The Vyne Residences
The Vyne Residences in JVT by Metrical Development: registered completion date 25 November 2026, 80.42% built at the April 2026 DLD inspection, launch price from AED 966,000 and a 10/60/30 payment plan.
Short answer
The Vyne Residences, a 263 unit tower by Metrical Development in Jumeirah Village Triangle (JVT), is due for handover in November 2026. The Dubai Land Department (DLD) register gives a completion date of 25 November 2026, the same month Metrical gave at launch. The last published DLD inspection, on 22 April 2026, recorded 80.42% complete. Sales opened on 15 May 2024 with a launch price from AED 966,000.
- Status
- under construction
- Handover date
- November 2026 (Metrical); registered completion date 25 November 2026 (DLD)
- Construction
- 80.42% complete (DLD inspection, 22 Apr 2026)
- Payment plan
- 10% on booking, 60% during construction, 30% on handover (Data Habibi); one agency lists 20/40/40
- Starting price
- From AED 966,000 at launch (May 2024, Property Finder)
Registered completion date
25 Nov 2026
DLD project register via Continental Club
Construction progress
80.42%
DLD inspection, 22 Apr 2026
Launch price
AED966,000
Property Finder; Data Habibi gives AED 863,000
Median 1 bedroom price
AED1,071,222
223 DLD sales, via Continental Club, Sep 2026
When will The Vyne Residences be handed over?
Metrical Development gives November 2026 for The Vyne Residences. The Dubai Land Department (DLD) register, where it is listed as project 3094, records a completion date of 25 November 2026. Property Finder shows an expected completion of 24 November 2026. Metrical’s project page gave November 2026 as early as December 2024, so the date has not moved since launch.
The last published DLD inspection, on 22 April 2026, recorded 80.42% complete (DLD project register via Continental Club, registry updated 1 October 2026). No newer inspection had been published by 11 October 2026, about six weeks before the registered date.
Building-by-building dates and how the date has changed: The Vyne Residences handover date.
The Vyne Residences construction update
DLD records construction starting on 15 May 2024, the same day sales opened. Property Finder showed 63.72% at an update dated 17 December 2025. The DLD inspection of 22 April 2026 recorded 80.42%, a gain of 16.7 points in about four months. If that pace held, the structure would have reached completion around late summer 2026, though no inspection has confirmed it.
The DLD register describes a ground floor, four commercial and services floors, 16 typical floors and a penthouse level. Metrical calls it a 23 storey building on Al Khail Road in JVT District 5. Propsearch names Al Sayegh Contracting as main contractor and Emirates Engineer Consulting Engineering as consultant. The project value submitted to the Land Department was AED 124.4 million.
The Vyne Residences homes and sizes
| Home type | Units | Typical size |
|---|---|---|
| Studio | 17 | 594 sq ft |
| 1 bedroom | 208 | 700 to 983 sq ft |
| 2 bedroom | 28 | 1,233 to 1,791 sq ft |
| 3 bedroom | 2 | 2,187 to 2,561 sq ft |
| Other units | 8 | 857 to 4,395 sq ft |
Unit counts and sizes are from the DLD register via Continental Club; ranges exclude the smallest and largest 5% of each type. About four in five homes are 1 bedroom apartments. Shared facilities listed by Property Finder include a pool, gym and landscaped gardens.
The Vyne Residences prices and resale
Property Finder records a launch price from AED 966,000; Data Habibi gives AED 863,000. By late September 2026 the DLD register held 281 sales, two of them resales. Medians were:
- Studio: AED 893,222 (17 sales)
- 1 bedroom: AED 1,071,222 (223 sales)
- 2 bedroom: AED 1,699,059 (29 sales)
The overall median works out at about AED 1,428 per sq ft (Continental Club, transactions updated 30 September 2026). Data Dubai counts 57 sales in the trailing 12 months at a median of AED 1.05 million. Recent 1 bedroom sales of about 730 sq ft registered at AED 1,000,000 on 14 September 2026 and AED 1,050,000 on 28 September 2026, below some January 2026 sales of AED 1.2 million for similar units.
The Vyne Residences payment plan
Data Habibi and Harper Wellington list 10% on booking, 60% during construction and 30% on handover. AiGents Realty shows a different split of 20% down, 40% during construction and 40% on handover. On the 1 bedroom median of AED 1,071,222, a 30% handover payment is about AED 321,000. The 4% DLD fee is due on top.
The Vyne Residences developer and delivery record
Metrical Development is registered with DLD as developer number 1283. Continental Club counts 10 projects in the register as of 22 September 2026, seven completed and three under construction, with completed handovers between September 2020 and September 2025. Data Habibi records 953 units delivered, including The Ivy in JVT and The Vybe in JVC, and rates 86% of six tracked projects as delivered within 90 days of the original date. The other active projects are Leven Residences in JVT, due Q4 2027, and S’Vn Residences in JVC, due Q4 2028.
What to check before buying at The Vyne Residences
- Whether the building completion certificate has been issued. The registered date of 25 November 2026 is close, and a new DLD inspection or a completion notice from Metrical will show whether it holds.
- The payment split in the SPA, since agencies list both 10/60/30 and 20/40/40.
- Recent resale and off-plan prices for the same layout. September 2026 sales of 1 bedrooms at AED 1.0 million sit below several sales from earlier in 2026.
- Supply at handover. With 208 one bedroom units completing together, rents for that layout may face competition in the first months.
The Vyne Residences location: Jumeirah Village Triangle, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is The Vyne Residences handover date?
Metrical Development gives November 2026. The DLD register records a completion date of 25 November 2026, and Property Finder shows an expected completion of 24 November 2026 (accessed 11 Oct 2026).
What is The Vyne Residences completion date?
The registered completion date is 25 November 2026. The building was 80.42% complete at the DLD inspection of 22 April 2026, up from 63.72% on 17 December 2025.
What is The Vyne Residences price?
The launch price was from AED 966,000 (Property Finder); Data Habibi records AED 863,000. Registered sales have medians of AED 893,222 for studios and AED 1,071,222 for 1 bedrooms (DLD data via Continental Club, Sep 2026).
What is The Vyne Residences payment plan?
Data Habibi and Harper Wellington list 10% on booking, 60% during construction and 30% on handover. One agency, AiGents Realty, shows 20/40/40. The SPA sets the schedule for each unit.