Handover date

When is the Muraba Veil handover date?

Updated 11 October 2026 Muraba Veil

Short answer

The DLD register holds a completion date of 31 December 2028 for Muraba Veil, and Muraba targets Q4 2028. The latest DLD inspection, on 28 September 2026, recorded 7.6% construction progress. At the pace of the past year, about 0.58% a month, the tower would not be finished by that date.

Registered completion date (DLD)

31 Dec 2028

DLD register via Continental Club, updated 8 Oct 2026

Latest construction progress

7.6%

DLD inspection, 28 Sep 2026

Developer's stated date

Q4 2028

Muraba, via Continental Club and broker pages

Date at unveiling

Not given

Time Out Dubai, 23 Oct 2024

Muraba Veil handover date: the latest position

The Dubai Land Department (DLD) register holds a completion date of 31 December 2028 for Muraba Veil, the 73 storey tower beside the Dubai Water Canal in Al Wasl. Muraba gives the same target, Q4 2028, and broker pages agree. More on the project: Muraba Veil.

The DLD inspection of 28 September 2026 recorded 7.6%. With 27 months left, about 92% of the work remains. Continental Club’s pace estimate from the past year of inspections is about 0.58% a month, far below what the registered date requires. Construction was registered as starting on 1 December 2024, so 22 of the 49 months in the registered window had passed by the September 2026 inspection.

Muraba Veil handover date by building

Muraba Veil is a single tower, DLD project 3106.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Muraba Veil 7.6% (28 Sep 2026) 31 Dec 2028 Q4 2028 (developer via Continental Club; LuxuryProperty, Christie’s)

The tower is registered as five basements, ground, one podium and 72 floors, with 135 units. Muraba markets 131 residences, and the register’s total includes a few non-residential units. The escrow account is with Commercial Bank of Dubai.

How the Muraba Veil handover date has changed

  • 17 to 23 October 2024: Muraba and RCR Arquitectes unveiled the tower. Time Out Dubai reported that no completion date had been confirmed.
  • 1 December 2024: construction registered as starting, with a registered completion date of 31 December 2028.
  • 2025: broker payment plans set the final 50% for December 2028, and Gulf News reported a December 2028 completion.
  • 16 March 2026: DLD inspection, 5.45%.
  • 18 June 2026: DLD inspection, 7.16%.
  • 17 September 2026: DLD inspection, 7.5%.
  • 28 September 2026: DLD inspection, 7.6%. The register still holds 31 December 2028.

What the Muraba Veil handover date means for payments

Under the 50/50 plan listed by The Foundry, buyers pay 5% on booking, 15% plus the 4% DLD fee 30 days later, and 10% each in September 2025, 2026 and 2027. The other 50% is due on completion. On the 2 bedroom median of AED 13,658,036, that completion payment is about AED 6.83 million.

The construction instalments are fixed by date, so by September 2027 buyers will have paid half the price whatever the progress on site. Only the final 50% moves if completion moves.

What to check before relying on the Muraba Veil date

  1. The completion date and grace period in the SPA, since half the price is tied to completion.
  2. Progress at each new DLD inspection. Inspections have come every one to three months in 2026, so the trend for project 3106 is easy to follow in the DLD project status service.
  3. Funding for the completion payment. About AED 6.83 million on a median 2 bedroom falls due on the completion date set in the SPA, which may differ from the registered 31 December 2028.

Questions buyers also ask

When will Muraba Veil be completed?

The DLD registered completion date is 31 December 2028. Muraba targets Q4 2028. Construction was registered as starting on 1 December 2024.

How far along is Muraba Veil construction?

7.6% at the DLD inspection of 28 September 2026, up from 7.5% on 17 September, 7.16% on 18 June and 5.45% on 16 March 2026.

Has the Muraba Veil handover date been delayed?

No change has been announced. No date was given at the October 2024 unveiling, and December 2028 has been quoted since 2025 by the register, the developer and the press.

How much is due at the Muraba Veil handover?

Half the price. The 50/50 plan puts 50% on completion, set for December 2028 (The Foundry, Christie's).

Sources

  1. Continental Club, Muraba Veil (DLD register) (opens in a new tab)continentalclub.ae · DLD inspection 28 Sep 2026; registry updated 8 Oct 2026
  2. The Foundry, Muraba Veil (opens in a new tab)thefoundryrealty.com · accessed 11 Oct 2026
  3. Christie's International Real Estate Dubai, Muraba Veil (opens in a new tab)christiesrealestatedubai.com · accessed 11 Oct 2026