Handover date

When is the Binghatti Hillviews handover date?

Updated 11 October 2026 Binghatti Hillviews

Short answer

Binghatti Hillviews' registered completion date at the Dubai Land Department (DLD) is 1 April 2026, which has passed. Binghatti's own page now says Q4 2026, and Continental Club's record shows a developer-supplied Q2 2027. The last published DLD inspection, on 25 June 2026, recorded 32.6% complete. Sources disagree by more than a year, so the SPA date and its grace period are what a buyer can rely on.

Registered completion date (DLD)

1 Apr 2026

DLD project 3321, via Continental Club; passed

Latest construction progress

32.6%

DLD inspection, 25 Jun 2026

Developer's stated date

Q4 2026

Binghatti project page, accessed 11 Oct 2026

Date at launch and latest record

Q1 2026 to Q2 2027

Broker listing, Oct 2024; Continental Club developer field, Oct 2026

Binghatti Hillviews handover date: the latest position

Binghatti Hillviews, a 37 residential floor Binghatti tower in Dubai Science Park, has a registered completion date of 1 April 2026 at the Dubai Land Department (DLD). That date has passed. Binghatti’s project page now gives Q4 2026, and Continental Club’s DLD-based record lists a developer-supplied date of Q2 2027. Full project details are on the Binghatti Hillviews page.

The last published DLD inspection, on 25 June 2026, recorded 32.6% complete (DLD project register via Continental Club, inspection 25 June 2026). The register extract of 4 October 2026 showed no newer figure.

Binghatti Hillviews handover date by building

Hillviews is a single tower, DLD project 3321, with 1,581 registered units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Binghatti Hillviews (DLD project 3321) 32.6%, 25 Jun 2026 1 Apr 2026 Q4 2026 (Binghatti); Q2 2027 (Continental Club developer field); Apr 2026 (Property Finder, Propsearch)
For comparison: Binghatti Hills (DLD project 3053) 90%, 24 Jul 2026 See Binghatti Hills handover date Q2 2026 (Binghatti)

How the Binghatti Hillviews handover date has changed

Date Event Source
1 Oct 2024 Sales open at AED 824,000; the DLD register records construction start on 1 October 2024 and completion on 1 April 2026 Property Finder; DLD via Mitchells
Oct 2024 Brokers advertise handover in Q1 2026 Al Fariq Properties, 17 Oct 2024
31 Dec 2025 DLD inspection: about 13% Continental Club (32.6% less 19.27 points)
1 Apr 2026 Registered completion date passes DLD register
25 Jun 2026 DLD inspection: 32.6% DLD via Continental Club
Oct 2026 Binghatti page shows Q4 2026; Continental Club record shows Q2 2027 Binghatti; Continental Club

The 18 month programme filed at launch was not met. The registered date has not been updated on the register, but the developer’s own published date has moved from Q1 2026 at launch to Q4 2026. On 10 October 2026 Dubai Handover listed the tower as 192 days past its registered date.

What the Binghatti Hillviews handover date means for payments

Binghatti’s plan is 20% on booking, 50% during construction in five instalments, and 30% at 100% completion. The 30% balance, about AED 256,000 on an AED 853,000 studio, follows the real completion date. With the tower about a third built in June 2026, part of the construction instalments were also still to fall due.

What to check before relying on the Binghatti Hillviews date

  1. The SPA date and grace period. The three published dates span more than a year, and only the SPA binds the developer.
  2. Whether the unit is a resale. Almost all 1,581 units were sold by September 2026, so many buyers take over an existing contract and its remaining instalments.
  3. The latest DLD inspection. The last public reading is from June 2026. The Dubai REST app shows the current figure for project 3321.
  4. The project name and number. Binghatti Hills (3053) and Binghatti Hillviews (3321) are different towers, and their dates are often confused.

Questions buyers also ask

Is Binghatti Hillviews finished?

No. It was 32.6% complete at the DLD inspection of 25 June 2026 and was still listed as under construction on 4 October 2026 (Mitchells).

What is the Binghatti Hillviews completion date?

The completion date on file at DLD is 1 April 2026. That date has passed. Binghatti's page gives Q4 2026 and Continental Club's record gives Q2 2027.

Has the Binghatti Hillviews handover date been delayed?

Yes. At launch in October 2024 the tower was advertised for Q1 2026, and the registered date was 1 April 2026. Binghatti now gives Q4 2026, and the tower was a third built in June 2026.

What is the Binghatti Hills View handover date?

Binghatti Hillviews, sometimes searched as Binghatti Hills View, has a registered completion date of 1 April 2026, now passed, and a Binghatti date of Q4 2026. It is a different project from Binghatti Hills, which was 90% complete in July 2026.