Handover date

When is the Marea Residences handover date?

Updated 11 October 2026 Marea Residences

Short answer

The DLD register holds a completion date of 20 June 2027 for Marea Residences on Dubai Islands, while Sharafi Development's website says Q3 2027. The latest DLD inspection, on 10 June 2026, recorded 5.33% construction progress. With that progress a year before the registered date, the developer's later quarter, or later, is more likely than June 2027.

Registered completion date (DLD)

20 Jun 2027

DLD register via Continental Club, updated 8 Oct 2026

Latest construction progress

5.33%

DLD inspection, 10 Jun 2026

Developer's stated date

Q3 2027

Sharafi Development website, accessed 11 Oct 2026

Date in June 2026 launch release

Q4 2027

Zawya, 2 Jun 2026

Marea Residences handover date: the latest position

The Dubai Land Department (DLD) register holds a completion date of 20 June 2027 for Marea, the register name for the 68 unit building by Sharafi Development on Dubai Islands. Sharafi’s own website gives Q3 2027, and its launch release of 2 June 2026 gave Q4 2027. More on the project: Marea Residences.

Progress makes the register date unlikely. The last DLD inspection, on 10 June 2026, recorded 5.33%, leaving almost the whole building to be built in about 12 months. Continental Club’s pace estimate, based on the past year of inspections, is about 0.5% a month. Construction was registered as starting on 20 July 2025, so the registered date allowed about 23 months for a 13 storey building.

Marea Residences handover date by building

Marea is a single building, registered as DLD project 3879.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Marea 5.33% (10 Jun 2026) 20 Jun 2027 Q3 2027 (Sharafi website, JRE, ezre.ae); Q4 2027 (Zawya release, 2 Jun 2026)

The building is planned as ground, two parking levels, 12 residential floors and a roof, with 68 units in the register and 67 on JRE.

How the Marea Residences handover date has changed

  • 20 July 2025: construction registered as starting, with a registered completion date of 20 June 2027.
  • 4 August 2025: first DLD inspection, 0%.
  • 16 December 2025: first DLD sale recorded, a 2 bedroom unit at AED 3,312,939.
  • 4 February 2026: DLD inspection, 3.52%.
  • 17 May 2026: Sharafi Development announced the formal launch (Zawya, as linked from the developer’s site).
  • 2 June 2026: the launch release, carried by Zawya and Gulf Construction Online, gave a Q4 2027 handover.
  • 10 June 2026: DLD inspection, 5.33%.
  • October 2026: the developer’s website and broker pages show Q3 2027. The register still holds 20 June 2027.

What the Marea Residences handover date means for payments

Under the 40/30/30 plan described by Gulf News and OPR, 10% is paid on booking and 30% during construction. A further 30% falls due on handover, and the last 30% is paid after handover as 5% every four months over two years. On the AED 2,749,440 starting price, the handover payment is about AED 824,832 (ezre.ae).

Because a large share is tied to handover, a later completion pushes back both the handover payment and the start of the two year post-handover schedule.

What to check before relying on the Marea Residences date

  1. The SPA date and grace period. The register, the website and the launch release give three different quarters.
  2. A newer DLD inspection. The June 2026 figure of 5.33% is the latest in the register. The DLD project status service shows any later reading for project 3879.
  3. Which payment plan the unit was sold on. Sharafi’s June 2026 release also mentioned a 30/70 plan and a 50/50 post-handover option, which change how much is due at the keys.

Questions buyers also ask

When will Marea Residences be completed?

The DLD registered completion date is 20 June 2027. Sharafi Development's website says Q3 2027. Construction was registered as starting on 20 July 2025 and was 5.33% complete on 10 June 2026.

Is the Marea Residences handover in Q3 or Q4 2027?

Sources differ. The developer's website and most broker pages say Q3 2027. The launch release of 2 June 2026 said Q4 2027. The register says 20 June 2027, which is in Q2.

Has the Marea Residences handover date been delayed?

No formal delay has been announced. The quarter quoted has moved from Q2 2027, held in the register and repeated by Continental Club, to Q3 and Q4 2027 in developer material.

How far along is Marea Residences construction?

5.33% at the DLD inspection of 10 June 2026, up from 3.52% on 4 February 2026 and 0% on 4 August 2025. No newer inspection was in the register as updated on 8 October 2026.

Sources

  1. Continental Club, Marea (DLD register) (opens in a new tab)continentalclub.ae · DLD inspection 10 Jun 2026; registry updated 8 Oct 2026
  2. Sharafi Development, Marea Residences (opens in a new tab)sharafidevelopment.com · accessed 11 Oct 2026
Request a Unit Review