Handover date

When is the Binghatti Flare handover date?

Updated 11 October 2026 Binghatti Flare

Short answer

Binghatti Flare has registered completion dates of 15 June 2027 for Binghatti Flare 02 and 14 July 2027 for Binghatti Flare 01 at the Dubai Land Department (DLD), and Binghatti's own date is Q2 2027. At the DLD inspection of 19 June 2026, Flare 01 was 20% complete and Flare 02 17.83%. The two towers have different dates, so the date for the tower named in the SPA is the one that applies.

Registered completion dates (DLD)

15 Jun 2027 and 14 Jul 2027

Flare 02 and Flare 01, via Continental Club

Latest construction progress

20% and 17.83%

Flare 01 and Flare 02, DLD inspection, 19 Jun 2026

Developer's stated date

Q2 2027

Binghatti project page, accessed 11 Oct 2026

Portal estimates

Jun 2027 to Q3 2027

Propsearch (Jun 2027); DirectDXB listing for Flare 01 (Q3 2027)

Binghatti Flare handover date: the latest position

Binghatti Flare, two Binghatti towers in JVT District 2, is due for completion in mid 2027. The Dubai Land Department (DLD) register holds a registered completion date of 15 June 2027 for Binghatti Flare 02 and 14 July 2027 for Binghatti Flare 01, and Binghatti’s project page says Q2 2027. Full project details are on the Binghatti Flare page.

At the DLD inspection of 19 June 2026, Flare 01 was 20% complete and Flare 02 17.83% (DLD project register via Continental Club, inspection 19 June 2026). No newer reading had been published by 4 October 2026 (Mitchells).

Binghatti Flare handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Binghatti Flare 01 (DLD project 4006, 845 units) 20%, 19 Jun 2026 14 Jul 2027 Q2 2027 (Binghatti); Q3 2027 (DirectDXB listing)
Binghatti Flare 02 (DLD project 4008, 613 units) 17.83%, 19 Jun 2026 15 Jun 2027 Q2 2027 (Binghatti)

Flare 01 is the taller tower, with 40 residential floors above a podium; Flare 02 has 34 (Binghatti). The smaller tower is registered to finish a month earlier, although it was slightly behind Flare 01 at the June inspection.

How the Binghatti Flare handover date has changed

Date Event Source
Jul 2025 Launch at an event in Egypt; first DLD sales registered on 9 July 2025 Propsearch; Mitchells
15 Jul 2025 Construction start registered for both towers; completion filed for June and July 2027 DLD via Mitchells
18 Jun 2026 Site video published JRE Dubai
19 Jun 2026 DLD inspection: Flare 01 at 20%, Flare 02 at 17.83% DLD via Continental Club
Oct 2026 Binghatti still lists Q2 2027; one Flare 01 listing shows Q3 2027 Binghatti; DirectDXB

The registered dates have not moved since launch. The only difference between sources is the Q3 2027 shown on one developer stock listing for Flare 01, which sits just after its 14 July 2027 registered date.

What the Binghatti Flare handover date means for payments

Binghatti’s published plan is 20% on booking, 50% during construction and 30% on completion. An alternative plan for Flare 01, 10% down and 60% during construction, also leaves 30% for handover (DirectDXB, September 2026). At about 20% built in June 2026, most of the construction instalments were still ahead, and the 30% balance follows the actual completion of the buyer’s own tower.

What to check before relying on the Binghatti Flare date

  1. The tower in the SPA. Flare 01 and Flare 02 are separate DLD projects with dates a month apart.
  2. The latest progress reading. The last public figures are from 19 June 2026. The Dubai REST app shows DLD’s current figure for projects 4006 and 4008.
  3. The SPA date versus Q3 2027. If the SPA gives a later date than the registered one, the SPA is what the buyer can enforce.
  4. When the large instalments fall. On the 10/60/30 plan, more of the price is paid during construction than on the 20/50/30 plan.

Questions buyers also ask

Is Binghatti Flare finished?

No. Both towers are under construction. At the DLD inspection of 19 June 2026, Flare 01 was 20% complete and Flare 02 17.83% (DLD project register via Continental Club).

What is the Binghatti Flare completion date?

The DLD register holds 15 June 2027 for Binghatti Flare 02 (project 4008) and 14 July 2027 for Binghatti Flare 01 (project 4006). Binghatti markets the project as Q2 2027.

When will Binghatti Flare 01 be ready?

Flare 01, the taller tower with 845 units, has a registered completion date of 14 July 2027 and was 20% built on 19 June 2026. One developer listing in October 2026 gave Q3 2027 for it (DirectDXB).

When will Binghatti Flare 02 be ready?

Flare 02, with 613 units, has a registered completion date of 15 June 2027 and was 17.83% built on 19 June 2026.

Has the Binghatti Flare handover date been delayed?

Not so far. The launch date of Q2 2027 and the registered dates of June and July 2027 are unchanged as of October 2026. The June 2026 progress readings were about 20% after 11 months of a 24 month programme.

Sources

  1. Mitchells Commercial Realty, Binghatti Flare 01 DLD registry (opens in a new tab)mitchellscommercialrealty.com · registry as at 4 Oct 2026
  2. Mitchells Commercial Realty, Binghatti Flare 02 DLD registry (opens in a new tab)mitchellscommercialrealty.com · registry as at 4 Oct 2026
  3. Propsearch, Binghatti Flare (opens in a new tab)propsearch.ae · updated 31 Jul 2026