Urban Park Residences
Urban Venture's 16-storey, 187-unit tower in Dubai Sports City. Registered completion date of 1 April 2026 has passed; 67.62% built on 30 July 2026. Prices, sizes and payment plans.
Short answer
Urban Park Residences, a 187-unit tower by Urban Venture in Dubai Sports City, has a registered completion date of 1 April 2026, which has passed. The last Dubai Land Department (DLD) inspection, on 30 July 2026, recorded it 67.62% complete. The developer's stated handover was Q2 2026, while several portals now show Q4 2026. Studios launched from AED 674,809 and DLD sales in October 2026 were AED 685,156 for a studio and AED 1,005,000 for a 1 bedroom.
- Status
- under construction
- Handover date
- DLD registered completion 1 Apr 2026 (passed); developer Q2 2026; portals now list Q4 2026
- Construction
- 67.62% complete (DLD inspection, 30 Jul 2026)
- Payment plan
- Sources differ: 50/50, 30/70 and 20/80 plans listed, with 50% to 80% due on handover
- Starting price
- Studios from AED 674,809 at launch (2024); from AED 740,892 in 2026 listings
Registered completion date
1 Apr 2026 (passed)
DLD project register via Continental Club
Construction progress
67.62%
DLD inspection, 30 Jul 2026
Homes
187 apartments
56 studios, 73 one bed, 58 two bed (DLD register via Continental Club)
Median sale price per sq ft
AED1,423
80 DLD sales, 28 Apr 2025 to 5 Oct 2026 (Mitchells)
When will Urban Park Residences be handed over?
The Dubai Land Department (DLD) register still gives Urban Park Residences a completion date of 1 April 2026. That date has passed. The last DLD inspection, on 30 July 2026, recorded the building 67.62% complete, so the registered date no longer reflects the site. The developer’s stated handover was Q2 2026 (Continental Club, developer supplied). Several portals have since moved to Q4 2026, including JRE, which gives December 2026, and Casadior.
Continental Club’s own projection, based on the pace between inspections of about 2.29 points a month, puts 100% at around 2 October 2027. That is a calculation, not a developer commitment. Mitchells notes that a passed registered date means only that the register has not been updated, not that the building is handed over.
Building-by-building dates and how the date has changed: Urban Park Residences handover date.
Urban Park Residences construction update
Construction started on 1 October 2024 (DLD project number 3230). DLD inspections recorded 40.79% on 8 August 2025, 46.00% on 6 January 2026 and 67.62% on 30 July 2026 (DLD register via Continental Club). Progress was slow through late 2025, about five points in five months, then picked up to about 22 points between January and July 2026.
Propsearch, updated 25 August 2026, records the main contractor as Strong Walls Constructions and a project value filed with DLD of AED 69.74 million. The plot was first meant for a different building, Rufi Park View, which was cancelled. The DLD register lists the project as active, with United Bank Limited as the escrow bank.
Urban Park Residences homes and sizes
The tower has two basement levels, a ground floor and 15 upper floors, with 187 apartments (Urban Venture; Propsearch). The DLD unit mix is below.
| Home type | Units | Size |
|---|---|---|
| Studio | 56 | 418 to 436 sq ft |
| 1 bedroom | 73 | 707 to 754 sq ft |
| 2 bedroom | 58 | 1,169 to 1,171 sq ft |
Sizes and unit counts are from the DLD register via Continental Club. Building features listed by the developer include smart home systems and building-wide Wi-Fi, with pools, a gym, a yoga deck and EV charging among the shared facilities.
Urban Park Residences prices and resale
At launch in 2024, studios were priced from AED 674,809, 1 bedrooms from AED 999,754 and 2 bedrooms from AED 1,426,031 (Palmera). Propsearch records a launch price from AED 674,000. Portals in 2026 show a range of AED 740,892 to AED 1,889,428 for remaining developer stock (JRE, OffplanIndex).
Registered sales give a firmer picture. Mitchells counts 80 DLD sales between 28 April 2025 and 5 October 2026, at a median of AED 1,423 per sq ft. By type, the medians were AED 1,721 per sq ft for studios, AED 1,416 for 1 bedrooms and AED 1,328 for 2 bedrooms. Recent DLD sales were:
- a studio of about 418 sq ft for AED 685,156 on 5 October 2026
- a 1 bedroom of about 733 sq ft for AED 1,005,000 on 2 October 2026
- a 2 bedroom of about 1,171 sq ft for AED 1,536,004 on 27 August 2026
Continental Club counts 123 DLD sales since 2024, of which only one was a resale. Property Finder showed 16 listings at AED 722,820 to AED 1.9 million when accessed on 11 October 2026. No RERA service charge budget has been set for the building; completed Dubai Sports City buildings have a median of AED 15.41 per sq ft a year (Continental Club).
Urban Park Residences payment plan
Published plans differ, and none is confirmed on the developer’s own site. Palmera lists 20% on booking, 30% during construction and 50% on handover. OffplanIndex lists a 30/70 plan: 10% down, 20% during construction and 70% on handover. Casadior lists 10% on booking, 10% on signing the SPA and 80% on handover. Continental Club describes an “easy payment plan” with zero down payment. PropertyStellar lists 50% before and 50% after handover. The common point is that most of the price falls due at handover, so the handover date drives when the largest payment is called.
Urban Park Residences developer and delivery record
Urban Venture Real Estate Development, the DLD-registered developer, is building the tower with ARKH Holding (Propsearch). It is a small developer with no other completed Dubai project identified in the DLD register sources used here. On this project, the developer’s Q2 2026 handover and the registered 1 April 2026 date were both missed, with the building about two thirds built in July 2026.
What to check before buying at Urban Park Residences
- A revised completion date from DLD. The registered 1 April 2026 date has passed, and a new date filed with DLD is the reference point for any delay.
- The handover clause and grace period in the SPA, since portals quote dates from Q2 2026 to Q4 2026.
- The exact payment plan in writing, because published plans range from 50% to 80% due on handover.
- Price per sq ft against DLD sales. Studios have sold at around AED 1,600 to AED 1,900 per sq ft, well above 2 bedrooms.
Urban Park Residences location: Dubai Sports City, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Urban Park Residences handover date?
The DLD register gives a completion date of 1 April 2026, but the building was only 67.62% complete at the DLD inspection of 30 July 2026, so that date has passed without completion. The developer's stated handover is Q2 2026 (Continental Club), and JRE and Casadior now list Q4 2026.
What is the Urban Park Residences completion date?
The registered completion date is 1 April 2026 (DLD project register). At its July 2026 rate of about 2.29 points a month, Continental Club estimates the building would reach 100% around October 2027. That is an estimate, not a developer date.
What is the Urban Park Residences price?
Studios launched from AED 674,809, 1 bedrooms from AED 999,754 and 2 bedrooms from AED 1,426,031 (Palmera). In October 2026 a studio sold for AED 685,156 and a 1 bedroom for AED 1,005,000 (DLD via Continental Club).
What is the Urban Park Residences payment plan?
Sources disagree. Palmera lists 20% on booking, 30% during construction and 50% on handover. OffplanIndex lists 30/70 and Casadior 20/80. All put at least half the price on handover.