Handover date

When will Dubai Creek Harbour be completed?

Updated 6 October 2026 Dubai Creek Harbour

Short answer

Dubai Creek Harbour has no single completion date, because Emaar builds it tower by tower. The latest registered completion date on the Dubai Land Department (DLD) register is 31 August 2030, for Valia, after Creek Haven (31 March 2030) and Creek Bay (30 April 2030). The most advanced towers still under construction are Creek Waters 2 at 81.84% (DLD inspection, 31 July 2026) and Creek Waters at 81.08% (3 August 2026), due 31 December and 30 September 2027. Dubai Creek Tower is not on any timetable: its construction tender was pushed back in June 2026, and Emaar has not published an end date for the whole master plan.

Latest registered completion date (DLD)

31 Aug 2030

Valia, 0% built at 16 Mar 2026 inspection. Continental Club, 2 Sep 2026

Most advanced tower under construction

81.84%

Creek Waters 2, DLD inspection 31 Jul 2026, due 31 Dec 2027

Most recent completion recorded

6 May 2026

The Cove II, DLD registry via Real Estate Club Dubai

Homes completed, and still due by 2029

10,582 / 7,217

Emaar report, Sep 2025, via AGBI

Dubai Creek Harbour completion date: the latest position

Dubai Creek Harbour will not be completed on one date. Emaar builds it tower by tower, and each tower has its own registered completion date with the Dubai Land Department. On the register in October 2026, those dates run from 30 September 2027 for Creek Waters to 31 August 2030 for Valia. Full details of the community are on the Dubai Creek Harbour page.

Emaar counted 10,582 completed homes in September 2025, with 7,217 more due by 2029 (AGBI). Several Creek Beach blocks, Creek Palace and The Cove II have since been recorded as finished. Dubai Creek Tower and the Dubai Square mall have no confirmed completion date, so the master plan has no published end date.

Dubai Creek Harbour completion date by project

Towers still being built, with the latest DLD inspection and the registered completion date on file. Most are registered in the DLD land area Al Khairan First, under the developer names Dubai Creek Harbour L.L.C or The Lagoons Phase One L.L.C.

Project Construction progress (DLD, date) Registered completion date Developer or portal date
Creek Waters 81.08%, 3 Aug 2026 30 Sep 2027 Q3 2027 (Property Finder)
Creek Waters 2 81.84%, 31 Jul 2026 31 Dec 2027 Due 2027 (Propsearch)
Aeon 77.91%, 24 Jun 2026 Not filed Q2 2028 (Real Estate Club Dubai)
Oria 71.10%, 29 Jul 2026 Not filed Not published
Valo 66.05%, 25 Jun 2026 Not filed Q3 2028 (Property Finder)
Altus 64.20%, 25 Jun 2026 31 Jan 2029 Due 2029 (Propsearch)
Arlo 35.42%, 3 Jun 2026 Not filed Not published
Address Residences Dubai Creek Harbour 26.44%, 4 May 2026 31 Jan 2029 Q1 2029 (Real Estate Club Dubai)
Palace Residences Creek Blue 20.52%, 9 Jun 2026 31 Mar 2029 Due 2029 (Propsearch)
Altan 11.06%, 2 Jul 2026 31 Jul 2029 About Q3 2029 (Real Estate Club Dubai)
Albero 11%, 2 Jul 2026 30 Sep 2029 Due 2029 (Propsearch)
Silva 10.16%, 19 Jul 2026 30 Sep 2029 Not published
Montiva (Emaar Green Gate) 5.85%, 22 Apr 2026 30 Sep 2029 Q3 2029 (Property Finder)
Creek Haven 0.87%, 16 Jun 2026 31 Mar 2030 Not published
Creek Bay 0.62%, 16 Jun 2026 30 Apr 2030 Not published
Valia 0%, 16 Mar 2026 31 Aug 2030 Q3 2030 (Property Finder)
Dubai Creek Tower No construction tender None None

DLD figures come from the register as republished by Continental Club and Mitchells Commercial Realty (September and October 2026). “Not filed” means the register shows no completion date for that project.

