When is the Lunaya handover date?
Short answer
The DLD register holds a completion date of 31 March 2029 for Lunaya, and Zaya gives Q1 2029, with handover phased from that quarter. The latest DLD inspection, on 30 June 2026, recorded 1.31% progress across the 564 home project. Because handover is phased, some homes may complete after the registered date, and portals quoting Q2 or December 2029 do not match the DLD record.
Registered completion date
31 Mar 2029
DLD project register via Continental Club
Latest DLD construction progress
1.31%
DLD inspection, 30 Jun 2026
Developer's stated date
Q1 2029, phased
Zaya, via M&M Real Estate, Sep 2026
Portal estimates
Q2 to Dec 2029
Ezre and Projects Scout, Oct 2026
Lunaya handover date: the latest position
The DLD register holds a completion date of 31 March 2029 for Lunaya, and Zaya gives Q1 2029, with handover phased from that quarter. Full project details are on the Lunaya page.
Works are at an early stage. The DLD inspection on 30 June 2026 recorded 1.31%, three months after the registered start on 1 April 2026. The project runs on a 36 month registered schedule from start to completion. That leaves about 33 months from the June inspection for the lagoons, community facilities and 564 homes, which is why the pace shown at the next inspections matters more than the low starting figure.
Lunaya handover date by building
The DLD record covers the 564 villas and townhouses as one project. Zaya has not published separate dates by cluster, although it describes handover as phased.
| Phase | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Lunaya villas and townhouses (564 units, DLD project 4456) | 1.31% (30 Jun 2026) | 31 Mar 2029 | Q1 2029, phased (Zaya via M&M); March 2029 (Property Finder); Q2 2029 (Ezre); Dec 2029 (Projects Scout) |
| Lunaya apartment buildings | Not on this record | Not on this record | 2029 (Insider) |
How the Lunaya handover date has changed
| Date | Event | Source |
|---|---|---|
| 1 Apr 2026 | Bookings open; registered project start | Property Finder, DLD register |
| 9 Apr 2026 | First DLD inspection, about 0.6% | DLD register via Continental Club |
| Apr to May 2026 | Most of the 564 homes sold | Certified Poor, Insider |
| 30 Jun 2026 | DLD inspection: 1.31% | DLD register via Continental Club |
| Sep 2026 | Zaya gives handover phased from Q1 2029 | M&M Real Estate |
| Sep 2026 | Register still holds 31 March 2029 | Continental Club |
The developer and DLD dates have not changed since launch. The later dates on some portals are listing estimates, not revisions by Zaya.
What the Lunaya handover date means for payments
Zaya’s brochure gives a 40/60 plan: 40% during construction and 60% on handover. Continental Club lists 35/65. Either way, most of the price is tied to completion. On the median DLD sale of AED 6,575,000, a 60% handover payment is about AED 3.95 million. If a home’s phase completes after 31 March 2029, that payment falls later too.
What to check before relying on the Lunaya date
- The phase and its completion date in the SPA, since Zaya describes handover as phased.
- Whether the home is a villa or an apartment. The apartment buildings are not covered by the 564 home DLD record or its 31 March 2029 date.
- Lagoon and amenity timing. Zaya’s 900,000 sq ft lagoons are part of the same master plan; the SPA or brochure states whether they are due at the same time as the homes.
Questions buyers also ask
What is the Lunaya completion date?
The DLD register holds 31 March 2029 for Lunaya (DLD project 4456, 564 units), via Continental Club with the registry updated 25 September 2026.
Will all Lunaya homes be handed over at the same time?
Not necessarily. Zaya describes handover as phased from Q1 2029 (M&M Real Estate, Sep 2026). The DLD record holds one completion date, 31 March 2029, for all 564 homes, so the SPA for each home is the place to confirm its date.
How far along is Lunaya?
1.31% at the DLD inspection on 30 June 2026, up from about 0.6% on 9 April 2026. Construction and bookings both started on 1 April 2026.
When will the Lunaya apartments be ready?
The apartment buildings launched after the villas are not part of the 564 home DLD record. Insider reports a 2029 handover for them and a 25/75 payment plan. Their completion dates are not on the Lunaya DLD record.