When is the Golf Grove by Regent handover date?
Short answer
Golf Grove by Regent has a registered completion date of 2 January 2028 in the Dubai Land Department project register, while Regent's own project page still shows Q2 2027. A DLD inspection on 10 June 2026 put construction at 8.74%. Regent promised handover in June 2027 when it broke ground in July 2025, so the registered date is about seven months later than that promise.
Registered completion date (DLD)
2 Jan 2028
DLD project register via Continental Club, registry updated 4 Oct 2026
Latest construction progress
8.74%
DLD inspection, 10 Jun 2026
Developer's stated date
Q2 2027
Regent Developments project page, accessed 11 Oct 2026
Date promised at groundbreaking
June 2027
Khaleej Times, 25 Jul 2025
Golf Grove by Regent handover date: the latest position
The Dubai Land Department (DLD) project register lists Golf Grove By Regent, project number 3245, with a registered completion date of 2 January 2028. The latest DLD inspection, on 10 June 2026, recorded the building at 8.74% complete. Full project details are on the Golf Grove by Regent page.
Regent Developments has not updated its public date. Its project page still shows an anticipated handover of Q2 2027, the same target it gave at groundbreaking in July 2025. Portals now show Q1 2028, closer to the registered date.
Golf Grove by Regent handover date by building
Golf Grove is a single building of 98 apartments: 56 studios and 42 one bedrooms, according to the DLD register.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Golf Grove by Regent (98 units) | 8.74% (10 Jun 2026) | 2 Jan 2028 | Q2 2027 (Regent, accessed 11 Oct 2026); Q1 2028 (Bayut listing) |
The progress figure rose by about 8.3 points between the inspections of 11 November 2025 and 10 June 2026 (DLD project register via Continental Club, registry updated 4 October 2026). Construction is registered as starting on 2 January 2025.
How the Golf Grove by Regent handover date has changed
| Date | What was stated | Source |
|---|---|---|
| Aug 2024 | Project first appears; estimated start January 2025 | Propsearch |
| 2 Jan 2025 | Registered construction start | DLD register via Continental Club |
| May 2025 | Fact sheet published; handover Q2 2027 | Regent fact sheet, Bayut listing |
| 18 to 25 Jul 2025 | Groundbreaking; 80% sold; handover planned for June 2027 | Regent on LinkedIn, Khaleej Times |
| 10 Jun 2026 | DLD inspection at 8.74% | DLD register via Continental Club |
| Oct 2026 | Registered completion 2 January 2028; Regent page still Q2 2027 | DLD register via Continental Club; Regent |
Regent has not announced a new date. The gap between Q2 2027 and the registered 2 January 2028 is about seven months. With 8.74% built in June 2026, meeting the registered date would require the remaining 91% within about 19 months.
What the Golf Grove by Regent handover date means for payments
Regent’s fact sheet sets out 10% on booking, 10% on signing the SPA, 40% during construction and 40% on handover. The construction share is split into four instalments of 10%, 5%, 5% and 10%, set on dates a few months apart rather than on progress milestones, according to broker listings of the plan. That means buyers may have paid most of the 60% pre-handover share well before the building is close to finished. The final 40% is due at completion, so a later handover also pushes back the largest single payment and any mortgage needed for it.
What to check before relying on the Golf Grove by Regent date
- The completion date in the SPA. Contracts signed in 2025 may state Q2 2027, which is earlier than the registered date. The grace period in the SPA sets when a delay claim can start.
- Whether construction instalments are dated or tied to progress. Dated instalments fall due regardless of how far the building has risen.
- The next DLD inspection. A reading well above 8.74% would support a 2027 or early 2028 finish; a small rise would point later.
- Resale terms. Only one of 88 registered sales was a resale by October 2026 (Continental Club). A resale buyer takes on the 40% handover payment.
Questions buyers also ask
What is the Golf Grove by Regent completion date?
The registered completion date is 2 January 2028 (DLD project register via Continental Club, registry updated 4 Oct 2026). Regent's project page still shows Q2 2027.
Has the Golf Grove by Regent handover date been delayed?
The target has moved later. At groundbreaking in July 2025 Regent said handover would come in June 2027 (Khaleej Times, 25 Jul 2025). The DLD register now carries 2 January 2028, and portals such as Bayut list Q1 2028.
Is Golf Grove by Regent finished?
No. The building was 8.74% complete at the DLD inspection of 10 June 2026, about 17 months after the registered construction start of 2 January 2025.
How much is due on handover at Golf Grove by Regent?
Regent's fact sheet puts 40% of the price on handover, after 10% on booking, 10% on signing the SPA and 40% during construction. There is no post-handover plan.