Handover date

When is the J-Haus Residences handover date?

Updated 11 October 2026 J-Haus Residences

Short answer

J-Haus Residences has a registered completion date of 30 June 2027 with the Dubai Land Department (DLD), and the developer markets it for Q2 2027. The only DLD inspection on the public register, dated 27 May 2025, recorded 56.68% complete. That figure is more than 16 months old and predates the registered construction start of 1 November 2025, so current progress is not publicly confirmed.

Registered completion date (DLD)

30 Jun 2027

DLD register via Continental Club, project 3763

Construction progress

56.68%

DLD inspection, 27 May 2025 (only published figure)

Developer's stated date

Q2 2027

Property Finder; Propsearch

Portal expected completion

1 Jun 2027

Property Finder, accessed 11 Oct 2026

J-Haus Residences handover date: the latest position

J-Haus Residences has a registered completion date of 30 June 2027 on the DLD project register, and Hirat Real Estate Development markets it for Q2 2027. Property Finder gives 1 June 2027 as the expected completion. Sizes, prices and the payment plans are on the J-Haus Residences page.

The only published DLD inspection, dated 27 May 2025, recorded 56.68% complete. The register also gives a construction start of 1 November 2025, after that inspection, and no newer inspection had been published by 11 October 2026. The building’s current stage is therefore not confirmed by DLD.

J-Haus Residences handover date by building

J-Haus is one low-rise building of two basements, a ground floor and four upper floors, with 128 apartments, registered as a single DLD project. The register names the developer as JVC Hirat Real Estate and the area as Al Barsha South Fourth, the land registry name for JVC.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
J-Haus Residences (project 3763) 56.68% (27 May 2025) 30 Jun 2027 Q2 2027 (Propsearch); 1 Jun 2027 (Property Finder)

How the J-Haus Residences handover date has changed

Date Event Source
27 May 2025 DLD inspection records 56.68% DLD register via Continental Club
May 2025 Propsearch first traces the project; estimated completion Q2 2027 Propsearch
17 Sep 2025 Construction start shown by Property Finder Property Finder
13 Oct 2025 Hirat briefs brokers on the project Harbor Real Estate
1 Nov 2025 Registered construction start DLD register via Continental Club
Jan 2026 Listing gives handover as June 2027 Property Finder listing
5 Oct 2026 Register still shows 30 Jun 2027 Continental Club

The date has stayed at Q2 2027 throughout. The open question is not the stated date but the lack of a recent inspection to show whether the building is on course for it.

What the J-Haus Residences handover date means for payments

The plans quoted by brokers put most of the price after handover. Tanami Properties lists 10% on booking, 30% during construction and 60% within 120 months after handover. A Property Finder listing from January 2026 shows 10% on booking, 10% after one month, 10% after six months, 10% on handover in June 2027 and 60% over 5 or 10 years after that. If handover moves, the start of those post-handover instalments moves with it.

What to check before relying on the J-Haus Residences date

  1. A current progress figure. DLD’s project status service may show an inspection newer than May 2025.
  2. Which payment plan the SPA uses, and the date the post-handover instalments begin.
  3. The completion date and grace period in the SPA, against the registered 30 June 2027.

Questions buyers also ask

What is the J-Haus Residences completion date?

30 June 2027 on the DLD register for project 3763 (DLD project register via Continental Club, updated 5 October 2026).

How far has construction at J-Haus Residences progressed?

The only published DLD inspection, on 27 May 2025, recorded 56.68%. No later inspection had been published by 11 October 2026.

Has the J-Haus Residences handover date been delayed?

No change has been published. Q2 2027 has been the marketed date since brokers first listed the project in 2025, and the registered date is 30 June 2027.

When does the post-handover payment start at J-Haus Residences?

After handover, which is set for June 2027. Broker plans spread up to 60% of the price over 5 to 10 years after that date (Tanami Properties; Property Finder listing, January 2026).