Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Amali Island handover date?

Updated 11 October 2026 Amali Island

Short answer

Amali Properties says Amali Island is scheduled for completion by the end of 2027, while the DLD register still shows a completion date of 31 March 2027. The latest DLD inspection, on 11 June 2026, recorded 16.37% complete, up from 11.65% in January. The March 2027 date dates from launch, before the marine works were finished, and is unlikely to be met.

Registered completion date (DLD)

31 Mar 2027

DLD project register via Continental Club

Latest construction progress

16.37%

DLD inspection, 11 Jun 2026

Developer's stated date

End of 2027

Amali Properties via Arabian Business, 12 Dec 2025

Date at launch

Q1 2027

Business Traveller, Jul 2024; Gulf Business, Oct 2024

Amali Island handover date: the latest position

Amali Properties says Amali Island is scheduled for completion by the end of 2027 (Arabian Business, 12 December 2025). The DLD project register still records a completion date of 31 March 2027, the Q1 2027 target given at launch, and agency listings such as Palmera still show Q1 2027. Prices, villa types and the payment plan are on the Amali Island page.

The latest DLD inspection, on 11 June 2026, recorded 16.37% complete, up 4.72 points from 21 January 2026. At about 1 point a month, the March 2027 date cannot be met. The end of 2027 date needs about 4.5 points a month from June 2026, which depends on villa construction speeding up once the marine works are done.

Amali Island handover date by building

All 24 villas sit in one DLD project, number 3038, on a single platform made by joining the Uruguay and São Paulo islands.

Project Construction progress (DLD, date) Registered completion date Developer or portal date
Amali Island, 24 villas 16.37%, 11 Jun 2026 31 Mar 2027 End of 2027 (Amali, Dec 2025); Q1 2027 (Palmera, Engel and Völkers)

The register does not split progress by villa. Infrastructure shared by every villa, including quay walls, canal edges and shoreline protection, had to be completed before vertical building could begin (Arabian Business).

How the Amali Island handover date has changed

Date What happened Source
2 May 2024 Amali Island unveiled as Amali Properties’ first project Gulf Business
1 Jul 2024 Construction start registered DLD register
8 Jul 2024 Handover expected by Q1 2027; 22 of 24 villas sold on launch day Business Traveller
29 Oct 2024 Ground breaking; piling due from March 2025; completion Q1 2027 Gulf Business
12 Dec 2025 DUTCO appointed; completion by end of 2027; sold out Arabian Business
21 Jan 2026 DLD inspection records 11.65% DLD register
11 Jun 2026 DLD inspection records 16.37% DLD register

The move from Q1 2027 to the end of 2027 came with the change of contractor for the marine and main works. The registered date of 31 March 2027 has not followed it.

What the Amali Island handover date means for payments

The usual plan is 10% on booking, 50% during construction and 40% on handover (Continental Club; Business Traveller). On the 5 bedroom DLD median of AED 50 million, about AED 20 million is due at handover, and on the AED 220 million Villa Avatea about AED 88 million.

What to check before relying on the Amali Island date

  1. Whether the SPA date has been amended to match the developer’s end of 2027 date, or still shows Q1 2027.
  2. Whether DLD has approved a new completion date, which the project status enquiry will show.
  3. The next DLD inspection. A figure near 30% by the end of 2026 would support end of 2027.
  4. The access and berth arrangements at handover, since an island villa cannot be used until boat access and utilities are running.

Questions buyers also ask

Is Amali Island finished?

No. It was 16.37% complete at the DLD inspection on 11 June 2026. Marine works and the main villa construction package were handed to DUTCO in December 2025.

What is the Amali Island completion date?

The registered completion date is 31 March 2027. Amali Properties now gives the end of 2027 (Arabian Business, 12 Dec 2025).

Has the Amali Island handover date been delayed?

Yes. At launch in 2024 and at the October 2024 ground breaking, Amali gave Q1 2027. In December 2025 it gave the end of 2027, about nine months later. The DLD register has not been updated to match.

When will Amali Island villa owners get their keys?

Amali has not published a handover schedule by villa. All 24 villas are in one DLD project with one registered date, so the developer's end of 2027 completion is the current guide.

Sources

  1. Palmera, Amali Island villas (opens in a new tab)palmera.realestate · accessed 11 Oct 2026
Request a Unit Review