When is the Milos by Karma handover date?
Short answer
The Milos by Karma handover date is 1 April 2027, the registered completion date on the Dubai Land Department (DLD) register, and portals list Q2 2027. The latest DLD inspection, on 22 April 2026, recorded the building 0.44% complete, about 20 months after the registered construction start of 1 August 2024. The date has not been revised on the register, but progress at that level leaves almost the whole building to be built.
Registered completion date (DLD)
1 Apr 2027
DLD project register via Continental Club
Latest construction progress
0.44%
DLD inspection, 22 Apr 2026
Portal date
Q2 2027
Property Finder; Augusta Properties, 4 Oct 2026; Propsearch April 2027
Progress in the year to April 2026
+0.42 points
DLD inspections, 14 Apr 2025 to 22 Apr 2026
Milos by Karma handover date: the latest position
Milos by Karma is registered for completion on 1 April 2027. That is the date on the Dubai Land Department (DLD) register. Property Finder and Augusta Properties list Q2 2027, and Propsearch estimates April 2027. More on prices and the payment plan is on the Milos by Karma page.
The latest DLD inspection, on 22 April 2026, recorded 0.44% complete. That was still the newest figure on the register in early October 2026. With construction registered from 1 August 2024, the building had moved less than half of one per cent in 20 months. The registered date has not changed, but no source shows the progress needed to meet it.
Milos by Karma handover date by building
Milos is a single 14 storey building with 195 apartments.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Milos By Karma (one building, 195 units, DLD project 3132) | 0.44%, 22 Apr 2026 | 1 Apr 2027 | Q2 2027 (Property Finder, Augusta); Apr 2027 (Propsearch) |
How the Milos by Karma handover date has changed
The published date has stayed in the second quarter of 2027. The progress figures are the part that has barely moved.
| Date | What happened | Source |
|---|---|---|
| 1 Aug 2024 | Registered construction start on a plot first meant for the cancelled Aurora DRC project. | DLD register via Continental Club; Propsearch |
| 14 Apr 2025 | DLD inspection: 0.02%. | DLD register via Continental Club |
| 11 Feb 2026 | Propsearch estimates handover in April 2027. | Propsearch |
| 22 Apr 2026 | DLD inspection: 0.44%. Registered completion date 1 April 2027. | DLD register via Continental Club |
| Oct 2026 | Portals still list Q2 2027; no newer inspection on the register. | Augusta Properties, 4 Oct 2026; Continental Club, 5 Oct 2026 |
What the Milos by Karma handover date means for payments
The plan is 10% on booking, 40% during construction, 10% on handover and 40% over 60 months after handover (Property Finder; Augusta Properties, 4 October 2026). On a 1 bedroom at the median registered price of AED 948,055, the handover payment is about AED 95,000, and about AED 379,000 follows in monthly instalments of around AED 6,300 for five years.
Because the post-handover period starts at handover, a later completion moves the whole tail of payments later too. How the 40% construction share is billed matters most: if it follows build stages, little of it should have been called by April 2026.
What to check before relying on the Milos by Karma date
- The SPA date and grace period. The SPA, not a portal’s Q2 2027, sets what Karma must deliver and when.
- A fresh DLD inspection. The April 2026 figure of 0.44% was six months old in October 2026. The DLD project status service shows newer inspections when they are filed.
- Escrow payments. The register names First Abu Dhabi Bank as escrow bank for project 3132. Instalments should go only to that account.
- Construction-stage billing. Whether the 40% construction share is due by date or by progress decides how much is paid before work is visible on site.
Questions buyers also ask
What is the Milos by Karma completion date?
1 April 2027 on the DLD register. Portals list Q2 2027 and Propsearch estimates April 2027.
Is construction under way at Milos by Karma?
Barely, on the DLD record. The inspection of 22 April 2026 recorded 0.44% complete, up from 0.02% on 14 April 2025. Construction was registered as starting on 1 August 2024.
Has the Milos by Karma handover date been delayed?
Not officially. The register and portals still show April 2027 or Q2 2027 as of October 2026. No revised date has been published.
How much is due at the Milos by Karma handover?
10% on handover, with a further 40% spread over 60 months afterwards. By handover, 60% of the price has been paid in total.