Handover date

When is the Binghatti Hillside handover date?

Updated 11 October 2026 Binghatti Hillside

Short answer

Binghatti Hillside's registered completion date was 30 June 2026, and Binghatti still lists Q2 2026 on its project page. The DLD inspection on 17 September 2026 recorded the tower 80% complete, up from 70.04% on 19 May 2026. Both dates have passed with no handover announced and no revised date published, so the date in each buyer's SPA and its grace period now matter most.

Registered completion date (DLD)

30 Jun 2026

DLD register, project 3481; passed

Latest construction progress

80%

DLD inspection, 17 Sep 2026

Developer's stated date

Q2 2026

Binghatti project page, accessed 11 Oct 2026

Progress in the last four months

+9.96 points

70.04% on 19 May 2026 to 80% on 17 Sep 2026

Binghatti Hillside handover date: the latest position

Binghatti Hillside has passed its registered completion date of 30 June 2026 without a handover. Binghatti’s own project page still says Q2 2026. The tower is a 411 unit building in Dubai Science Park, covered in full on the Binghatti Hillside page.

The Dubai Land Department inspected the site on 17 September 2026 and recorded it 80% complete. That is the most recent official figure. The register, checked on 4 October 2026, still shows the old date of 30 June 2026 and the status under construction. A passed date on the register means the record has not been updated, not that the building is finished.

Binghatti Hillside handover date by building

Binghatti Hillside is a single tower, so one row covers the whole project.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Binghatti Hillside (DLD project 3481, 411 units) 80%, 17 Sep 2026 30 Jun 2026 Q2 2026 (Binghatti, accessed 11 Oct 2026); June 2026 (Propsearch, updated 18 Jan 2026)

Binghatti has two other towers nearby with similar names. Binghatti Hills was 90% complete at its 24 July 2026 inspection, and Binghatti Hillviews was 32.6% complete on 25 June 2026. They are separate projects with separate dates.

How the Binghatti Hillside handover date has changed

Date What was published Source
31 Jan 2025 Construction start registered with DLD DLD register via Mitchells
11 Aug 2025 On sale with an estimated completion of Q2 2026 My Dubai Properties listing
18 Jan 2026 Estimated handover June 2026 Propsearch
19 May 2026 70.04% complete at DLD inspection DLD register via Continental Club
30 Jun 2026 Registered completion date passes DLD register
17 Sep 2026 80% complete at DLD inspection DLD register via Continental Club
11 Oct 2026 Binghatti page still shows Q2 2026, no new date Binghatti

The published date has not moved. What has changed is that the calendar has overtaken it. Between May and September 2026 the tower gained 9.96 points of progress, so about a fifth of the work recorded by DLD remained at the last inspection.

What the Binghatti Hillside handover date means for payments

Binghatti’s published plan is 20% on signing, 50% during construction and 30% on completion. Data Habibi lists a 10/50/40 version, with 40% due at handover. Either way, the largest single payment falls due at completion, so the later handover also moves that payment later. On a studio bought at about AED 776,000, the 30% completion payment is about AED 232,800, and under the 40% version it is about AED 310,400.

What to check before relying on the Binghatti Hillside date

  1. The completion date and grace period in the buyer’s SPA. The Q2 2026 date on Binghatti’s page is no longer a usable guide.
  2. The latest DLD inspection for project 3481, through DLD’s project status service. A new inspection after 17 September 2026 will show whether the pace has held.
  3. Which payment plan the contract uses, 20/50/30 or 10/50/40, since the share due at handover differs by 10% of the price.
  4. That the unit is in Hillside, not Hills or Hillviews, the two other Binghatti towers in Dubai Science Park.

Questions buyers also ask

Is Binghatti Hillside finished?

No. The DLD inspection on 17 September 2026 recorded it 80% complete, and the register still lists it as under construction (Mitchells, 4 October 2026). No handover has been announced.

What is the Binghatti Hillside completion date?

The registered completion date on the DLD register is 30 June 2026. That date has passed, and the register has not been updated with a new one as of 4 October 2026.

Has the Binghatti Hillside handover date been delayed?

Yes, against the published dates. Binghatti and Propsearch both gave Q2 2026 or June 2026. The tower was 80% complete on 17 September 2026, so it will hand over later than that. Binghatti has not given a new date.

How many buildings does Binghatti Hillside have?

One. The DLD register lists a single building with 411 units: 320 studios, 82 one bedroom apartments and 9 shops, per Binghatti.

Sources