Handover date

When is the Ember at Park Five handover date?

Updated 11 October 2026 Ember at Park Five

Short answer

The DLD register gives Ember at Park Five a completion date of 1 June 2027, in line with the summer 2027 date Deyaar gave at launch. A DLD inspection on 17 September 2026 recorded the building 18.24% complete. With about 82% of the work left less than eight months before that date, a later handover is likely, but no new date has been filed.

Registered completion date (DLD)

1 Jun 2027

DLD project register via Continental Club, updated 4 Oct 2026

Latest construction progress

18.24%

DLD inspection, 17 Sep 2026

Developer's stated date

Summer 2027

Deyaar, 27 Nov 2024

Portal date

June 2027

Property Finder, accessed 11 Oct 2026

Ember at Park Five handover date: the latest position

The Dubai Land Department (DLD) register gives Ember at Park Five a completion date of 1 June 2027. Deyaar said at launch in November 2024 that phase 1 of Park Five, made up of Elm and Ember, would complete in summer 2027, and Property Finder lists June 2027. Full project details are on the Ember at Park Five page.

The latest DLD inspection, on 17 September 2026, recorded the building 18.24% complete. That leaves about 82% of the work to do in less than eight months. No revised date had been filed in the register by 4 October 2026.

Ember at Park Five handover date by building

Ember is one building with 205 units. The table also shows the other Park Five buildings, which have their own DLD entries and dates.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Ember at Park Five 18.24% (17 Sep 2026) 1 Jun 2027 Summer 2027 (Deyaar); June 2027 (Property Finder)
Neem at Park Five 15.22% (9 Sep 2026) 1 Dec 2027 Not confirmed
Ivy at Park Five 6.28% (17 Sep 2026) 31 Dec 2027 Q4 2027
Alder at Park Five 6.07% (30 Sep 2026) 31 Dec 2027 Not confirmed

Progress and registered dates are from the DLD project register via Continental Club. Elm, the other phase 1 building, is not shown here.

How the Ember at Park Five handover date has changed

Date Event Source
23 Oct 2024 First DLD inspection records 0% Data Dubai
27 Nov 2024 Deyaar launches Park Five; phase 1 (Elm and Ember) due summer 2027 Deyaar
16 Dec 2024 Project registered with DLD, completion date 1 June 2027 Data Dubai
1 Apr 2025 Registered construction start DLD via Continental Club
29 Jun 2026 DLD inspection records 13.43% Mitchells
17 Sep 2026 DLD inspection records 18.24% DLD via Continental Club

The date has not moved since launch. What has changed is the pace. Data Dubai puts progress since June 2026 at about 1.8 percentage points a month. At that rate the building would be well short of complete by 1 June 2027, so buyers can expect the registered date to be revised or the SPA grace period to come into play.

What the Ember at Park Five handover date means for payments

The main plan is 10% on booking, 40% during construction and 50% on handover (Property Finder; Continental Club). Property Finder also lists a 10/30/60 plan. Under either plan, half or more of the price is paid on handover. If handover moves later, that payment moves later too, along with any mortgage drawdown tied to it.

What to check before relying on the Ember at Park Five date

  1. The completion date and grace period in the SPA. The registered 1 June 2027 date is the starting point, not a promise of keys on that day.
  2. The next DLD inspection figure. A building at 18.24% in September 2026 needs much faster progress to finish by June 2027.
  3. Which payment plan the unit uses, since a 60% final payment is harder to fund than 50% if the date moves.
  4. Phase confusion with other Park Five buildings. Ivy, Alder and Neem carry later dates, so listings that quote “Park Five” without the building name can mislead.

Questions buyers also ask

Is Ember at Park Five finished?

No. The building was 18.24% complete at the DLD inspection of 17 September 2026 (DLD project register via Continental Club).

What is the Ember at Park Five completion date?

The DLD registered completion date is 1 June 2027. Property Finder also lists June 2027, and Deyaar's launch release said summer 2027.

Has the Ember at Park Five handover date been delayed?

Not on paper. The registered date of 1 June 2027 still matches Deyaar's launch promise. But progress rose only from 13.43% on 29 June 2026 to 18.24% on 17 September 2026, which leaves most of the build to finish before June 2027.

When will the other Park Five buildings be ready?

Ivy and Alder are both registered for 31 December 2027, and Neem for 1 December 2027 (DLD project register via Continental Club). Elm launched with Ember in phase 1.

Sources

  1. Mitchells, Ember at Park Five DLD registry (opens in a new tab)mitchellscommercialrealty.com · register to 7 Sep 2026