
When is the Lumena by Omniyat handover date?
Short answer
The Lumena by Omniyat handover date is Q4 2029, and the registered completion date on the Dubai Land Department (DLD) register is 30 December 2029. The DLD recorded 0% at its inspection of 25 March 2026, and Omniyat said on 30 August 2026 that enabling works had been awarded. Propsearch reports a Q3 2029 target at launch in June 2025, so the date has already moved back one quarter.
Registered completion date
30 Dec 2029
DLD register via Mitchells, 4 Oct 2026
Latest construction progress
0%
DLD inspection, 25 Mar 2026
Developer's stated date
Q4 2029
Omniyat, 25 Aug 2025 and project page, Oct 2026
Target at launch
Q3 2029
Propsearch, June 2025 entry
Lumena by Omniyat handover date: the latest position
Omniyat gives Q4 2029 as the completion date for Lumena, its office tower at the gateway to Business Bay. The Dubai Land Department (DLD) register agrees, with a registered completion date of 30 December 2029 for project 3758. More on the offices, prices and payment plan is on the Lumena by Omniyat project page.
The tower is still at the preparatory stage. The DLD inspection of 25 March 2026 recorded 0%, the same as in May 2025. Omniyat’s update of 30 August 2026 reported enabling works awarded, and the register’s construction start is 31 December 2025, which leaves four years for a 260 metre tower.
Lumena by Omniyat handover date by building
Omniyat now markets two towers under the Lumena name. This table covers both, though only Lumena has a published register entry with dates.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Lumena (project 3758) | 0% (25 Mar 2026) | 30 Dec 2029 | Q4 2029 (Omniyat); Q4 2029 (Propsearch) |
| Lumena North | Not published | Not published | Test piling complete (Omniyat, 30 Aug 2026) |
How the Lumena by Omniyat handover date has changed
| Date | Event | Source |
|---|---|---|
| 14 May 2025 | DLD inspection before launch records 0%. | DLD register via Continental Club |
| 18 Jun 2025 | Omniyat unveils Lumena; Propsearch records a target of Q3 2029. | Propsearch |
| 25 Aug 2025 | Omniyat announces a sell-out at AED 3.4 billion and gives completion in Q4 2029. | Omniyat |
| 31 Dec 2025 | Registered construction start. | DLD register via Mitchells |
| 16 Jan 2026 | Omniyat says enabling works, shoring, piling and excavation will advance in 2026. | Omniyat |
| 25 Mar 2026 | DLD inspection records 0%. | DLD register via Mitchells |
| 30 Aug 2026 | Enabling works awarded; RTA relocation works for the Metro Gold Line under way. | Al Masdar Al Aqaari |
The date moved by one quarter between launch and the sell-out announcement, and has stayed at Q4 2029 since.
What the Lumena by Omniyat handover date means for payments
The launch plan was 5% on booking, 45% during construction and 50% on handover (Propsearch). On an office registered at AED 18.4 million on 18 September 2026, the handover payment would be about AED 9.2 million, due at the end of 2029 if the date holds. Since main works had not started by August 2026, the timing of the 45% construction stage matters as much as the final date.
What to check before relying on the Lumena by Omniyat date
- Whether the SPA says Q3 or Q4 2029, as early buyers may hold the launch target.
- Which tower the unit is in, Lumena or Lumena North, since only Lumena has a published register date.
- The first DLD inspection above 0%, which will show when main construction is under way.
- Any effect of the Metro Gold Line works on site access and the programme.
Questions buyers also ask
Has construction started at Lumena by Omniyat?
Only preparatory work. The register's construction start is 31 December 2025. Omniyat said in August 2026 that enabling works had been awarded and that RTA relocation works for the Dubai Metro Gold Line were under way. DLD inspections recorded 0% in May 2025 and March 2026.
What is the Lumena by Omniyat completion date?
30 December 2029 on the DLD register for project 3758 (Continental Club and Mitchells, October 2026).
Has the Lumena by Omniyat handover date been delayed?
Slightly. Propsearch records a Q3 2029 completion target at launch in June 2025; Omniyat's sell-out release in August 2025 and its project page give Q4 2029, matching the register.
Is Lumena North on the same timeline?
Omniyat has not published a separate date for Lumena North. In August 2026 it reported test piling complete there and enabling works awarded for both towers.
