When is the Lazord by Lapis handover date?
Short answer
Lazord by Lapis has a registered completion date of 31 December 2026, matching the December 2026 handover Lapis Properties has marketed since 2024. The last DLD inspection, on 3 September 2026, recorded the building 27.64% complete. With about 72% of the work left and under four months to go, the registered date is very unlikely to hold, although no new date has been published.
Registered completion date (DLD)
31 Dec 2026
DLD register via Continental Club
Latest construction progress
27.64%
DLD inspection, 3 Sep 2026
Developer's stated date
December 2026
Lapis Properties, 5 Jun 2025
Progress at the same point a year earlier
2.4%
DLD inspection, 8 Sep 2025
Lazord by Lapis handover date: the latest position
Lazord by Lapis is registered with the Dubai Land Department (DLD) for completion on 31 December 2026. Lapis Properties and Property Finder give the same December 2026 handover. Full project details are on the Lazord by Lapis page.
The building is well behind that date. DLD inspectors recorded it 27.64% complete on 3 September 2026, leaving about 72% of the work for the last four months of 2026. No revised date had been published by the developer or entered in the register by 26 September 2026, when Continental Club last updated its copy.
Lazord by Lapis handover date by building
Lazord is a single building of 313 registered units in Majan, Dubailand, registered as DLD project 3209.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Lazord by LAPIS | 27.64% (3 Sep 2026) | 31 Dec 2026 | December 2026 (Lapis Properties; Property Finder) |
Lapis said in June 2025 that it was preparing a second phase of Lazord. No second phase appears in the DLD register.
How the Lazord by Lapis handover date has changed
| Date | What happened | Source |
|---|---|---|
| 31 Jul 2024 | First DLD inspection, 0% | DLD register via Dubai Data |
| 9 Aug 2024 | Marketed with an anticipated completion of December 2026 | InvestInDXB |
| 3 Sep 2024 | Registered with the DLD | DLD register via Dubai Data |
| 1 Jan 2025 | Registered construction start | DLD register |
| 5 Jun 2025 | Lapis repeats a December 2026 handover | Lapis Properties |
| 8 Sep 2025 | 2.4% complete | DLD register |
| 30 Apr 2026 | 13.1% complete | DLD register |
| 3 Sep 2026 | 27.64% complete, date still 31 Dec 2026 | DLD register via Continental Club |
The date itself has not changed. What has changed is how far the construction figure trails it: a year before the registered date, the building was 2.4% complete.
What the Lazord by Lapis handover date means for payments
Under the 20/54/10/16 plan Lapis described in June 2025, 10% of the price is due on handover and 16% after it. Continental Club lists a version with 24% after handover at 1% a month. If handover moves into 2027 or later, the handover payment and the start of the post-handover instalments move with it. Instalments linked to construction progress also depend on the building reaching each stage.
What to check before relying on the Lazord by Lapis date
- The completion date and grace period in the SPA, since the registered 31 December 2026 looks out of reach at current progress.
- The next DLD inspection figure, which will show whether the pace recorded between April and September 2026 has held.
- Which payment plan version is in the contract, because the share due after handover ranges from 16% to 24% across published versions.
Questions buyers also ask
When will Lazord by Lapis be completed?
The registered completion date is 31 December 2026. At 27.64% complete on 3 September 2026, the building would need far faster progress than any recorded so far to finish by then.
Has the Lazord by Lapis handover date been delayed?
Not officially. The DLD register and Lapis Properties both still show December 2026. The gap is between that date and the construction progress, not between two published dates.
Is Lazord by Lapis finished?
No. The DLD recorded it 27.64% complete on 3 September 2026, up from 13.1% on 30 April 2026.
How fast is Lazord by Lapis being built?
Progress rose 14.6 points between 30 April and 3 September 2026, about 3.6 points a month. Before that it moved more slowly, from 0.2% in May 2025 to 13.1% in April 2026 (DLD register via Dubai Data).