When is the Mr. C Residences Downtown handover date?
Short answer
The Mr. C Residences Downtown handover date is 27 January 2027, the registered completion date on the Dubai Land Department (DLD) register, and portals list Q1 2027. The DLD inspection of 4 August 2026 recorded the tower 73.23% complete. The original payment schedule set completion for December 2026, so the date has moved about one month, and 27% of the work remained in August with under six months to go.
Registered completion date (DLD)
27 Jan 2027
DLD project register via Continental Club
Latest construction progress
73.23%
DLD inspection, 4 Aug 2026
Original completion in payment schedule
Dec 2026
Mr. C Downtown Dubai sales site; Data Habibi records Q4 2026
Portal date
Q1 2027
Crown Key; JRE; Data Habibi, accessed 11 Oct 2026
Mr. C Residences Downtown handover date: the latest position
Mr. C Residences Downtown is registered for completion on 27 January 2027. That is the date on the Dubai Land Department (DLD) register for project 2476, and portals such as Crown Key and JRE list Q1 2027. More on prices and sizes is on the Mr. C Residences Downtown page.
The DLD inspection of 4 August 2026 recorded 73.23% complete. The project’s own payment schedule had set completion for December 2026, so the registered date is about a month later. About 27% of the work remained in August 2026, with five and a half months left to the registered date.
Mr. C Residences Downtown handover date by building
The project is one tower of 169 apartments in City Walk, Al Wasl.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Mr. C Residences Downtown (one tower, 169 units, DLD project 2476) | 73.23%, 4 Aug 2026 | 27 Jan 2027 | Dec 2026 (original payment schedule); Q1 2027 (Crown Key, JRE, Data Habibi) |
How the Mr. C Residences Downtown handover date has changed
| Date | What happened | Source |
|---|---|---|
| Sep 2021 | Registered construction start. | DLD record via Overit and Data Habibi |
| Jan 2023 | First sales registered with the DLD. | Keyva |
| At launch | Payment schedule sets 60% at completion in December 2026, with stage payments at 60% (December 2025) and 80% (June 2026). | Mr. C Downtown Dubai sales site |
| Jun 2026 | Scheduled date for the 80% construction stage. | Mr. C Downtown Dubai sales site |
| 4 Aug 2026 | DLD inspection: 73.23%. Registered completion date 27 January 2027. | DLD register via Continental Club |
| Oct 2026 | Portals list Q1 2027. Some still show an older DLD figure of 50.1%. | Crown Key; JRE; Overit |
Data Habibi describes the change from Q4 2026 to Q1 2027 as a one month postponement. Progress also trails the payment timetable: the 80% stage was set for June 2026, and the tower was at 73.23% in August.
What the Mr. C Residences Downtown handover date means for payments
The plan puts 40% before completion and 60% at completion. The schedule is 5% at reservation, 15% plus the 4% DLD fee at SPA signing, 10% at 60% construction and 10% at 80% construction. Because the stage payments follow certified progress, the 80% instalment falls due only once the DLD records that level.
The 60% completion payment is about AED 4.86 million on a 2 bedroom at AED 8.1 million, and about AED 7.2 million on a 3 bedroom at the AED 11,969,903 registered on 16 September 2026. With the registered date at 27 January 2027, that payment moves from December 2026 into early 2027.
What to check before relying on the Mr. C Residences Downtown date
- The completion date in the SPA. Early contracts may state December 2026, while the register holds 27 January 2027.
- Whether the 80% stage has been certified. That instalment depends on DLD progress, not a calendar date.
- Funding for the 60% balance. A completion payment of several million dirhams needs mortgage approval or cash in place by early 2027.
- The DLD inspection after August 2026. A figure near 90% by late 2026 would support the January 2027 date.
Questions buyers also ask
What is the Mr. C Residences Downtown completion date?
27 January 2027 on the DLD register for project 2476. Portals list Q1 2027.
Is Mr. C Residences Downtown finished?
No. The DLD inspection of 4 August 2026 recorded 73.23% complete. Construction began in September 2021.
Has the Mr. C Residences Downtown handover date been delayed?
By about a month on paper. The payment schedule set completion in December 2026 and Data Habibi records an original Q4 2026 promise. The register now shows 27 January 2027.
How much is due at the Mr. C Residences Downtown handover?
60% of the price is due at completion. On a 2 bedroom at AED 8.1 million, that is about AED 4.86 million.