Handover date

When is the Octa Isle Interiors by Missoni handover date?

Updated 11 October 2026 Octa Isle Interiors by Missoni

Short answer

Octa Isle Interiors by Missoni has a registered completion date of 30 September 2027, which matches OCTA Development's Q3 2027 handover. A Dubai Land Department inspection on 1 September 2026 recorded construction 6.24% complete, up from 3.35% in May. With about 13 months left and most of the building still to be built, the pace of the next inspections matters more than the date itself.

Registered completion date

30 Sep 2027

DLD project register via Continental Club

Latest construction progress

6.24%

DLD inspection, 1 Sep 2026

Developer's stated date

Q3 2027

OCTA launch, Sep 2025; Property Finder: Sep 2027

Average pace since May 2025

0.41 points a month

Data Dubai, from DLD inspections

Octa Isle Interiors by Missoni handover date: the latest position

Octa Isle Interiors by Missoni is registered with the Dubai Land Department (DLD) for completion on 30 September 2027. OCTA Development announced a Q3 2027 handover at launch in September 2025, and Property Finder shows September 2027, so the developer and the register agree. Prices, sizes and payment plans are on the project page: Octa Isle Interiors by Missoni.

The latest DLD inspection, on 1 September 2026, recorded 6.24%. That leaves almost the whole building to complete in about 13 months.

Octa Isle Interiors by Missoni handover date by building

Octa Isle is one building of ground, two podium levels, 12 residential floors and a roof, registered as DLD project 3793 in Nakhlat Deira, the DLD district for Dubai Islands.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Octa Isle Interiors By Missoni (112 units) 6.24% (1 Sep 2026) 30 Sep 2027 Q3 2027 (OCTA, Alnair); September 2027 (Property Finder)

How the Octa Isle Interiors by Missoni handover date has changed

Date Event Source
27 May 2025 DLD inspection: 0% Data Dubai
1 Aug 2025 Construction start on the DLD register; completion set for 30 Sep 2027 DLD via Continental Club
28 Aug 2025 Project registered with the DLD Data Dubai
8 to 9 Sep 2025 Launch announced with a Q3 2027 handover Zawya; Alnair
16 Feb 2026 DLD inspection Data Dubai
21 May 2026 DLD inspection: 3.35% DLD via Continental Club
1 Sep 2026 DLD inspection: 6.24% DLD via Continental Club
6 Oct 2026 Register update still holds 30 Sep 2027 DLD via Continental Club

The date has held since launch. One data site still showed the registered status as not started in late September 2026 (Overit, data updated 26 September 2026), while the DLD inspections show slow but rising progress. Between May and September 2026 the building gained 2.89 points in just over three months. To reach 100% by 30 September 2027, it would need about 7 points a month from September 2026.

What the Octa Isle Interiors by Missoni handover date means for payments

On the main 68/32 plan, buyers pay 20% on booking, 8% at 6 months and 8% at 12 months after booking, then 8% at each of 30%, 50%, 60% and 70% construction, and 32% on handover (Tanami Properties). For September 2025 buyers, the two time based payments fell due by September 2026. The four stage based payments, 32% in all, have not been triggered at 6.24% and will follow the pace of work. On the 30/70 offer for some 2 bedroom units, 70% waits for handover.

What to check before relying on the Octa Isle Interiors by Missoni date

  1. The completion date and grace period in the SPA, since the registered date leaves about 13 months for some 94% of the work.
  2. Which plan the unit is on. The handover share is 32% on one plan and 70% on the other.
  3. The next DLD inspection, to see whether the pace rises from the roughly 0.9 points a month recorded between May and September 2026.

Questions buyers also ask

When will Octa Isle Interiors by Missoni be completed?

The registered completion date is 30 September 2027, and OCTA gives Q3 2027. Construction was 6.24% complete on 1 September 2026.

What is the Octa Isle completion date on the DLD register?

30 September 2027, under DLD project 3793, with a construction start of 1 August 2025 (DLD project register via Continental Club, updated 6 October 2026).

Has the Octa Isle Interiors by Missoni handover date been delayed?

No change has been recorded. The Q3 2027 date announced at launch in September 2025 still matches the registered 30 September 2027.

How much is due on handover at Octa Isle?

32% under the main 68/32 plan, or 70% under the 30/70 offer listed for some 2 bedroom units (Tanami Properties).

Sources