Handover date

When is the 171 Garden Heights handover date?

Updated 11 October 2026 171 Garden Heights

Short answer

171 Garden Heights has a registered completion date of 31 December 2026 on the Dubai Land Department (DLD) register, with Q4 2026 given as the handover. The latest DLD inspection, on 8 June 2026, recorded 33.66% progress. At the 2.51 points a month recorded so far, Continental Club estimates completion around August 2028, so a revised date from JAD Global is likely to matter more than the registered one.

Registered completion date (DLD)

31 Dec 2026

DLD register via Continental Club, updated 7 Oct 2026

Latest construction progress

33.66%

DLD inspection, 8 Jun 2026

Developer's stated date

Q4 2026

Developer-supplied, Continental Club; Propsearch Dec 2026

Pace-based estimate

Aug 2028

Continental Club estimate at 2.51 points a month, not a developer date

171 Garden Heights handover date: the latest position

171 Garden Heights, DLD project 3127 in Jumeirah Garden City, has a registered completion date of 31 December 2026. Continental Club lists a developer-supplied handover of Q4 2026 and Propsearch gives December 2026. Prices, sizes and the payment plan are on the 171 Garden Heights page.

The DLD inspection of 8 June 2026 recorded 33.66% progress, and the register had no newer inspection in its 7 October 2026 update. With about two thirds of the work left and under seven months to the registered date, the building would need close to 10 points a month. It has averaged 2.51 points a month.

171 Garden Heights handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
171 Garden Heights (159 units) 33.66%, 8 Jun 2026 31 Dec 2026 Q4 2026 (developer-supplied); Dec 2026 (Propsearch)

It is a single G+2P+8 building. JAD Global’s second project nearby, JAD 288, is a separate DLD project registered for 31 December 2027.

How the 171 Garden Heights handover date has changed

Date Event Source
19 Jun 2024 First DLD inspection: 0% DLD register via Continental Club
11 Sep 2024 Registered construction start; completion set for 31 December 2026 DLD register via Continental Club
Oct 2024 Sales launch from AED 1.1 million Propsearch
2 Apr 2025 DLD inspection: 3.95% DLD register via Continental Club
16 Jul 2025 DLD inspection: 6.72% DLD register via Continental Club
12 Nov 2025 DLD inspection: 14.33% DLD register via Continental Club
24 Feb 2026 DLD inspection: 26.22% DLD register via Continental Club
8 Jun 2026 DLD inspection: 33.66% DLD register via Continental Club
7 Oct 2026 Register still shows 31 December 2026; pace-based estimate 21 August 2028 Continental Club

The registered date has stayed at 31 December 2026 since launch. The fastest stretch was between November 2025 and February 2026, when progress rose almost 12 points in about three and a half months. The following inspection added 7.44 points over a similar period.

What the 171 Garden Heights handover date means for payments

The plan is 10% down payment, 50% during construction and 40% on handover. The 40% falls when the developer issues its handover notice after completion, not on the registered date. On a 1 bedroom at the DLD median of AED 1,229,745, that is about AED 491,900. If completion moves into 2028 in line with the pace-based estimate, the final payment moves with it.

What to check before relying on the 171 Garden Heights date

  1. Whether the construction instalments follow dates or progress. With 50% due during construction, a date-based schedule could run ahead of the build.
  2. The grace period in the SPA beyond 31 December 2026, and what the contract says once it is used up.
  3. The next DLD inspection result, the first since June 2026.

Questions buyers also ask

When will 171 Garden Heights be completed?

The registered completion date is 31 December 2026. The building was 33.66% complete on 8 June 2026, and at its recorded pace Continental Club estimates 100% around 21 August 2028.

Is 171 Garden Heights finished?

No. It was 33.66% complete at the latest DLD inspection on 8 June 2026.

Has the 171 Garden Heights handover date been delayed?

Not formally. The DLD register still shows 31 December 2026 in its 7 October 2026 update, and JAD Global had not published a new date. Progress is well behind what that date needs.

How much is paid at 171 Garden Heights handover?

40% of the price, after 10% down and 50% during construction (Continental Club, Propsearch).