Illustration: construction cranes on a residential tower at dusk
Handover date

When is the 09 Life Residences handover date?

Updated 11 October 2026 09 Life Residences

Short answer

09 Life Residences has a registered completion date of 1 December 2027, and the handover target published for the developer is Q3 2027. The last Dubai Land Department inspection, on 26 August 2026, recorded the building 6.84% complete. Progress so far has been about half a point a month, so both dates depend on a much faster build from late 2026.

Registered completion date

1 Dec 2027

DLD project register via Continental Club

Latest construction progress

6.84%

DLD inspection, 26 Aug 2026

Developer's handover target

Q3 2027

Ezre, Grand Reve, Miva

Construction start

1 Nov 2025

DLD project register

09 Life Residences handover date: the latest position

09 Life Residences is registered with the Dubai Land Department (DLD) for completion on 1 December 2027. The handover target published for Deniz Properties is Q3 2027 (Ezre; Grand Reve; Miva, 30 January 2026). Prices, sizes and payment plans are on the project page: 09 Life Residences.

The DLD inspection of 26 August 2026 recorded the building 6.84% complete. Between 17 December 2025 and 26 August 2026 it gained about 4.5 points, roughly half a point a month. Reaching 100% by December 2027 would mean about 6 points a month from September 2026, and Q3 2027 would need faster still.

09 Life Residences handover date by building

09 Life Residences is one building with 127 apartments in Wadi Al Safa 5, the DLD area name for Dubailand Residence Complex (DLD project number 4250).

Building Construction progress (DLD, date) Registered completion date Developer or portal date
09 Life Residences (127 units) 6.84% (26 Aug 2026) 1 Dec 2027 Q3 2027 (Ezre, Grand Reve, Miva); Q4 2027 (Continental Club)

How the 09 Life Residences handover date has changed

Date Event Source
1 Nov 2025 Construction start recorded; registered completion 1 December 2027 DLD via Continental Club
17 Dec 2025 DLD inspection: 2.37% DLD via Continental Club
27 Jan 2026 Launch at the Ritz-Carlton DIFC; studios from AED 675,000 Ain Alemirate, 28 Jan 2026
30 Jan 2026 Handover given as Q3 2027 Miva
1 Jun 2026 DLD inspection: 5.54% DLD via Continental Club
26 Aug 2026 DLD inspection: 6.84% DLD via Continental Club
Oct 2026 Handover still listed as Q3 2027 Ezre, Grand Reve

The date has not changed since launch. The developer’s previous building, 08 Life Residences in International City 2, gives a comparison: its registered completion date was 31 May 2026, and it was 64.87% complete at the DLD inspection of 26 August 2026 (DLD register via Continental Club).

What the 09 Life Residences handover date means for payments

Deniz advertises 20% down and 40% payable over three years after handover. Grand Reve gives the full split as 20% on booking, 40% during construction, 10% on handover and 30% over three years after handover. On that plan, the handover date fixes when the 10% is called and starts the three-year post-handover schedule. Ezre lists a variant with 4% on handover and 36% after, and Continental Club shows 40% on handover, so the amount due at handover varies by contract.

What to check before relying on the 09 Life Residences date

  1. The completion date written into the SPA, since Q3 2027 and 1 December 2027 are a quarter apart.
  2. The next DLD inspection after August 2026, which shows whether the build has moved past the slow early stage.
  3. Progress at 08 Life Residences, as the clearest guide to how Deniz has handled its own registered dates.

Questions buyers also ask

When will 09 Life Residences be completed?

The registered completion date is 1 December 2027 (DLD project register). Brokers give Q3 2027 as the developer's handover target.

Is 09 Life Residences finished?

No. It was 6.84% complete at the DLD inspection of 26 August 2026, about nine months after construction started.

Has the 09 Life Residences handover date been delayed?

Not yet. The Q3 2027 target given at launch in January 2026 still appeared on broker pages in October 2026, and the registered date of 1 December 2027 is unchanged.

How much is due at 09 Life Residences handover?

It depends on the plan. Grand Reve lists 10% on handover and 30% over three years after it; Ezre lists a version with 4% on handover and 36% after; Continental Club shows 40% on handover.

Sources

  1. DLD project register via Continental Club, 09 Life Residences (opens in a new tab)continentalclub.ae · inspection 26 Aug 2026; registry updated 8 Oct 2026
  2. Mitchells, 09 Life Residences DLD registry and registered sales (opens in a new tab)mitchellscommercialrealty.com · registry status 27 Sep 2026
  3. Grand Reve Realty, 09 Life Residences (opens in a new tab)grandreverealty.com · accessed 11 Oct 2026
  4. Ezre, 09 Life Residences (opens in a new tab)ezre.ae · accessed 11 Oct 2026
Request a Unit Review