When is the 105 Residences by Kamdar handover date?
Short answer
105 Residences by Kamdar has a registered completion date of 28 February 2027, and Kamdar Developments gives Q1 2027. The DLD inspection of 13 July 2026 recorded the building 10.1% complete, up from about 3.6% in April 2026. At that pace, the registered date looks very hard to meet, and the date in each buyer's SPA, with its grace period, is the one to rely on.
Registered completion date (DLD)
28 Feb 2027
DLD register via Mitchells, 4 Oct 2026
Latest construction progress
10.1%
DLD inspection, 13 Jul 2026
Developer's stated date
Q1 2027
Kamdar Developments, accessed 11 Oct 2026
Portal date
31 Mar 2027
DubaiHaus, accessed 11 Oct 2026
105 Residences by Kamdar handover date: the latest position
105 Residences by Kamdar is registered for completion on 28 February 2027, and Kamdar Developments says the building will be ready to move in from Q1 2027. Full project details are on the 105 Residences by Kamdar page.
The building is a long way behind that date. The DLD inspection of 13 July 2026 recorded 10.1% progress, with under eight months left. Reaching 100% by 28 February 2027 would take about 12 percentage points a month from July. The pace between the April and July 2026 inspections was about 2 points a month (Continental Club). Kamdar has not published a revised date.
105 Residences by Kamdar handover date by building
The project is one building, DLD project number 3310, in JVC District 13.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| 105 Residences by Kamdar (105 units, G+P+5) | 10.1% (13 Jul 2026) | 28 Feb 2027 | Q1 2027 (Kamdar); 31 Mar 2027 (DubaiHaus) |
How the 105 Residences by Kamdar handover date has changed
| Date | Event | Source |
|---|---|---|
| 9 Dec 2024 | Launch from AED 640,000, Kamdar’s first public project | Construction Week |
| 1 Mar 2025 | Registered construction start | DLD register via Mitchells |
| 2 Apr 2026 | DLD inspection, about 3.6% | Derived from Continental Club |
| 13 Jul 2026 | DLD inspection, 10.1% | DLD register via Continental Club |
| 4 Oct 2026 | Register still shows 28 Feb 2027 | Mitchells |
The launch coverage in December 2024 did not state a handover quarter. Kamdar’s own site gives Q1 2027, which matches the registered date, and neither has changed. Portals differ slightly: DubaiHaus shows 31 March 2027, a month after the registered date. The gap is between the date and the progress, not between sources.
What the 105 Residences by Kamdar handover date means for payments
Two plans appear on developer price lists (EZRE, October 2026). Under 10/20/70, the 20% construction share is paid in two 10% instalments and 70% falls due at handover, so most of the price waits for completion. A later completion delays that payment. Under the post-handover plan, 10% is paid on booking, 35% during construction and 5% on handover, and the remaining 50% runs for 50 months at 1% a month, so its start date also moves with the handover.
What to check before relying on the 105 Residences by Kamdar date
- The completion date and grace period in the SPA. At 10.1% in July 2026, the grace period may decide when a late completion becomes a contract issue.
- The next DLD inspection. The July 2026 figure is the latest; a September or October inspection would show whether the pace has picked up.
- Whether construction instalments are tied to stages or dates. Stage-based instalments slow down with the build; dated ones do not.
- The escrow account at Mashreq Bank for DLD project 3310, checked in the Dubai REST app.
Questions buyers also ask
When will 105 Residences by Kamdar be completed?
The registered completion date is 28 February 2027 (DLD register via Mitchells, 4 October 2026). Kamdar says the building will be ready to move in from Q1 2027. The DLD recorded 10.1% progress on 13 July 2026.
Is 105 Residences by Kamdar on schedule?
The progress figures suggest not. The building was 10.1% complete in July 2026, with under eight months to the registered date. Progress rose 6.47 points between the April and July 2026 inspections (Continental Club). Kamdar has not announced a new date.
Has the 105 Residences by Kamdar handover date been delayed?
Not formally. Kamdar's site still says Q1 2027 and the register still holds 28 February 2027. No revised date had been published by 11 October 2026.
How much is due at handover at 105 Residences by Kamdar?
It depends on the plan. Under 10/20/70, 70% is due on handover. Under the post-handover plan, 5% is due on handover and 50% follows over 50 months at 1% a month.