Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Enara by Omniyat handover date?

Updated 11 October 2026 Enara by Omniyat

Short answer

The Enara by Omniyat handover date is Q3 2028 on Omniyat's own project page, later than the registered completion date of 31 December 2027 on the Dubai Land Department (DLD) register. The DLD recorded the tower 7.25% complete on 12 June 2026, and Omniyat put it at 14% in late August 2026. Omniyat also cut its 2026 structure target from level 10 in February to level three in August, so the December 2027 date looks unlikely to hold.

Registered completion date

31 Dec 2027

DLD register via Continental Club, updated 8 Oct 2026

Latest construction progress

7.25%

DLD inspection, 12 Jun 2026

Developer's stated date

Q3 2028

Omniyat project page, accessed 11 Oct 2026

Progress reported by Omniyat

14%

Omniyat via Al Masdar Al Aqaari, 30 Aug 2026

Enara by Omniyat handover date: the latest position

Omniyat’s project page gives Q3 2028 as the completion date for Enara, its office tower in Marasi Bay, Business Bay (accessed 11 October 2026). The Dubai Land Department (DLD) register still carries a completion date of 31 December 2027 for project 3220. More on the offices, prices and payment plan is on the Enara by Omniyat project page.

The latest DLD inspection, on 12 June 2026, recorded 7.25% complete. Omniyat’s own figure, reported on 30 August 2026, was 14%. Either way, most of the tower is still to be built with about 15 months left to the register date.

Enara by Omniyat handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Enara by Omniyat (49 registered units, 34 offices) 7.25% (12 Jun 2026) 31 Dec 2027 Q3 2028 (Omniyat); December 2027 (Propsearch, Mar 2026)

DLD inspection history, from Continental Club:

Inspection Progress
15 Aug 2024 0%
8 Aug 2025 3.66%
20 Jan 2026 5.63%
12 Jun 2026 7.25%

How the Enara by Omniyat handover date has changed

Date Event Source
1 Oct 2024 Registered construction start. The register’s completion date is 31 December 2027. DLD register via Mitchells
Nov 2024 First office sales registered with the DLD. DLD transactions via Continental Club
21 May 2025 Omniyat says 32 of 34 offices are sold. Gulf News
16 Feb 2026 Dutco appointed main contractor; piling complete; structure to reach level 10 in 2026. Omniyat via Zawya
6 Mar 2026 Propsearch shows an estimated handover of December 2027. Propsearch
30 Aug 2026 Omniyat reports 14% complete, structure to reach level three by the end of 2026, completion in 2028. Al Masdar Al Aqaari
Oct 2026 Omniyat’s project page shows Q3 2028; the register still shows 31 December 2027. Omniyat; Continental Club

The developer’s date has moved from the end of 2027 into the third quarter of 2028, and the 2026 structure target has been lowered.

What the Enara by Omniyat handover date means for payments

Continental Club lists a 70/30 plan: 70% paid before handover and 30% on handover. Omniyat has not published the plan itself. On the AED 70.4 million office registered on 15 January 2026, a 30% handover payment would be about AED 21.1 million. If completion follows Omniyat’s Q3 2028 date, that payment comes about nine months after the register date.

What to check before relying on the Enara by Omniyat date

  1. The date and grace period in the office SPA, against Omniyat’s newer Q3 2028 date.
  2. Whether the pre-handover 70% is tied to milestones, since the structure target for 2026 has been cut from level 10 to level three.
  3. The next DLD inspection, to see whether the register moves toward Omniyat’s reported 14%.

Questions buyers also ask

Is Enara by Omniyat finished?

No. It was 7.25% complete at the DLD inspection of 12 June 2026, and Omniyat reported 14% at the end of August 2026. The superstructure phase began after Dutco was appointed main contractor in February 2026.

What is the Enara by Omniyat completion date?

31 December 2027 on the DLD register for project 3220. Omniyat's project page gives Q3 2028.

Has the Enara by Omniyat handover date been delayed?

Omniyat's own date is now Q3 2028, about nine months after the 31 December 2027 date on the register and on Propsearch. Omniyat has not announced the change in a press release.

How fast is Enara by Omniyat being built?

The DLD figure rose from 3.66% on 8 August 2025 to 7.25% on 12 June 2026, about 0.35% a month over the past year (Continental Club).

Sources

  1. DLD project register via Continental Club, Enara By Omniyat (opens in a new tab)continentalclub.ae · inspection 12 Jun 2026, register updated 8 Oct 2026
  2. Mitchells, Enara by Omniyat DLD registry (opens in a new tab)mitchellscommercialrealty.com · register as at 2 Oct 2026
  3. Propsearch, Enara by Omniyat (opens in a new tab)propsearch.ae · updated 6 Mar 2026