When is the Mi Casa by London Gate handover date?
Short answer
Mi Casa by London Gate is marketed for handover in Q4 2027, with Property Finder naming 1 December 2027, but its registered completion date with the Dubai Land Department is 26 October 2028. The last DLD inspection on file, on 14 August 2025, recorded 19.09% progress, and no newer reading had been added by the register update of 7 October 2026. The SPA for each unit decides which date applies.
Registered completion date
26 Oct 2028
DLD project register via Continental Club
Latest construction progress
19.09%
DLD inspection, 14 Aug 2025
Developer and portal date
Q4 2027
Property Finder names 1 Dec 2027
Gap between the two dates
About 10 months
1 Dec 2027 to 26 Oct 2028
Mi Casa by London Gate handover date: the latest position
Mi Casa by London Gate is sold with a Q4 2027 handover, and Property Finder gives an expected completion of 1 December 2027. The Dubai Land Department (DLD) register holds a registered completion date of 26 October 2028, about ten months later. Prices, sizes and the payment plan are on the project page: Mi Casa by London Gate.
The progress record is thin. The only DLD inspection on file, dated 14 August 2025, recorded 19.09%, and the register updated on 7 October 2026 still showed it. Impala Real Estate repeats the same 19.09% figure on its page in September 2026.
Mi Casa by London Gate handover date by building
Mi Casa is one building of basement, ground and four floors, registered as DLD project 3647 in JVC District 16.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Mi Casa by London Gate (72 flats, 4 shops) | 19.09% (14 Aug 2025) | 26 Oct 2028 | Q4 2027 (Continental Club, OffplanIndex); 1 Dec 2027 (Property Finder) |
How the Mi Casa by London Gate handover date has changed
| Date | Event | Source |
|---|---|---|
| 1 Apr 2025 | Construction start on the DLD register | DLD via Continental Club |
| 14 Aug 2025 | DLD inspection: 19.09% | DLD via Continental Club |
| 2 Sep 2025 | Construction start according to Property Finder | Property Finder |
| 19 Nov 2025 | Launch with studios from AED 762,000 and a 30/70 plan | Alnair |
| 12 Mar 2026 | Broker listing states Q4 2027 handover | Property Finder (Axis Real Estate listing) |
| 7 Oct 2026 | Register still shows 19.09% and 26 Oct 2028 | DLD via Continental Club |
| 11 Oct 2026 | Property Finder still shows 1 Dec 2027 and marks the project sold out | Property Finder |
Sources disagree on the start of construction, 1 April 2025 on the register and 2 September 2025 on Property Finder. The marketed Q4 2027 date has not moved since launch. The registered date of 26 October 2028 gives the developer more time than its own sales material.
What the Mi Casa by London Gate handover date means for payments
Under the 30/70 plan, buyers pay 20% on booking and 10% in four instalments during construction, so 30% is paid before the keys. The remaining 70% is due on handover at 100% completion, with nothing after. If handover lands in December 2027, that payment falls about two years after the November 2025 launch. If it follows the registered date, it moves to late 2028. For buyers funding the 70% with a mortgage, the bank valuation happens near the actual handover, not the marketed date.
What to check before relying on the Mi Casa by London Gate date
- The completion date written in the SPA, and whether it is Q4 2027 or the registered 26 October 2028, plus the grace period.
- A current DLD inspection. The only reading is from August 2025, before the sales launch.
- The trigger for the four construction instalments, since they are listed only as “during construction”.
Questions buyers also ask
When will Mi Casa by London Gate be completed?
London Gate and the portals give Q4 2027, and Property Finder shows an expected completion of 1 December 2027. The DLD registered completion date is 26 October 2028.
Why does the DLD date differ from the Q4 2027 handover?
The DLD register holds the completion date filed for the project, 26 October 2028, while Q4 2027 is the date used in the sales material. Neither source explains the gap. The date in the SPA is the one a buyer can enforce.
How far along is Mi Casa by London Gate?
19.09% at the DLD inspection of 14 August 2025, the only reading on file. The register updated on 7 October 2026 still showed that figure.
How much is due on handover at Mi Casa by London Gate?
70% of the price, under the 30/70 plan. The other 30% is 20% on booking and 10% during construction.