Wasl's launch releases did not state a handover date. For Tower B, Bayut's Q4 2026 and the registered 1 March 2027 date differ by about a quarter.