Handover date

When is the Binghatti Ruby handover date?

Updated 11 October 2026 Binghatti Ruby

Short answer

Binghatti Ruby's registered completion date is 28 February 2026, and Binghatti still gives Q1 2026, but the tower has not been handed over. The latest DLD inspection, on 23 July 2026, recorded it 46.43% complete. Propsearch now estimates handover in Q4 2027, so the published date is no longer a guide to when keys will be ready.

Registered completion date (DLD)

28 Feb 2026

DLD project register via Continental Club

Latest construction progress

46.43%

DLD inspection, 23 Jul 2026

Developer's stated date

Q1 2026

Binghatti project page, accessed 11 Oct 2026

Portal estimate

Q4 2027

Propsearch, updated 15 Aug 2026

Binghatti Ruby handover date: the latest position

Binghatti Ruby has a registered completion date of 28 February 2026 in the DLD project register, and Binghatti’s own page still says Q1 2026. That date has passed and the tower is not finished. More detail on prices and the building is on the Binghatti Ruby page.

At the latest DLD inspection, on 23 July 2026, the building was 46.43% complete. Propsearch, updated on 15 August 2026, puts the estimated handover at Q4 2027. Binghatti has not announced a revised date.

Binghatti Ruby handover date by building

Binghatti Ruby is one tower, registered with DLD as a single project (project number 3533) with 628 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Binghatti Ruby 46.43%, 23 Jul 2026 28 Feb 2026 Q1 2026 (Binghatti); Q4 2027 estimate (Propsearch, 15 Aug 2026)

How the Binghatti Ruby handover date has changed

Date What happened Source
13 Dec 2024 Binghatti facts sheet issued at launch, studios from AED 695,000 Binghatti via Mitchells
17 Dec 2024 Listing gives a Q4 2025 completion date Arab Property
1 Jan 2025 Construction start recorded DLD register
28 Feb 2026 Registered completion date passes DLD register
10 Mar 2026 Inspection records 20.04% complete DLD register
23 Jul 2026 Inspection records 46.43% complete DLD register
15 Aug 2026 Estimated handover given as Q4 2027 Propsearch

The registered date and the developer’s date have not moved, even though the building has fallen well behind them. The Q4 2025 figure from the launch listing does not match Binghatti’s Q1 2026, so the launch promise depends on the source.

What the Binghatti Ruby handover date means for payments

Binghatti’s plan is 20% on booking, 50% during construction and 30% on completion. The final 30% is tied to completion, not to a calendar date, so it falls due only when the building is finished. On a studio bought at the launch price of AED 695,000, that last payment would be about AED 208,500. No post-handover plan is listed for this project.

What to check before relying on the Binghatti Ruby date

  1. The completion date and grace period in your SPA. The SPA date, not the Q1 2026 marketing date, is what the contract enforces.
  2. Which construction instalments are tied to progress. The SPA sets which parts of the 50% construction share follow building milestones, which matters since the tower was only 46.43% complete in July 2026.
  3. The next DLD inspection. DLD’s project status service publishes new figures after each inspection; the July 2026 figure is the latest available.
  4. Resale timing. Only one of 604 registered sales was a resale, so anyone planning to sell before completion has little price history to go on.

Questions buyers also ask

Is Binghatti Ruby finished?

No. The DLD register recorded the tower 46.43% complete at its inspection on 23 July 2026. It has not been handed over.

What is the Binghatti Ruby completion date?

The DLD project register holds a completion date of 28 February 2026, and Binghatti's project page gives Q1 2026. Both have passed. Propsearch estimated Q4 2027 when it updated its page on 15 August 2026.

Has the Binghatti Ruby handover date been delayed?

In practice, yes. Arab Property listed a Q4 2025 completion date at launch in December 2024, and Binghatti listed Q1 2026. The building was less than half built in July 2026. Binghatti has not published a new date.

How fast is construction moving at Binghatti Ruby?

Progress rose from 20.04% on 10 March 2026 to 46.43% on 23 July 2026, a gain of 26.39 points in about four and a half months (DLD project register via Continental Club).

Sources

  1. Propsearch, Binghatti Ruby (opens in a new tab)propsearch.ae · updated 15 Aug 2026
Request a Unit Review