Handover date

When is the Arabian Ranches 3 handover date?

Updated 12 October 2026 Arabian Ranches 3

Short answer

Most of Arabian Ranches 3 is already handed over, and the three phases still under construction have registered completion dates of 31 October 2026 for Anya, 30 December 2026 for Anya 2 and 30 September 2027 for May (DLD register via Dubai Handover and Tohid Fetrat). DLD inspections put Anya at 98.5% complete in late July 2026. Anya 2 was recorded 100% complete and Ready on the DLD register at the inspection of 7 October 2026, and May at the inspection of 10 August 2026. Property Finder shows Anya for December 2026, two months after its registered date, so the date in each buyer's SPA is the one that applies.

Anya, registered completion date (DLD)

31 Oct 2026

DLD register via Dubai Handover, accessed 1 Oct 2026

Anya, latest construction progress

98.5%

DLD inspection, late Jul 2026

May, the last phase, registered completion

30 Sep 2027

100% complete and Ready on the DLD register, inspection 10 Aug 2026

Anya, portal estimate

Dec 2026

Property Finder, accessed 1 Oct 2026

Arabian Ranches 3 handover date: the latest position

Arabian Ranches 3 is mostly handed over. Emaar has delivered the phases launched between 2019 and 2022, and three townhouse phases remain: Anya, registered for completion on 31 October 2026, Anya 2 on 30 December 2026 and May on 30 September 2027. More on the community: Arabian Ranches 3.

Two of the three are now recorded finished. Anya 2 was recorded 100% complete and Ready on the DLD register at the inspection of 7 October 2026, up from 97% on 15 July 2026. May was recorded 100% complete and Ready at the inspection of 10 August 2026, up from 95.07% on 5 June 2026, more than a year before its registered date (DLD register via Continental Club). Anya was 98.5% complete at its late July 2026 inspection, and its registered date of 31 October 2026 had not passed as of 12 October 2026.

Arabian Ranches 3 handover date by phase

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
Anya (492 townhouses) 98.5%, late Jul 2026 31 Oct 2026 Oct 2026 (Propsearch); Dec 2026 (Property Finder)
Anya 2 (362 townhouses) 100%, Ready, 7 Oct 2026 30 Dec 2026 Dec 2026 (Property Finder)
May (298 townhouses) 100%, Ready, 10 Aug 2026 30 Sep 2027 Sep 2027 (Property Finder, Propsearch)
Raya Handed over Passed Marked ready (Property Finder)
Sun, Joy, Ruba Handed over Passed Q2 2022, Aug 2022, Mar 2023 (Propsearch)
Bliss, Caya, June, Elie Saab, Sun Phase 3 Handed over Passed Marked ready (Property Finder)

Unit counts are from the DLD register via Dubai Handover and Tohid Fetrat. Propsearch gives May a lower estimate of 270 units.

How the Arabian Ranches 3 handover date has changed

The three remaining phases have kept or beaten their launch timelines so far.

Date What happened Source
Dec 2022 to Jan 2023 Anya goes on sale. Emaar’s schedule puts the final 20% at 100% completion in October 2026. Property Finder; Elan Real Estate, 9 Jan 2023
22 May 2023 Anya’s registered construction start. DLD register via Dubai Handover
26 Jun 2023 Anya 2 goes on sale, with completion expected on 30 December 2026. Property Finder
9 Aug 2023 May goes on sale, with completion expected on 30 September 2027. Property Finder; Tohid Fetrat
Oct 2025 Anya 81.07% complete; May 85.64% complete. Property Finder
Jun to Jul 2026 May 95.07%, Anya 2 97%, Anya 98.5%. Registered dates unchanged. DLD inspection data
10 Aug 2026 May recorded 100% complete and Ready on the DLD register. DLD register via Continental Club
7 Oct 2026 Anya 2 recorded 100% complete and Ready on the DLD register. DLD register via Continental Club

Raya is the one phase in the community with a published date that passed: its project page had listed June 2026, and Property Finder now marks it ready. Property Finder’s December 2026 date for Anya is two months later than the registered 31 October 2026, and is a portal estimate rather than a registered change.

