Handover date

When is the Aspirz by Danube handover date?

Updated 11 October 2026 Aspirz by Danube

Short answer

Aspirz by Danube is due for handover in Q4 2028, and the DLD register lists a completion date of 31 December 2028. The Dubai Land Department (DLD) recorded the tower 5.08% complete at its inspection of 30 July 2026, and Danube's internal inspection of 30 September 2026 put it at 11%, with piling and shoring finished. The date has not changed since launch, but with most of the structure still to build, the next two DLD inspections matter.

Registered completion date (DLD)

31 Dec 2028

DLD register via Continental Club, updated 1 Oct 2026

Latest construction progress (DLD)

5.08%

DLD inspection, 30 Jul 2026

Developer's stated date

Q4 2028

Danube Properties, accessed 11 Oct 2026

Danube's own progress figure

11%

Danube internal inspection, 30 Sep 2026

Aspirz by Danube handover date: the latest position

Aspirz by Danube is due for handover in Q4 2028, and the Dubai Land Department (DLD) register gives a completion date of 31 December 2028. Danube’s date and the register date fall in the same quarter. See the Aspirz by Danube project page for prices, unit types and payment plans.

The latest DLD inspection, on 30 July 2026, recorded 5.08%. Danube’s own inspection on 30 September 2026 recorded 11%, listing shoring and piling as completed, the main contractor on board, and excavation and substructure works in progress.

Aspirz by Danube handover date by building

Aspirz is a single 40 floor tower over two basements and seven podium levels, registered with 706 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Aspirz By Danube (DLD project 3838) 5.08% (30 Jul 2026) 31 Dec 2028 Q4 2028 (Danube); 11% complete by Danube’s count (30 Sep 2026)

Offices on floors 2 to 15 and hotel apartments on floors 17 to 40 are in the same building and share one completion date.

How the Aspirz by Danube handover date has changed

Date What happened Source
7 Jul 2025 Danube announces Aspirz as its latest launch Danube Properties
Aug 2025 Launch coverage: 698 units, completion Q4 2028 Construction World, 25 Aug 2025
1 Nov 2025 Construction start on the DLD register Continental Club
6 Apr 2026 DLD inspection: about 1.1% Continental Club
30 Jul 2026 DLD inspection: 5.08% Continental Club
30 Sep 2026 Danube inspection: 11%, piling and shoring complete Danube Properties
Oct 2026 Register completion date 31 December 2028; Danube still gives Q4 2028 Continental Club; Danube

The April figure is worked back from the 3.96 point rise the register records between the April and July inspections. The date has not moved. At about 1% a month between April and July, the pace will need to rise sharply once the superstructure starts for the tower to finish by December 2028.

What the Aspirz by Danube handover date means for payments

On the most common broker-listed plan, 10% is paid on booking, 60% during construction and 30% on handover. On a AED 850,000 studio that leaves AED 255,000 due at handover. The 30 month post-handover version takes 9% on handover and spreads 30% over 30 months after it, so a later handover also pushes the final instalment later. Danube markets Aspirz on its 1% monthly plan, under which instalments are tied to months rather than to construction progress.

What to check before relying on the Aspirz by Danube date

  1. The SPA date for the unit type. Offices and hotel apartments share the tower but may be sold under different contract terms.
  2. DLD progress rather than Danube’s internal figure. The 11% figure is Danube’s own; the independent DLD figure was 5.08% two months earlier.
  3. How many monthly instalments fall before the superstructure rises. On a 1% monthly plan, a large share is paid while the tower is still below ground.
  4. The management terms for the hotel apartments, since Danube sells them furnished with hotel-style services, which affect running costs after handover.

Questions buyers also ask

When will Aspirz by Danube be ready?

Danube says Q4 2028, and the DLD register gives 31 December 2028.

What is the Aspirz by Danube completion date?

31 December 2028 is the completion date on the DLD register for project 3838.

Has the Aspirz handover date changed since launch?

No. Danube announced Q4 2028 when it launched Aspirz in 2025 and still gives Q4 2028. The register date of 31 December 2028 falls in the same quarter.

How much of Aspirz by Danube is built?

5.08% at the DLD inspection of 30 July 2026. Danube's own inspection of 30 September 2026 put overall progress at 11%, with shoring and piling done and excavation and substructure works under way.

Sources

  1. DLD project register via Continental Club, Aspirz by Danube (opens in a new tab)continentalclub.ae · inspection 30 Jul 2026, register updated 1 Oct 2026
  2. Danube Properties, Aspirz construction progress (opens in a new tab)danubeproperties.com · inspection dated 30 Sep 2026
  3. Danube Properties, Aspirz portfolio page (opens in a new tab)danubeproperties.com · accessed 11 Oct 2026