Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Athlon by Aldar handover date?

Updated 1 October 2026 Athlon by Aldar

Short answer

The Athlon by Aldar handover date is 31 May 2028 for the phase 1 villas and townhouses and 30 September 2028 for phase 2, the registered completion dates on the Dubai Land Department (DLD) register. At DLD inspections on 23 July 2026, phase 1 was 18.22% complete and phase 2 was 12.31% complete. The Rise by Athlon apartments are a separate, later phase, registered for 30 December 2029 and 30 January 2030 depending on the building, and were under 1% built in May 2026.

Registered completion date (DLD), phase 1

31 May 2028

Phase 2: 30 Sep 2028. DLD register, via Mitchells, 26 Sep 2026

Latest construction progress, phase 1

18.22%

DLD inspection, 23 Jul 2026. Phase 2: 12.31%

Developer's stated date

Q2 2028 and Q3 2028

Phase 1 and phase 2, developer supplied, via Continental Club, Sep 2026

Rise by Athlon apartments, registered

Dec 2029 to Jan 2030

DLD register, via Mitchells, Sep 2026

Athlon by Aldar handover date: the latest position

The Athlon by Aldar villas and townhouses are due in two phases. Phase 1, with 893 homes, has a registered completion date of 31 May 2028, and phase 2, with 599 homes, has a registered completion date of 30 September 2028, both on the Dubai Land Department register. At DLD inspections on 23 July 2026, phase 1 was 18.22% complete and phase 2 was 12.31% complete. Prices, plans and the wider community are covered on the Athlon by Aldar page.

Progress picked up in 2026. Between the inspections of 13 April and 23 July 2026, phase 1 gained 5.06 points and phase 2 gained 3.9 points. To meet 31 May 2028, phase 1 would need to complete the remaining 81.78% in about 22 months from its July inspection. The Rise by Athlon apartments are a separate phase that started construction on 15 January 2026 and is not due until December 2029 or January 2030.

Athlon by Aldar handover date by building

The DLD register splits Athlon into two villa projects and four apartment projects, each with its own completion date. Portals that give one date for “Athlon” are describing one of these phases only.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Athlon phase 1, 893 villas and townhouses (project 3143) 18.22%, 23 Jul 2026 31 May 2028 Q2 2028 (developer, via Continental Club); 31 May 2028 (Property Finder)
Athlon phase 2, 599 villas and townhouses (project 3145) 12.31%, 23 Jul 2026 30 Sep 2028 Q3 2028 (developer, via Continental Club; Bayut, 3 Nov 2025)
Rise by Athlon 1, Azul, Teal and Magenta towers, 650 homes 0.68%, 19 May 2026 30 Dec 2029 Dec 2029 (Property Finder)
Rise by Athlon 2, Neon and Cyan towers, 407 homes 0.08%, 19 May 2026 30 Jan 2030 Q1 2030 (Continental Club)
Rise by Athlon 3, Grid and Tempo, 120 homes 0.48%, 19 May 2026 30 Jan 2030 Q1 2030 (Continental Club)
Rise by Athlon 4, Foundry, 66 homes 0.56%, 19 May 2026 30 Dec 2029 Not published separately

Phase 1 includes the 76 Horizon premium villas and phase 2 the 75 Pillars premium villas, according to the developer’s filed descriptions on the register.

How the Athlon by Aldar handover date has changed

No change to the villa dates has been published since launch.

Date What happened Source
1 May 2024 Aldar unveiled Athlon with 1,492 villas and townhouses, sales from 7 May at AED 2.8 million. Aldar, via Zawya
4 May 2024 Launch payment schedule gave handover as May 2028. Petkovic Properties
9 May 2024 Aldar said the first two phases sold out in 48 hours, worth AED 4.1 billion. Aldar
16 Jul 2024 Construction start registered for both villa phases. DLD register
15 Jan 2026 Construction start registered for the four Rise by Athlon apartment projects. DLD register
23 Jul 2026 Phase 1 at 18.22%, phase 2 at 12.31%. Completion dates still 31 May 2028 and 30 September 2028. DLD register, via Mitchells

What the Athlon by Aldar handover date means for payments

A large share of the price falls due at handover. The launch schedule published on 4 May 2024 asked 5% at booking, 5% at SPA signing, then instalments in November 2024, May 2025, March 2026, November 2026 and July 2027, with 40% on handover in May 2028. Some units were sold on a 70/30 version with 30% at handover. Property Finder lists 5/55/40, and Bayut lists four plans Aldar has used, with 20% to 40% due on handover. On the AED 2.8 million starting price, a 40% handover payment is AED 1.12 million. For Rise by Athlon, Aldar’s portal lists 5% on booking, 75% during construction and 20% on completion, according to OffPlan Insider.

What to check before relying on the Athlon by Aldar date

  1. Whether your villa is in phase 1 or phase 2. The two are four months apart on the register, and the SPA will name the project.
  2. Which Rise by Athlon building your apartment is in. Rise 1 and Rise 4 are registered for 30 December 2029, Rise 2 and Rise 3 for 30 January 2030.
  3. How the 40% handover payment will be funded, since under the launch plan it is the largest single instalment and falls due at handover.
  4. The DLD progress for project 3143 or 3145, through DLD’s project status enquiry service, and the grace period stated in your SPA.

Questions buyers also ask

What is the Athlon by Aldar completion date?

31 May 2028 for phase 1 (893 villas and townhouses) and 30 September 2028 for phase 2 (599 homes). These are the registered completion dates on the DLD register (via Mitchells, 26 Sep 2026). The Rise by Athlon apartments are registered for 30 December 2029 or 30 January 2030.

Is Athlon by Aldar finished?

No. At DLD inspections on 23 July 2026, phase 1 was 18.22% complete and phase 2 was 12.31% complete. The Rise by Athlon apartment buildings were between 0.08% and 0.68% complete at inspections on 19 May 2026. Nothing at Athlon has been handed over.

When will the Rise by Athlon apartments be ready?

Rise by Athlon 1 (650 homes) and Rise by Athlon 4 (66 homes) are registered for completion on 30 December 2029. Rise by Athlon 2 (407 homes) and Rise by Athlon 3 (120 homes) are registered for 30 January 2030. Property Finder lists December 2029 (DLD register via Mitchells; Property Finder, both accessed 1 Oct 2026).

Has the Athlon by Aldar handover date been delayed?

No change has been published. At the May 2024 launch, brokers gave May 2028 for the first homes, and the DLD register still holds 31 May 2028 for phase 1. Phase 2 has carried 30 September 2028 on the register (Petkovic Properties, 4 May 2024; DLD register, Sep 2026).

How much is due at the Athlon by Aldar handover?

Under the launch plan most buyers took, 40% of the price is due on handover, with 5% at booking, 5% at SPA signing and the rest in instalments to July 2027. Some units were sold on a 70/30 plan with 30% at handover (Petkovic Properties, 4 May 2024). Property Finder lists 5/55/40.

Sources

  1. Property Finder, Rise By Athlon 1 (opens in a new tab)propertyfinder.ae · accessed 1 Oct 2026