Handover date

When is the Artistry One Residences handover date?

Updated 11 October 2026 Artistry One Residences

Short answer

Artistry One Residences has a registered completion date of 9 February 2029, and Select Group gives Q1 2029. The only DLD inspection, on 14 January 2026, recorded 0%, before the registered construction start of 9 February 2026. Artistry Two, the twin tower, carries the same registered date, and one data source shows a later Q4 2029 for Artistry One that the register does not support.

Registered completion date (DLD)

9 Feb 2029

DLD register via Continental Club, updated 5 Oct 2026

Latest construction progress

0%

DLD inspection, 14 Jan 2026

Developer's stated date

Q1 2029

Select Group, accessed 11 Oct 2026

Other date shown

Q4 2029

Continental Club developer field, Oct 2026

Artistry One Residences handover date: the latest position

Artistry One Residences is registered for completion on 9 February 2029, and Select Group gives Q1 2029 for handover. The register entry is DLD project number 4259, filed by Select Global Development. Full project details are on the Artistry One Residences page.

Construction had not started when the DLD last inspected the site, on 14 January 2026, and recorded 0%. The register gives 9 February 2026 as the construction start, exactly three years before the registered completion date. No later DLD percentage had been published by 5 October 2026.

Artistry One Residences handover date by building

Select Group is building two towers under the Artistry name in d3. They are registered as separate projects with the same dates.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Artistry One Residences (36 storeys, 232 units) 0% (14 Jan 2026) 9 Feb 2029 Q1 2029 (Select Group); Q4 2029 (Continental Club developer field)
Artistry Two Residences (235 units) 0% (14 Jan 2026) 9 Feb 2029 2029 (Select Group); Feb 2029 (Property Finder)

Property Finder describes Artistry Two as a 38 storey tower; Select Group’s own page says 37 floors.

How the Artistry One Residences handover date has changed

Date Event Source
14 Jan 2026 DLD inspection records 0% at both towers DLD register via Continental Club
15 Jan 2026 Artistry One registered with DLD DXB Off Plan
20 Jan 2026 Private sales open, 1 bedrooms from AED 2.3 million Insider Real Estate
4 Feb 2026 Artistry Two launched; handovers “in 2029” Select Group via Construction Week
9 Feb 2026 Registered construction start for both towers DLD register
5 Oct 2026 Register still shows 9 Feb 2029 Continental Club

The date has held since launch. The only outlier is Continental Club’s developer field showing Q4 2029 for Artistry One, while its own page for Artistry Two shows Q1 2029.

What the Artistry One Residences handover date means for payments

The plan is 20% on booking, then 10% within 6, 12 and 18 months, and 50% on handover (EZRE). The construction instalments are tied to time from booking, so a buyer who booked in January 2026 has paid 50% by about July 2027, around 18 months before the registered completion date. The other 50%, about AED 1.15 million on a 1 bedroom at AED 2.3 million, waits for handover. Select Group’s site also mentions a 10% booking deposit, so the split can vary by release.

What to check before relying on the Artistry One Residences date

  1. Which tower the unit is in. Artistry One is DLD project 4259 and Artistry Two is 4261, with separate escrow records.
  2. The completion date written in the SPA, given the Q1 2029 and Q4 2029 figures in circulation.
  3. The first DLD inspection after the February 2026 start. It is the first figure that will show the actual pace.

Questions buyers also ask

When will Artistry One Residences be completed?

The registered completion date is 9 February 2029 (DLD register via Continental Club, updated 5 October 2026). Select Group gives Q1 2029.

When will Artistry Two Residences be handed over?

Artistry Two, DLD project 4261, also has a registered completion date of 9 February 2029 and showed 0% at its 14 January 2026 inspection. Select Group said at its launch on 4 February 2026 that handovers would start in 2029. Property Finder lists it as Artistry Phase 2, completing in February 2029.

Has the Artistry One Residences handover date changed?

No. Select Group gave Q1 2029 when sales opened in January 2026, and the register holds 9 February 2029. The Q4 2029 on one data page is the only later figure.

How much is due at handover at Artistry One Residences?

50% of the price. The plan is 20% on booking, 30% during construction and 50% on handover; on a 1 bedroom at AED 2.3 million, that is about AED 1.15 million.