Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Creek Waters handover date?

Updated 1 October 2026 Creek Waters

Short answer

The Creek Waters handover date is 30 September 2027, the registered completion date on the Dubai Land Department (DLD) register, and Property Finder and Propsearch give Q3 2027. Creek Waters 2 is a separate tower registered for 31 December 2027. The DLD inspections put Creek Waters at 81.08% complete on 3 August 2026 and Creek Waters 2 at 81.84% on 31 July 2026, so the twin towers are at almost the same stage but three months apart on paper.

Registered completion date (DLD), Creek Waters

30 Sep 2027

DLD register, project 2614, via Mitchells, accessed 1 Oct 2026

Latest construction progress, Creek Waters

81.08%

DLD site inspection, 3 Aug 2026

Registered completion date (DLD), Creek Waters 2

31 Dec 2027

Project 2634; 81.84% at DLD inspection, 31 Jul 2026

Date change since launch

None recorded

Property Finder, booking opened 1 Feb 2023 with completion 1 Sep 2027

Creek Waters handover date: the latest position

Creek Waters is registered for completion on 30 September 2027. That is the date the Dubai Land Department holds for project number 2614, and Property Finder and Propsearch give the same Q3 2027. The DLD site inspection of 3 August 2026 recorded the tower 81.08% complete, up 8.9 points from the inspection of 10 April 2026. More on prices and sizes is on the Creek Waters page.

Creek Waters 2, the twin tower next to it, is registered for 31 December 2027, three months later. Its DLD inspection of 31 July 2026 recorded 81.84%, slightly ahead of Creek Waters. The two towers started a week apart in August 2023 and are at almost the same stage, so the later date for Creek Waters 2 reflects the registered schedule rather than slower building. For Creek Waters, about 19% of the work remained at the August inspection, with 14 months to the registered date.

Creek Waters handover date by building

The DLD register lists each tower as a separate project, with its own progress figure and registered date. Both are described as 2 basements, ground, podium and 50 floors.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Creek Waters (453 homes, project 2614) 81.08%, 3 Aug 2026 30 Sep 2027 Q3 2027 (Property Finder, Propsearch)
Creek Waters 2 (455 homes, project 2634) 81.84%, 31 Jul 2026 31 Dec 2027 Dec 2027 (Property Finder, Bayut)

Creek Waters 2 gained about 8 points between the DLD inspections of 20 April and 31 July 2026, a similar pace to Creek Waters (Continental Club, DLD data).

How the Creek Waters handover date has changed

Neither date has moved since sales opened.

Date What happened Source
1 Feb 2023 Booking opened for Creek Waters, with an expected completion of 1 September 2027. Property Finder
Apr 2023 Launch payment schedule placed the final 10% in September 2027. Kredium
15 and 22 Aug 2023 Registered construction starts for Creek Waters and Creek Waters 2. Creek Waters 2 went on sale on 22 August with a December 2027 date. DLD register; Property Finder
Apr 2026 DLD inspections: about 72% for Creek Waters (10 April) and about 74% for Creek Waters 2 (20 April). Continental Club, DLD data
31 Jul and 3 Aug 2026 81.84% for Creek Waters 2 and 81.08% for Creek Waters. DLD register
Sep 2026 Registered dates still 30 September 2027 and 31 December 2027. DLD register, via Mitchells

Kredium gives October 2027 for Creek Waters, a month after the registered date; every other source checked gives September 2027 or Q3 2027.

What the Creek Waters handover date means for payments

Both towers use a 10/80/10 plan: 10% at booking, 80% during construction and 10% on handover. The Creek Waters launch schedule ran on fixed dates: 10% at booking, then 10% in June 2023, December 2023 and June 2024, 15% in February 2025 and September 2025, 10% in April 2026 and October 2026, and the final 10% in September 2027.

On that schedule, buyers from launch have paid 90% by October 2026, and only the last 10% lines up with completion. On a 1 bedroom at the AED 1.6 million launch price, that final payment is AED 160,000. A detailed schedule for Creek Waters 2 was not found, though it uses the same 10/80/10 split.

What to check before relying on the Creek Waters date

  1. Which tower your unit is in. Creek Waters and Creek Waters 2 have different registered dates even though their progress is almost the same.
  2. Whether your SPA ties the last 10% to a calendar date or to completion. The launch schedule named September 2027, so a later completion could leave that payment due before keys are handed over, or move it, depending on the wording.
  3. For a resale unit, Emaar’s statement of account, since most of the price was due by October 2026 and the buyer takes over whatever remains.
  4. The DLD progress for project 2614 or 2634, through DLD’s project status enquiry service.

Questions buyers also ask

What is the Creek Waters completion date?

30 September 2027, the registered completion date for DLD project number 2614 (DLD register, via Mitchells, accessed 1 Oct 2026). Property Finder lists an expected completion of 1 September 2027 and Propsearch Q3 2027. One agent, Kredium, gives October 2027.

When is the Creek Waters 2 handover date?

Creek Waters 2 is a separate Emaar tower with a registered completion date of 31 December 2027 (DLD project 2634). Property Finder and Bayut give December 2027. The DLD inspection of 31 July 2026 put it at 81.84% complete.

Is Creek Waters finished?

No. The DLD site inspection of 3 August 2026 put Creek Waters at 81.08% complete, up 8.9 points from the inspection of 10 April 2026. The register still listed it as under construction on 27 September 2026 (Mitchells, DLD data).

Has the Creek Waters handover date been delayed?

No change has been published. Property Finder has listed an expected completion of 1 September 2027 since booking opened on 1 February 2023, and the launch payment schedule placed the final 10% in September 2027. The DLD register holds 30 September 2027.

How much is due at the Creek Waters handover?

10%. Both towers use a 10/80/10 plan. On the Creek Waters launch schedule, 90% was due in instalments by October 2026 and the final 10% in September 2027 (Kredium, accessed 1 Oct 2026).

Sources

  1. Mitchell's, Creek Waters DLD registry (project 2614) (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  2. Mitchell's, Creek Waters 2 DLD registry (project 2634) (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  3. Propsearch, Creek Waters (opens in a new tab)propsearch.ae · accessed 28 Sep 2026
Request a Unit Review