Handover date

When is the Aura Prestige handover date?

Updated 11 October 2026 Aura Prestige

Short answer

Aura Prestige has a registered completion date of 1 November 2026, but the DLD inspection on 1 October 2026 recorded the building only 40.06% complete. At the pace recorded since April 2026, about 3.9 percentage points a month, finishing would take until about early 2028. Agents have marketed Q4 2026 or Q1 2027, and no revised date had been published by 11 October 2026.

Registered completion date (DLD)

1 Nov 2026

DLD register via Continental Club

Latest construction progress

40.06%

DLD inspection, 1 Oct 2026

Dates in marketing

Q4 2026 to Q1 2027

Property Finder, Proprain, Grand Reve Realty, JRE

Progress since April 2026

+19.4 points

20.65% on 30 Apr to 40.06% on 1 Oct 2026, DLD

Aura Prestige handover date: the latest position

Aura Prestige is registered with the Dubai Land Department (DLD) for completion on 1 November 2026. The DLD inspection on 1 October 2026 recorded the building 40.06% complete, so that date will pass with the building unfinished. Full project details are on the Aura Prestige page.

No revised date had been published by 11 October 2026. Marketing has given Q4 2026 (Property Finder, Proprain) and Q1 2027 (Grand Reve Realty, JRE). Neither matches the progress on site. At the rate recorded between April and October 2026, about 3.9 percentage points a month, the remaining 60% would take about 15 months, which points to early 2028. That is a calculation from DLD figures, not a developer date.

Aura Prestige handover date by building

Aura Prestige is a single building of 81 units, registered as DLD project 3788 in the Nadd Hessa district of Dubai Silicon Oasis.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Aura Prestige (LG+G+8, 81 units) 40.06% (1 Oct 2026) 1 Nov 2026 Nov 2026 (Property Finder); Q1 2027 (Grand Reve Realty, JRE)

How the Aura Prestige handover date has changed

Date What happened Source
1 Jun 2025 Registered construction start; first DLD inspection, 0% DLD register via Dubai Data
25 Sep 2025 Registered with the DLD, completion 1 Nov 2026 DLD register via Dubai Data
Feb 2026 First registered sales Dubai Data
30 Apr 2026 20.65% complete DLD register via Continental Club
1 Oct 2026 40.06% complete; registered date still 1 Nov 2026 DLD register via Continental Club

The registered date has not moved, but the gap between it and the work on site has widened. The schedule gave 17 months from construction start to completion. After 16 months, the building was 40% built. Agents’ dates already vary by a quarter, from Q4 2026 to Q1 2027, and both look early against the DLD figures. A developer can apply to the DLD to extend a registered completion date, and a new date would appear in the project status record.

What the Aura Prestige handover date means for payments

The plan is 20% down payment, 40% during construction and 40% on handover (Grand Reve Realty; JRE; Proprain). For a 2 bedroom at the registered median of AED 1.53 million, the handover payment is about AED 612,000. If completion moves into 2027 or 2028, that payment moves with it, and so does any mortgage drawdown. Instalments during construction that are tied to progress milestones would also follow the slower pace.

What to check before relying on the Aura Prestige date

  1. The completion date and grace period in the SPA, and what the contract allows if completion runs well past 1 November 2026.
  2. Any new completion date filed with the DLD, shown in the project status service, before relying on a portal’s Q4 2026 or Q1 2027.
  3. Any resale listing that gives a 2026 handover. On the 1 October 2026 inspection, the building was 40% built.
  4. Mortgage approval validity, since an approval issued for a 2026 handover may expire before the building is finished.

Questions buyers also ask

When will Aura Prestige be completed?

The DLD register says 1 November 2026, but the building was 40.06% complete on 1 October 2026, so it will not be finished by then. At the pace recorded since April 2026, completion would come around early 2028. The developer has not published a new date.

Has the Aura Prestige handover date been delayed?

In practice, yes. The registered date of 1 November 2026 has not been changed in the register, but the building was only 40.06% complete a month before it. Some agents already give Q1 2027.

How far along is Aura Prestige?

40.06% at the DLD inspection on 1 October 2026, up from 20.65% on 30 April 2026 and 0% on 1 June 2025 (Continental Club; Dubai Data).

Will Aura Prestige be ready by the end of 2026?

No. At 40.06% complete on 1 October 2026, the building would need to gain about 20 percentage points a month to finish by December, five times the pace recorded since April 2026.

Sources

  1. Continental Club, projects with handover in 2026 (DLD project register) (opens in a new tab)continentalclub.ae · inspection 1 Oct 2026, accessed 11 Oct 2026
  2. Dubai Data, Aura Prestige (opens in a new tab)datadubai.ae · data through 30 Sep 2026
  3. Proprain, Aura Prestige at DSO (opens in a new tab)proprain.com · accessed 11 Oct 2026
  4. JRE, Aura Prestige (opens in a new tab)jre.ae · accessed 11 Oct 2026
Request a Unit Review