Handover date

When is the Fashionz by Danube handover date?

Updated 6 October 2026 Fashionz by Danube

Short answer

Danube's main project page gives July 2027 as the Fashionz by Danube handover date, while the FAQ on the same page still shows July 2026. The Dubai Land Department (DLD) inspection of 10 September 2026 recorded 40.00%, and Danube's own inspection on 31 August 2026 put the tower at 45%. The DLD register holds no completion date, so the date in each buyer's SPA is the only contractual reference.

Registered completion date (DLD)

Not on the register

DLD register, project 2640, via Mitchells and Continental Club, accessed 6 Oct 2026

Latest construction progress

40.00%

DLD inspection, 10 Sep 2026; Danube reports 45% at 31 Aug 2026

Developer's stated date

Jul 2027

Danube main project page; its FAQ still says July 2026 (accessed 6 Oct 2026)

Date at launch

Jan 2027

Zawya Projects, quoted by Danube, Apr 2023

Fashionz by Danube handover date: the latest position

Danube’s main project page gives July 2027 as the completion date for Fashionz by Danube in Jumeirah Village Triangle, while the FAQ on the same page still says July 2026. The DLD register, which files the tower as Fashionz 1 By Danube, project number 2640, holds no completion date. The DLD inspection of 10 September 2026 recorded 40.00%, and Danube’s own inspection on 31 August 2026 recorded 45%. Prices and unit sizes are on the Fashionz by Danube page.

On 30 July 2026 Danube named Fashionz among 11 projects due for handover within 12 months, which matches July 2027 (Gulf News). The two progress figures come from different inspections ten days apart and use different methods, so they do not match.

Fashionz by Danube handover date by building

Fashionz is a single tower. The DLD records basement, ground, four podium levels, 52 floors and a roof, with 788 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Fashionz 1 By Danube (single tower) 40.00%, 10 Sep 2026. Danube: 45%, 31 Aug 2026 None on register Jul 2027 (Danube main page); Jul 2026 (Danube FAQ); Q3 2026 (Continental Club, developer supplied)

On 31 August 2026 the 22nd floor slab was being cast, blockwork had reached the 17th floor and plastering had started on the 6th and 7th floors (Danube).

How the Fashionz by Danube handover date has changed

Date What happened Source
25 Apr 2023 Launch with prices from AED 850,000. Completion expected by January 2027. Khaleej Times; Zawya Projects quoted by Danube
2 Jun 2023 Project registered with the DLD. DLD register, via Dubai Data
1 Aug 2023 Registered construction start. No completion date filed. DLD register
12 Apr 2024 5.5% at the DLD inspection. DLD register, via Dubai Data
30 Oct 2025 24.1% at the DLD inspection. DLD register, via Dubai Data
14 May 2026 32.5% at the DLD inspection. DLD register, via Dubai Data
30 Jul 2026 Named among 11 Danube projects due within 12 months. Danube, via Gulf News
31 Aug 2026 45% on Danube’s internal inspection. Danube
10 Sep 2026 40.00% at the DLD inspection. DLD register, via Continental Club
6 Oct 2026 Main project page shows July 2027; FAQ still shows July 2026. Danube

Between July 2025 and September 2026 the DLD figure rose by about 1.4 percentage points a month on average (Dubai Data). The July 2027 date would need about 60 points in ten months.

What the Fashionz by Danube handover date means for payments

Fashionz is sold on Danube’s 1% monthly plan, so buyers pay monthly during construction and a later handover means more instalments before the handover payment. Continental Club lists 10% on booking, 45% during construction, 15% on handover and 30% over 30 months after handover. Bayut lists 10% down, 54% during construction, 1% on handover and 35% over 35 months after handover. On either split, a share of the price falls due after the keys, and the timing of that tail moves with the handover date.

What to check before relying on the Fashionz by Danube date

  1. The completion date in the SPA, since Danube’s own page carries July 2026 and July 2027 and the DLD register has no date.
  2. Whether a completion date has been added to the DLD register for project 2640, through DLD’s project status enquiry service.
  3. Which payment split the SPA uses, since 15% or 1% on handover and 30% or 35% afterwards change the cash needed at the keys.
  4. The next DLD inspection figure. A rise well above the recent pace would be needed to meet July 2027.

Questions buyers also ask

What is the Fashionz by Danube handover date?

July 2027, on Danube's main project page. The FAQ on the same page still says July 2026, and the DLD register holds no completion date (accessed 6 Oct 2026).

Is Fashionz by Danube finished?

No. The DLD inspection of 10 September 2026 put it at 40.00%, up from 32.5% on 14 May 2026. Danube's own inspection on 31 August 2026 put it at 45%, with the 22nd floor slab being cast.

Has the Fashionz by Danube handover date been delayed?

Yes, on Danube's own figures. At launch in April 2023 the target reported was January 2027. Danube's page FAQ says July 2026 and its main project details now say July 2027. In July 2026 Danube listed Fashionz among 11 projects due within 12 months (Gulf News, 30 Jul 2026).

How much is due at the Fashionz by Danube handover?

Sources differ. Continental Club lists 15% on handover and 30% over 30 months after it. Bayut lists 1% on handover and 35% over 35 months after it. The SPA sets the split for each unit.

Sources

  1. Danube Properties, Fashionz project page (opens in a new tab)danubeproperties.com · accessed 6 Oct 2026
  2. Continental Club, Fashionz 1 by Danube (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 25 Sep 2026
  3. Mitchells Commercial Realty, Fashionz 1 By Danube DLD register (opens in a new tab)mitchellscommercialrealty.com · register as at 23 Sep 2026