
When is the MAG 777 handover date?
Short answer
MAG 777's registered completion date was 15 January 2026, and it has passed without the tower being finished. A DLD inspection on 30 July 2026 recorded it 67.37% complete, up from 58.74% in April 2026. Portals now list Q3 2026, but MAG has not published a revised date, and at the recorded pace completion would run into 2027.
Registered completion date (DLD)
15 Jan 2026 (passed)
DLD project register via Continental Club
Latest construction progress
67.37%
DLD inspection, 30 Jul 2026
Developer's launch promise
End of 2025
MAG via Middle East Construction News, 8 Oct 2024
Portal estimate now
Q3 2026
Dubainary and dxbpropy, accessed 11 Oct 2026
MAG 777 handover date: the latest position
MAG 777’s registered completion date, 15 January 2026, has passed. The DLD register still lists the Dubai Sports City tower as active, and its latest inspection, on 30 July 2026, recorded it 67.37% complete. More on prices, sizes and payment plans is on the MAG 777 project page.
Portals now show Q3 2026, but MAG has not published a revised date and the register has not been updated. Daily snapshots of the register on Dubai Handover show the figure unchanged at 67.4% through 8 October 2026, meaning no newer inspection had been recorded by then.
MAG 777 handover date by building
MAG 777 is a single 22 storey building with 266 units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| MAG 777 (DLD project 3193) | 67.37%, 30 Jul 2026 | 15 Jan 2026 (passed) | End of 2025 at launch; Q3 2026 on portals |
The DLD register also lists a second MAG project, Mag 888, but that is a separate project in Downtown Dubai (DLD project 3542) with a planned completion of 31 March 2028. Freehold Solutions reports it as listed cancelled in the register. It is not a phase of MAG 777.
How the MAG 777 handover date has changed
- 4 October 2024: Project registered with DLD, completion date 15 January 2026.
- 8 October 2024: Launch. MAG says the tower is already 60% complete and will be ready by the end of 2025 (Middle East Construction News).
- 1 November 2024: Registered construction start.
- 15 January 2026: Registered completion date passes.
- 2 April 2026: DLD inspection at 58.74%.
- 30 July 2026: DLD inspection at 67.37%.
- October 2026: Portals list Q3 2026; no revised date from MAG.
The launch claim of 60% complete and the DLD figure of 58.74% in April 2026 do not match. At the April to July 2026 pace of about 2.2 points a month, the remaining 33 points would take about 15 months, which would put completion in late 2027.
Sales have continued after the registered date passed. Studios registered at AED 778,560 and AED 813,200 on 21 September 2026, and Continental Club counts only one resale among 144 sales since 2024, so most buyers are still waiting on their first handover date.
What the MAG 777 handover date means for payments
Most of the price is due on handover. Continental Club lists 20% down payment, 10% during construction and 70% on handover; fäm Properties lists 20%, 30% and 50% on handover. On a studio at the median registered price of AED 786,780, that is between about AED 393,000 and AED 551,000 due at handover. The delay leaves that sum unpaid for longer rather than changing it.
What to check before relying on the MAG 777 date
- The completion date and any grace period in the SPA, since the January 2026 registered date is now about nine months past.
- Any amended SPA or notice from MAG setting a new completion date.
- The next DLD inspection for project 3193. None had been recorded after 30 July 2026 as of 8 October 2026.
Questions buyers also ask
Is MAG 777 finished?
No. The tower was 67.37% complete at the DLD inspection on 30 July 2026, and the register still lists it as active, not completed (DLD register via Continental Club, updated 5 Oct 2026).
When will MAG 777 be completed?
No firm date is published. The registered date of 15 January 2026 has passed, and portals show Q3 2026. Between April and July 2026 the tower gained about 2.2 points a month; at that pace the last 33 points would take about 15 months.
Has the MAG 777 handover date been delayed?
Yes. MAG said at launch in October 2024 that the tower would be ready by the end of 2025, and the DLD register set 15 January 2026. Both dates have passed.
How much is due at MAG 777 handover?
Between 50% and 70% of the price, depending on the plan. Continental Club lists 70% on handover; fäm Properties lists 50%.

