When is the Binghatti Amberhall handover date?
Short answer
Binghatti Amberhall's registered completion date at the Dubai Land Department (DLD) is 28 February 2026, and Binghatti's own page still says Q1 2026. The last published DLD inspection, on 30 April 2026, recorded the tower 38.03% complete. The registered date has passed and no revised date has been published, so the date in each buyer's SPA, and its grace period, is the one to rely on.
Registered completion date (DLD)
28 Feb 2026
DLD project 3552, via Continental Club; passed
Latest construction progress
38.03%
DLD inspection, 30 Apr 2026
Developer's stated date
Q1 2026
Binghatti project page, accessed 11 Oct 2026
Days past the registered date
224
Dubai Handover, 10 Oct 2026
Binghatti Amberhall handover date: the latest position
Binghatti Amberhall, a Binghatti tower of apartments, offices and shops in JVC District 13, has a registered completion date of 28 February 2026 at the Dubai Land Department (DLD). That date has passed. Binghatti’s project page still says the tower is expected to be completed by Q1 2026, and no revised date has been filed or announced. Full project details are on the Binghatti Amberhall page.
The last published DLD inspection, on 30 April 2026, recorded 38.03% complete (DLD project register via Continental Club, inspection 30 April 2026). The register extract published on 4 October 2026 still showed that figure, so there is no public progress reading after April.
Binghatti Amberhall handover date by building
DLD files Amberhall as one project, number 3552, with 710 units. Continental Club’s register record describes it as three buildings at the same site, but all share one completion date and one progress figure.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Amberhall (DLD project 3552) | 38.03%, 30 Apr 2026 | 28 Feb 2026 | Q1 2026 (Binghatti); Mar 2026 (Propsearch) |
How the Binghatti Amberhall handover date has changed
| Date | Event | Source |
|---|---|---|
| 15 Feb 2025 | Bookings open; construction start registered the same day | Property Finder; DLD register |
| 3 Mar 2025 | Project registered with DLD, completion date 28 Feb 2026; Binghatti markets Q1 2026 | Data Dubai (DLD register); Binghatti |
| 30 Apr 2026 | DLD inspection: 38.03% complete, two months after the registered date | DLD via Continental Club |
| 4 Oct 2026 | Register still shows 28 Feb 2026 and 38.03% | Mitchells |
| 10 Oct 2026 | Listed as 224 days past the registered date | Dubai Handover |
The date itself has not been changed on the register or by Binghatti. What has changed is the gap between that date and the site. A one year programme for a building with three basements, a podium and residential floors above left little margin, and the April inspection showed it was not met. Dubai Handover’s daily snapshots show the same 28 February 2026 date and 38% figure throughout August and September 2026.
What the Binghatti Amberhall handover date means for payments
Binghatti’s plan is 20% on signing, 50% during construction and 30% on completion. The 30% completion payment falls due when the building is completed, so a later completion also pushes back the last and largest single payment. The construction instalments in between are tied to progress, and at 38% built in April 2026 part of that 50% was still to come.
What to check before relying on the Binghatti Amberhall date
- The SPA completion date and grace period. The registered date is behind, so the delay clauses in the SPA decide what a buyer can claim, not the published quarter.
- A current progress figure. The last public reading is from 30 April 2026. DLD’s project status service in the Dubai REST app shows any newer inspection for project 3552.
- Which payment milestones are certified. Ask which construction instalments are already due under the SPA and which wait for further progress.
- Commercial versus residential units. The 710 units include offices and shops. Any building-level date applies to all of them, but commercial buyers may have different SPA terms.
Questions buyers also ask
Is Binghatti Amberhall finished?
No. The DLD register lists it as under construction, and the last published inspection, on 30 April 2026, recorded 38.03% complete (DLD project register via Continental Club). The register extract published on 4 October 2026 showed no newer figure (Mitchells).
What is the Binghatti Amberhall completion date?
The completion date on file at DLD is 28 February 2026. Property Finder shows the same date and Propsearch estimates March 2026. That date passed with the project at well under half built.
Has the Binghatti Amberhall handover date been delayed?
Yes, in practice. The launch target was Q1 2026, with a one year build from a 15 February 2025 start. Binghatti has not published a new date, but the April 2026 inspection put the tower at 38.03%, so Q1 2026 was not met.
How much is due at the Binghatti Amberhall handover?
Under Binghatti's 20/50/30 plan, 30% of the price is due on completion. That payment moves with the actual completion date, not the registered one.