What the Arabian Ranches 3 handover date means for payments

All three phases are sold out from Emaar, so the launch plans apply only to original buyers. For Anya, Emaar’s January 2023 schedule was 10% at booking, seven 10% instalments during construction and 20% at 100% completion, though Property Finder shows a 10/20/70 split for the same phase. Anya 2 and May launched on 10% at booking, 80% during construction and 10% on handover (Property Finder). On these plans most of the price is already paid, and the final 10% or 20% falls due when Emaar issues the completion notice.

A buyer purchasing a resale unit in Anya, Anya 2 or May before handover usually takes on the instalments the seller still owes Emaar, including the handover payment.

What to check before relying on the Arabian Ranches 3 date

  1. Whether the unit is in Anya or Anya 2. They share a name and sit side by side, but their registered dates are two months apart, 31 October and 30 December 2026.
  2. The DLD inspection date behind the percentage. Anya’s 98.5% dates from late July 2026. Anya 2 and May are recorded 100% complete and Ready, from inspections on 7 October and 10 August 2026.
  3. The completion date and grace period in the original SPA. For a resale, ask the seller for the Emaar SPA, since that date, not a portal estimate, governs handover.
  4. What is still owed to Emaar. Ask the seller for an Emaar statement of account showing the balance due at completion.

Questions buyers also ask

When will Arabian Ranches 3 be ready?

Most of it already is. Sun, Joy, Ruba, Raya, Bliss, Caya, June, Elie Saab and Sun Phase 3 are handed over. The last three phases have registered completion dates of 31 October 2026 (Anya), 30 December 2026 (Anya 2) and 30 September 2027 (May), per the DLD register.

What is the Anya Arabian Ranches 3 handover date?

The DLD register gives Anya a completion date of 31 October 2026, and Anya was 98.5% complete at its late July 2026 inspection (Dubai Handover). Propsearch also estimates October 2026. Property Finder lists December 2026.

Has the Anya handover date been delayed?

No change is recorded. Emaar's launch payment schedule in January 2023 put the final instalment at 100% construction completion in October 2026, and the registered date is still 31 October 2026. Property Finder's December 2026 date is a portal estimate, not a registered change.

When will Anya 2 and May be handed over?

Anya 2 is registered for completion on 30 December 2026. It was 97% built on 15 July 2026 and was recorded 100% complete and Ready on the DLD register at the inspection of 7 October 2026. May is registered for 30 September 2027. It was 95.07% built on 5 June 2026 and was recorded 100% complete and Ready at the inspection of 10 August 2026 (DLD register via Continental Club).

Is Arabian Ranches 3 finished?

Not fully. Emaar has handed over the earlier phases, starting with Sun in Q2 2022, Joy in August 2022 and Ruba in March 2023 (Propsearch), but Anya was still under construction in October 2026. Anya 2 and May are recorded 100% complete and Ready on the DLD register.

Sources

  1. Continental Club, Arabian Ranches III Anya 2 (DLD registry) (opens in a new tab)continentalclub.ae · DLD inspection 7 Oct 2026, accessed 12 Oct 2026
  2. Continental Club, Arabian Ranches III May (DLD registry) (opens in a new tab)continentalclub.ae · DLD inspection 10 Aug 2026, accessed 12 Oct 2026
  3. Propsearch, Anya at Arabian Ranches 3 (opens in a new tab)propsearch.ae · updated 25 Aug 2026, accessed 1 Oct 2026
  4. Propsearch, May at Arabian Ranches 3 (opens in a new tab)propsearch.ae · updated 6 Apr 2026, accessed 1 Oct 2026
  5. Property Finder, Anya Phase 2 (opens in a new tab)propertyfinder.ae · accessed 1 Oct 2026
  6. Property Finder, May by Emaar (opens in a new tab)propertyfinder.ae · accessed 1 Oct 2026
  7. Propsearch, Arabian Ranches 3 (opens in a new tab)propsearch.ae · accessed 28 Sep 2026