Handover date

When is the Alba Tower handover date?

Updated 11 October 2026 Alba Tower

Short answer

Alba Tower has a registered completion date of 30 June 2028, while broker listings still market a Q4 2027 handover. The latest DLD inspection, on 27 July 2026, recorded 30.92% complete. The register's date is the later of the two, and buyers' SPAs may carry either.

Registered completion date (DLD)

30 Jun 2028

DLD project register via Continental Club

Latest construction progress

30.92%

DLD inspection, 27 Jul 2026

Broker handover date

Q4 2027

Tanami Properties; Gold Pillars; HomeSearch, accessed 11 Oct 2026

Registered construction start

30 Sep 2024

DLD register via Mitchells

Alba Tower handover date: the latest position

Alba Tower has a registered completion date of 30 June 2028 in the DLD project register. Broker listings still show a Q4 2027 handover, so the register is about two quarters later than the date most buyers see. Prices, sizes and the payment plan are on the Alba Tower page.

The last DLD inspection, on 27 July 2026, recorded 30.92% complete. The tower is 22 months into a registered build of about 45 months, and a third of the work is done, which is broadly consistent with the June 2028 date but leaves little room for Q4 2027.

Alba Tower handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Alba Tower, Jumeirah Garden City (DLD project 3059, 73 homes) 30.92%, 27 Jul 2026 30 Jun 2028 Q4 2027 (Tanami Properties, Gold Pillars, HomeSearch); 29 Jun 2028 (PropertyStellar)

Alba Tower is one building of two basements, a ground floor, eight floors and a roof, so all homes share the one date. The register lists 73 homes; brochures say 72. Mitchells counts 41 registered sales by 11 September 2026, so more than half the homes have owners waiting on the same date. The sales are mostly 1 bedrooms of 416 to 853 sq ft and 2 bedrooms of 686 to 840 sq ft.

How the Alba Tower handover date has changed

Date What happened Source
Q1 2024 Launched with a Q4 2027 handover target AiGents Realty
30 Sep 2024 Construction start registered; completion registered for 30 Jun 2028 DLD register via Mitchells
27 Jul 2026 DLD inspection records 30.92% DLD register
Oct 2026 Broker listings still show Q4 2027 Tanami Properties; HomeSearch

The Q4 2027 date was the launch target. The register has carried 30 June 2028 since construction was registered, so the gap is between the marketed date and the filed date rather than a recent change.

What the Alba Tower handover date means for payments

Under the main plan, 39% of the price is due on handover, after 20% at booking and 41 monthly instalments of 1% (Tanami Properties). Under the 15% discount plan for 1 bedrooms, 29% is due on handover. On a 1 bedroom at the registered median of AED 905,000, a 39% handover payment is about AED 353,000. If handover comes in June 2028 rather than late 2027, that payment moves back by about six months. The 41 monthly instalments run from the booking date, so a buyer who booked at launch in early 2024 would pay the last of them in mid 2027, about a year before the registered completion date.

What to check before relying on the Alba Tower date

  1. Which date the SPA states, Q4 2027 or 30 June 2028, and the grace period after it.
  2. The developer named in the SPA and escrow, since some broker pages credit Reportage Properties while the register shows Century Seven Properties.
  3. The next DLD inspection after July 2026, to see whether progress keeps pace with a mid 2028 finish.

Questions buyers also ask

When will Alba Tower be completed?

The DLD register gives 30 June 2028. Broker listings show Q4 2027.

Is Alba Tower delayed?

The registered date of 30 June 2028 is about two quarters later than the Q4 2027 handover still used in listings. The registered date itself has not passed, and at 30.92% in July 2026 the tower was roughly in line with a mid 2028 finish.

How much of Alba Tower is built?

30.92% at the DLD inspection of 27 July 2026 (DLD register via Continental Club and Mitchells).

Do all Alba Tower apartments hand over together?

Yes. Alba Tower is a single building, DLD project 3059, with 73 homes under one completion date.

Sources

  1. Mitchells, Alba Tower DLD registry and registered sales (opens in a new tab)mitchellscommercialrealty.com · register as at 4 Oct 2026
  2. Tanami Properties, Alba Tower payment plan (opens in a new tab)tanamiproperties.com · accessed 11 Oct 2026
  3. Gold Pillars, Alba Tower brochure (opens in a new tab)goldpillars.ae · accessed 11 Oct 2026
  4. PropertyStellar, Alba Tower (opens in a new tab)propertystellar.com · accessed 11 Oct 2026
  5. AiGents Realty, Alba Tower (opens in a new tab)aigentsrealty.com · accessed 11 Oct 2026