Handover date

When was the Deira Enrichment Project handed over?

Updated 6 October 2026 Deira Enrichment Project

Short answer

The Deira Enrichment Project was handed over in stages between September 2020 and April 2022. Ithra Dubai handed over Sherina Plaza (Plot 3) in September 2020, completed Plots 1 and 2 in January 2021, launched One Deira on 16 August 2021 and opened the Gold Souk Extension on 26 April 2022. That was later than Ithra's 2019 plan to start handovers at the end of 2019. Work continues on Gold Street in the new Dubai Gold District, due in Q4 2026, and Ithra has not published a date for Phase 2.

First handover

Sep 2020

Sherina Plaza, Plot 3. Ithra Dubai, 1 Sep 2020

Gold Souk Extension opened

26 Apr 2022

Hind and Maryam Plazas. Deira Enrichment Project

Developer's first handover target

End of 2019

Ithra Dubai via Construction Week, 24 Jun 2019

Gold Street, Dubai Gold District

Q4 2026

Ithra Dubai via Khaleej Times, 6 May 2026

Deira Enrichment Project handover date: the latest position

The Deira Enrichment Project handover date for Phase 1 has passed. Ithra Dubai, owned by the Investment Corporation of Dubai, handed over the main Phase 1 plazas between September 2020 and April 2022. The first was Sherina Plaza in September 2020, and the last large piece, the Gold Souk Extension, opened on 26 April 2022. More on the homes and the area is on the Deira Enrichment Project page.

Two parts are still to come. Gold Street, the centrepiece of the Dubai Gold District that Ithra launched on 27 January 2026, was under construction in May 2026 and due to open in Q4 2026 (Khaleej Times, 6 May 2026). Phase 2, a planned marina district next to the Waterfront Market, has no published date.

Deira Enrichment Project handover date by plaza

Plaza or plot Progress before handover Handed over or opened Developer or portal date
Sherina Plaza (Plot 3) 85%, Jun 2019 Close-out and handover from 1 Sep 2020 End of 2019 (Ithra, Jun 2019)
Plot 11 70%, Jun 2019 Handed over by Feb 2021 Next after Plot 3 (Ithra, Jun 2019)
Plots 1 and 2 60% and 75%, Jun 2019 Completed Jan 2021 Not given separately
One Deira (District 4) Not published Launched 16 Aug 2021 Completed on schedule (Ithra)
Gold Souk Extension (Hind and Maryam Plazas) Not published Opened 26 Apr 2022 End of 2020, then Q4 2021
Gold Street, Dubai Gold District Under construction, May 2026 Not yet open Q4 2026 (Ithra, May 2026)
Phase 2 marina district No progress published Not yet open No date published

Sources: Construction Week (24 June 2019; 22 February 2021); Ithra Dubai (1 September 2020; 16 August 2021; 27 September 2021); Propsearch; Khaleej Times (6 May 2026). Ithra’s August 2021 release said Hind and Maryam Plazas were handed over by March 2021, while Propsearch gives Maryam Plaza a completion of April 2022, the month the Gold Souk Extension opened.

How the Deira Enrichment Project handover date has changed

Date What happened Source
2017 Construction starts on Plots 1, 2, 3, 11 and 13 Propsearch
24 Jun 2019 Ithra plans phased handover from the end of 2019 and early 2020 Construction Week
22 Jun 2020 Districts 1, 2, 3, 11 and 13 in final stages Ithra Dubai
1 Sep 2020 Sherina Plaza enters close-out and handover Ithra Dubai
22 Feb 2021 Plots 11 and 3 handed over, Plots 1 and 2 completed; eight or nine plots due in 2021 Construction Week
16 Aug 2021 One Deira launched Ithra Dubai
27 Sep 2021 Gold Souk Extension said to be on track for Q4 2021 Ithra Dubai
26 Apr 2022 Gold Souk Extension opens Deira Enrichment Project
1 Apr 2025 Six-hotel cluster of 999 keys opens under Accor brands Hotelier Middle East
27 Jan 2026 Dubai Gold District launched WAM
6 May 2026 Gold Street due to open in Q4 2026 Khaleej Times

Against the end-2019 target, the first handover came about nine months late, and the Gold Souk Extension opened more than a year after its first date.

What to check before relying on a Deira Enrichment Project date

  1. Which plaza the home is in. Plazas finished at different times between 2020 and 2022.
  2. The lease terms. Ithra Dubai offers DEP homes for lease, so the date that matters to a tenant is the lease start, not a handover under an SPA.
  3. Works near the Gold Souk. Gold Street was still being built in 2026, and Phase 2 has no published start date.

Questions buyers also ask

Is the Deira Enrichment Project finished?

The main Phase 1 plazas are finished and leased. Gold Street, part of the Dubai Gold District that Ithra Dubai launched in January 2026, was under construction in May 2026 and due to open in Q4 2026. Phase 2, a planned marina district, has no published date.

When was the Gold Souk Extension handed over?

It opened on 26 April 2022 in Hind and Maryam Plazas, with 295 shops, 250 offices and 468 homes (Deira Enrichment Project). It had been due by the end of 2020 and then in Q4 2021.

When will Deira Enrichment Project Phase 2 be completed?

Ithra Dubai has not published a date. Its site describes Phase 2 as a marina district beside the Waterfront Market, with residential towers, hotels and a private marina.

Was the Deira Enrichment Project delivered on time?

Later than first planned. In June 2019 Ithra Dubai said phased handover would start at the end of 2019. The first plaza was handed over in September 2020, and the Gold Souk Extension opened in April 2022 (Construction Week; Ithra Dubai).

Sources

  1. Propsearch, Deira Waterfront (opens in a new tab)propsearch.ae · updated 6 Feb 2026
  2. Propsearch, Maryam Plaza (opens in a new tab)propsearch.ae · updated 7 May 2025
  3. Propsearch, One Deira (opens in a new tab)propsearch.ae · updated 7 May 2025