When is the Binghatti Moonlight handover date?
Short answer
Binghatti Moonlight's registered completion date was 15 June 2026, and Binghatti's own page still says Q2 2026. That date has passed. The last DLD inspection, on 29 June 2026, recorded the tower 19.24% complete, and no newer inspection or revised date was on the register by 4 October 2026. A later handover is certain, but neither Binghatti nor the DLD had published the new date by 11 October 2026.
Registered completion date (DLD)
15 Jun 2026
Passed; DLD project 3722, via Continental Club, updated 4 Oct 2026
Latest construction progress
19.24%
DLD inspection, 29 Jun 2026
Developer's stated date
Q2 2026
Binghatti, accessed 11 Oct 2026
Later date in one broker listing
31 Mar 2027
Lucretia International, accessed 11 Oct 2026
Binghatti Moonlight handover date: the latest position
Binghatti Moonlight was due for completion on 15 June 2026. That is the registered completion date the Dubai Land Department holds for project 3722, and Binghatti’s page still gives Q2 2026. The date has passed. Two weeks later, on 29 June 2026, a DLD inspection recorded the tower 19.24% complete. More on prices and unit sizes is on the Binghatti Moonlight page.
No newer inspection had been added to the register by 4 October 2026, and the registered date had not been changed. Binghatti has not published a revised handover date. One broker listing gives 31 March 2027 (Lucretia International), but no developer or DLD source confirms it. At the pace recorded so far, about 19% in 14 months, the remaining work is far larger than what has been done.
Binghatti Moonlight handover date by building
Moonlight is a single 26 storey tower, so one date and one progress figure apply to all 286 units, offices included.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Moonlight (236 apartments, 47 offices, 3 shops) | 19.24%, 29 Jun 2026 | 15 Jun 2026 (passed) | Q2 2026 (Binghatti); June 2026 (Property Finder; Propsearch); 31 Mar 2027 (Lucretia International) |
How the Binghatti Moonlight handover date has changed
The published date has not moved. What has changed is that it has passed with most of the tower still to build.
| Date | What happened | Source |
|---|---|---|
| 15 Apr 2025 | Booking opened and the DLD registered construction start. Expected completion 15 June 2026. | Property Finder; DLD register |
| 29 Apr 2025 | First DLD inspection on record. | DLD register, via Continental Club |
| 9 Jul 2025 | Launch coverage gives completion in Q2 2026. | Prelaunch.ae |
| 7 May 2026 | Propsearch estimates handover in June 2026. | Propsearch |
| 15 Jun 2026 | Registered completion date passes. | DLD register |
| 29 Jun 2026 | DLD inspection records 19.24% complete. | DLD register, via Continental Club |
| 4 Oct 2026 | Register still shows 15 June 2026 and no newer inspection. Binghatti still says Q2 2026. | Continental Club; Binghatti |
What the Binghatti Moonlight handover date means for payments
Binghatti’s plan is 20% on signing, 50% during construction and 30% on completion. The 30% falls due at completion, so it moves with the real handover date rather than the registered one. On a 1 bedroom at the AED 1,512,999 DLD median, that last payment is about AED 453,900. On a 2 bedroom at the AED 2,108,999 median, it is about AED 632,700 (Continental Club, DLD data updated 3 October 2026). The construction share is paid as the building progresses.
What to check before relying on the Binghatti Moonlight date
- The completion date and grace period written in the SPA, which decide what applies now that 15 June 2026 has passed.
- Any extension filed with the DLD for project 3722, through the DLD project status enquiry service.
- The source of any new date offered. The 31 March 2027 date in one broker listing is not from Binghatti or the DLD.
- How many construction instalments are already paid, since 19.24% progress and a 50% construction share may not line up in a given SPA.
Questions buyers also ask
Is Binghatti Moonlight finished?
No. The DLD recorded it 19.24% complete on 29 June 2026, the latest published inspection (Continental Club, DLD registry updated 4 October 2026).
What is the Binghatti Moonlight completion date?
15 June 2026 on the DLD register, matching Binghatti's Q2 2026 and Property Finder's June 2026. The date has passed with the tower under 20% built.
Has the Binghatti Moonlight handover date been delayed?
In practice, yes. The registered date of 15 June 2026 passed with construction at 19.24%. Binghatti had not announced a new date by 11 October 2026. One broker listing gives 31 March 2027, but that is not a developer or DLD figure.
How much is due at the Binghatti Moonlight handover?
30% of the price, under Binghatti's 20/50/30 plan. On a 1 bedroom at the AED 1,512,999 DLD median, that is about AED 453,900.