When is the Butterfly Towers handover date?
Short answer
Butterfly Towers has a registered completion date of 31 January 2029 at the Dubai Land Department (DLD), and Al Sayyah Group markets Q1 2029. The DLD inspection of 21 May 2026 recorded construction at 7.65%. Both towers share one DLD record, so there is no separate date for Butterfly A and Butterfly B.
Registered completion date (DLD)
31 Jan 2029
DLD project 3060, via Mitchell's
Latest construction progress (DLD)
7.65%
DLD inspection, 21 May 2026
Developer's stated date
Q1 2029
Al Sayyah Group, via Takween Aldar and Continental Club
Date change since launch
None
January 2029 on record since registration (Dubricks; Propsearch)
Butterfly Towers handover date: the latest position
Butterfly Towers is registered for completion on 31 January 2029 at the Dubai Land Department (DLD), under project 3060, recorded on the register as “butterfly” in Arjan. Al Sayyah Group and brokers market Q1 2029, the same quarter. Prices, sizes and payment plans: Butterfly Towers.
The DLD inspection of 21 May 2026 recorded 7.65% progress. No later inspection had been published by 11 October 2026.
Butterfly Towers handover date by building
The two towers are 20 storeys each by Propsearch’s count: basement, ground, two podium levels and 17 floors on the DLD description. They share one project record.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Butterfly A (residential) | 7.65%, 21 May 2026 (whole project) | 31 Jan 2029 | Q1 2029 (developer); Jan 2029 (Propsearch) |
| Butterfly B (includes retail units) | 7.65%, 21 May 2026 (whole project) | 31 Jan 2029 | Q1 2029 (developer); Jan 2029 (Propsearch) |
How the Butterfly Towers handover date has changed
| Date | What was recorded | Source |
|---|---|---|
| 2 Jul 2024 | First DLD inspection, 0% | DLD, via Continental Club |
| 29 Aug 2024 | Project registered; anticipated completion 31 Jan 2029 | DLD record, via Dubricks |
| Nov 2024 | Launch by Al Sayyah Group | Propsearch |
| 1 Jan 2025 | Registered construction start | DLD register, via Mitchell’s |
| 17 Nov 2025 | First registered off-plan sale in the Mitchell’s dataset | DLD sales register |
| 21 May 2026 | 7.65% complete | DLD inspection, via Continental Club |
| 11 Oct 2026 | Developer still markets Q1 2029 | Takween Aldar; Continental Club |
The January 2029 date has not moved since the project was registered. By the May 2026 inspection, about 16 months into a 49 month programme from the registered start, 7.65% of the work was recorded.
What the Butterfly Towers handover date means for payments
Under the 5 year post-handover plan, buyers pay 20% at booking and 5% every three months during construction, up to 30%. Only 10% is due on handover, and the last 40% runs for 60 months after it at 4% every six months (Takween Aldar). A later handover pushes back the start of those post-handover instalments rather than adding to them. Under the 50/50 plan listed for retail units, 50% is due on handover, so the date matters more.
What to check before relying on the Butterfly Towers date
- The SPA date and grace period for the unit, since the developer’s Q1 2029 and the register’s 31 January 2029 leave no margin.
- Whether construction instalments are time based or linked to progress. At 5% every three months, the 30% may be paid well before the towers are half built.
- The next DLD inspection in the DLD project status service, the first since May 2026.
- The post-handover schedule in the SPA, including what happens to the remaining 40% if the unit is resold.
Questions buyers also ask
When will Butterfly Towers be completed?
The registered completion date is 31 January 2029. Dubricks also shows a handover date of 1 January 2029 in the DLD project record, and the developer markets Q1 2029.
Is Butterfly Towers on schedule?
The register has not changed the date. Progress was 0% on 2 July 2024 and 7.65% on 21 May 2026, the two published DLD inspections (Continental Club). About 92% of the work remained 32 months before the registered date.
Do Butterfly A and Butterfly B hand over at the same time?
The DLD register holds both buildings under one project, number 3060, with one completion date of 31 January 2029 and one progress figure.
How much is due at the Butterfly Towers handover?
10% under the 5 year post-handover plan, with a further 40% paid over 60 months after handover; 50% under the 50/50 plan (Takween Aldar).