Dubai Creek Harbour projects completed since 2023

Project Construction progress Completion recorded Note
Rosewater at Creek Beach Complete, 100% (DLD, 7 Nov 2024) DLD handover date 1 Jun 2025 Continental Club; Propsearch
Palace Residences North 100%, 8 Sep 2025 Registered completion date 30 Jun 2027 Built well ahead of its registered date (Mitchells)
Creek Beach: Savanna, Cedar, Mangrove, Canopy, Moor 100% 7 Nov 2025 Savanna, Cedar and Mangrove were marketed for July to Q3 2026, Moor for Q4 2026; Propsearch still lists them as due 2026
Creek Palace 100% 31 Mar 2026 783 apartments, single tower
The Cove II 100% 6 May 2026 2,683 homes across Towers 4 to 8; Propsearch still lists Buildings 4 to 11 as under construction

Completion dates for the last three rows are the dates recorded in the DLD registry, via Real Estate Club Dubai’s tracker (verified 1 and 5 October 2026).

How the Dubai Creek Harbour completion date has changed

Date What happened Source
Aug 2022 Emaar took full ownership from Dubai Holding, for about AED 8 billion Propsearch
Sep 2025 10,582 homes completed, 7,217 more due by 2029 Emaar via AGBI
7 Nov 2025 Savanna, Cedar, Mangrove, Canopy and Moor recorded finished, ahead of 2026 marketing dates DLD via Real Estate Club Dubai
14 Jan 2026 Alabbar says a Dubai Creek Tower tender will be offered within three months Khaleej Times
31 Mar 2026 Creek Palace recorded finished DLD via Real Estate Club Dubai
6 May 2026 The Cove II recorded finished, on its May 2026 schedule DLD via Real Estate Club Dubai
23 Jun 2026 Dubai Creek Tower tender delayed by at least four months over material costs AGBI
Sep 2026 Creek Haven, Creek Bay and Valia registered for 2030, the latest dates on file DLD via Continental Club

The pattern so far is that Creek Beach and The Cove II finished on or before their marketed dates. The one long delay is Dubai Creek Tower, where construction stopped in 2020.

What the Dubai Creek Harbour dates mean for payments

Emaar sets payment plans tower by tower, so the amount due on completion differs across the community. Real Estate Club Dubai reports an 80/20 plan at Emaar Green Gate, which would leave 20% of the price due on completion. Emaar has not confirmed that plan in its own announcements. For towers with no registered completion date filed, such as Aeon, Oria, Valo and Arlo, the SPA is the only document that fixes when that final payment falls due.

What to check before relying on a Dubai Creek Harbour date

  1. The DLD project name of the tower. The register uses names such as “Address Residences L Dubai Creek Harbour” and the land area Al Khairan First, not always the marketing name.
  2. Whether a registered completion date is on file. Four of the towers most advanced in 2026 had none, so portal quarters are estimates only.
  3. How far the tower has to go. Towers due in 2029 were between 5.85% and 64.20% built in mid 2026, while those due in 2030 had barely started.
  4. Supply finishing at the same time. About 7,200 homes are due by 2029, and Creek Waters and Creek Waters 2 alone finish three months apart in 2027.

Questions buyers also ask

When will Dubai Creek Harbour be completed?

There is no single completion date. Towers registered with DLD run from 30 September 2027 (Creek Waters) to 31 August 2030 (Valia). Emaar counted 10,582 completed homes in September 2025, with 7,217 more due by 2029 (AGBI). Dubai Creek Tower and the Dubai Square mall have no confirmed completion date.

Is Dubai Creek Harbour finished?

No. Many towers are complete, including The Cove II (recorded finished 6 May 2026), Creek Palace (31 March 2026) and the Creek Beach blocks Savanna, Cedar, Mangrove, Canopy and Moor (recorded 7 November 2025). At least 16 more towers were under construction or at the start of works in mid 2026 (DLD register).

Which Dubai Creek Harbour towers will be completed next?

Creek Waters (81.08%, registered completion 30 September 2027) and Creek Waters 2 (81.84%, 31 December 2027), followed by Aeon (77.91% on 24 June 2026, Q2 2028 per Real Estate Club Dubai) and Oria (71.10% on 29 July 2026). Aeon, Oria, Valo and Arlo have no registered completion date filed with DLD.

When will Dubai Creek Tower be completed?

No date has been set. Construction stopped in 2020. Emaar chairman Mohamed Alabbar said in January 2026 that a construction tender would be offered within three months, and AGBI reported on 23 June 2026 that the tender had been delayed by at least four months because of higher material costs.

Is Rosewater at Creek Beach finished?

Yes. Propsearch lists Rosewater at Creek Beach, three buildings of 9 to 13 storeys, as complete. The DLD recorded all three buildings 100% built on 7 November 2024 and gives a handover date of 1 June 2025.