When is the AG AUM Residence handover date?
Short answer
AG AUM Residence has a registered completion date of 30 November 2028, and the developer gives Q4 2028. The last Dubai Land Department inspection, on 24 March 2026, recorded the tower 2.44% complete, 16 months into a 48-month schedule. Meeting the date would need much faster progress than the register has shown so far.
Registered completion date
30 Nov 2028
DLD project register via Continental Club
Latest construction progress
2.44%
DLD inspection, 24 Mar 2026
Developer's stated date
Q4 2028
Continental Club (developer supplied); Property Finder
Progress, Jul 2025 to Mar 2026
+2.05 points
DLD project register via Continental Club
AG AUM Residence handover date: the latest position
AG AUM Residence is registered with the Dubai Land Department (DLD) for completion on 30 November 2028. At the last DLD inspection, on 24 March 2026, the tower was 2.44% complete, 16 months after construction started on 30 November 2024. Prices, sizes and the payment plan are on the project page: AG AUM Residence.
The developer gives Q4 2028, and Property Finder lists November 2028, both matching the register. No newer DLD reading had been published by October 2026, so the March figure is the latest official one.
AG AUM Residence handover date by building
AG AUM Residence is one tower with 260 units, registered as “AG AUM Residence” (DLD project 3262) in Wadi Al Safa 5, the DLD district for Dubailand Residence Complex.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| AG AUM Residence (260 units, 3B + G + 13 + R) | 2.44% (24 Mar 2026) | 30 Nov 2028 | Q4 2028 (developer, via Continental Club); Nov 2028 (Property Finder); Q3 2027 and Q4 2028 (Aigents Realty) |
How the AG AUM Residence handover date has changed
| Date | Event | Source |
|---|---|---|
| 30 Nov 2024 | Booking opens and construction starts; completion registered for 30 Nov 2028 | Property Finder; DLD via Continental Club |
| 21 Jul 2025 | DLD inspection, about 0.4% | DLD via Continental Club |
| 24 Mar 2026 | DLD inspection: 2.44% | DLD via Continental Club |
| 21 May 2026 | Latest registered sale, a 1 bedroom at AED 886,085 | DLD via Continental Club |
| Oct 2026 | Register still shows 30 Nov 2028; developer gives Q4 2028 | Continental Club; Property Finder |
The date has not changed since launch. The issue is the pace. The registered schedule allows 48 months, and a third of that time had passed by March 2026 with 2.44% recorded. To finish by 30 November 2028, the tower would need about three points a month from April 2026, against about a quarter of a point a month between July 2025 and March 2026. High-rise progress often speeds up once the structure rises, so the next inspection matters more than a straight-line projection.
What the AG AUM Residence handover date means for payments
Every published plan has 15% paid at booking and 45% during construction, which Property Finder says is split into six instalments. The final 40% is listed as due after handover by Property Finder and on handover by Aigents Realty. If it is due on handover, it will move with the actual completion date. If it is a post-handover plan, the instalments only start once the building is delivered, so a later handover delays them too.
What to check before relying on the AG AUM Residence date
- The construction instalment triggers. If the six instalments are tied to dates rather than progress stages, buyers could pay 60% of the price on a site that is still at the foundation stage.
- The SPA completion date and grace period, against the registered 30 November 2028.
- That the unit is in DLD project 3262. AG Properties also sells AUM 99 Residences nearby, with its own Q1 2029 date.
- The next DLD inspection, which will be the first reading since March 2026.
Questions buyers also ask
Is AG AUM Residence finished?
No. The DLD inspection of 24 March 2026 recorded the tower 2.44% complete. Its registered completion date is 30 November 2028.
What is the AG AUM Residence completion date?
30 November 2028 on the DLD register (via Continental Club). The developer and Property Finder give Q4 2028. Aigents Realty also shows Q3 2027 in one section, which does not match the register.
Has the AG AUM Residence handover date been delayed?
No revised date has been filed. The registered date is still 30 November 2028. The concern is pace: the tower gained only 2.05 points between July 2025 and March 2026.
When will AUM 99 Residences be ready?
AUM 99 Residences is a separate AG Properties project in the same community, listed by Property Finder for Q1 2029. Its DLD registration and dates are separate from AG AUM Residence.