Handover date

When is the Mi Casa by London Gate handover date?

Updated 11 October 2026 Mi Casa by London Gate

Short answer

Mi Casa by London Gate is marketed for handover in Q4 2027, with Property Finder naming 1 December 2027, but its registered completion date with the Dubai Land Department is 26 October 2028. The last DLD inspection on file, on 14 August 2025, recorded 19.09% progress, and no newer reading had been added by the register update of 7 October 2026. The SPA for each unit decides which date applies.

Registered completion date

26 Oct 2028

DLD project register via Continental Club

Latest construction progress

19.09%

DLD inspection, 14 Aug 2025

Developer and portal date

Q4 2027

Property Finder names 1 Dec 2027

Gap between the two dates

About 10 months

1 Dec 2027 to 26 Oct 2028

Mi Casa by London Gate handover date: the latest position

Mi Casa by London Gate is sold with a Q4 2027 handover, and Property Finder gives an expected completion of 1 December 2027. The Dubai Land Department (DLD) register holds a registered completion date of 26 October 2028, about ten months later. Prices, sizes and the payment plan are on the project page: Mi Casa by London Gate.

The progress record is thin. The only DLD inspection on file, dated 14 August 2025, recorded 19.09%, and the register updated on 7 October 2026 still showed it. Impala Real Estate repeats the same 19.09% figure on its page in September 2026.

Mi Casa by London Gate handover date by building

Mi Casa is one building of basement, ground and four floors, registered as DLD project 3647 in JVC District 16.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Mi Casa by London Gate (72 flats, 4 shops) 19.09% (14 Aug 2025) 26 Oct 2028 Q4 2027 (Continental Club, OffplanIndex); 1 Dec 2027 (Property Finder)

How the Mi Casa by London Gate handover date has changed

Date Event Source
1 Apr 2025 Construction start on the DLD register DLD via Continental Club
14 Aug 2025 DLD inspection: 19.09% DLD via Continental Club
2 Sep 2025 Construction start according to Property Finder Property Finder
19 Nov 2025 Launch with studios from AED 762,000 and a 30/70 plan Alnair
12 Mar 2026 Broker listing states Q4 2027 handover Property Finder (Axis Real Estate listing)
7 Oct 2026 Register still shows 19.09% and 26 Oct 2028 DLD via Continental Club
11 Oct 2026 Property Finder still shows 1 Dec 2027 and marks the project sold out Property Finder

Sources disagree on the start of construction, 1 April 2025 on the register and 2 September 2025 on Property Finder. The marketed Q4 2027 date has not moved since launch. The registered date of 26 October 2028 gives the developer more time than its own sales material.

What the Mi Casa by London Gate handover date means for payments

Under the 30/70 plan, buyers pay 20% on booking and 10% in four instalments during construction, so 30% is paid before the keys. The remaining 70% is due on handover at 100% completion, with nothing after. If handover lands in December 2027, that payment falls about two years after the November 2025 launch. If it follows the registered date, it moves to late 2028. For buyers funding the 70% with a mortgage, the bank valuation happens near the actual handover, not the marketed date.

What to check before relying on the Mi Casa by London Gate date

  1. The completion date written in the SPA, and whether it is Q4 2027 or the registered 26 October 2028, plus the grace period.
  2. A current DLD inspection. The only reading is from August 2025, before the sales launch.
  3. The trigger for the four construction instalments, since they are listed only as “during construction”.

Questions buyers also ask

When will Mi Casa by London Gate be completed?

London Gate and the portals give Q4 2027, and Property Finder shows an expected completion of 1 December 2027. The DLD registered completion date is 26 October 2028.

Why does the DLD date differ from the Q4 2027 handover?

The DLD register holds the completion date filed for the project, 26 October 2028, while Q4 2027 is the date used in the sales material. Neither source explains the gap. The date in the SPA is the one a buyer can enforce.

How far along is Mi Casa by London Gate?

19.09% at the DLD inspection of 14 August 2025, the only reading on file. The register updated on 7 October 2026 still showed that figure.

How much is due on handover at Mi Casa by London Gate?

70% of the price, under the 30/70 plan. The other 30% is 20% on booking and 10% during construction.

Sources

  1. DLD project register via Continental Club, Mi Casa by London Gate (opens in a new tab)continentalclub.ae · inspection 14 Aug 2025, registry updated 7 Oct 2026
  2. Property Finder, Mi Casa project page (opens in a new tab)propertyfinder.ae · accessed 11 Oct 2026
  3. Impala Real Estate, Mi Casa (opens in a new tab)impalarealestate.com · accessed 11 Oct 2026
  4. OffplanIndex, Mi Casa (opens in a new tab)offplanindex.com · accessed 11 Oct 2026