Illustration: aerial view of a villa community with green spaces
Taraf Holding · Jumeirah Golf Estates

Terra Golf Collection

Taraf's gated collection of 6 bedroom villas and townhouses in Jumeirah Golf Estates. Registered completion date 31 December 2027; DLD recorded 20.05% built on 1 September 2026.

6 bedroom villas and townhouses Updated 11 October 2026

Short answer

Terra Golf Collection has a registered completion date of 31 December 2027 at the Dubai Land Department (DLD), later than the June 2027 and Q2 2027 handover given in earlier listings and in July 2025. The DLD inspection on 1 September 2026 recorded 20.05% complete. Taraf launched the 6 bedroom villas and townhouses in Jumeirah Golf Estates on 14 December 2023, with townhouses from AED 7.24 million and a 60/40 payment plan.

Status
under construction
Handover date
31 Dec 2027 (DLD registered completion date); Q2 2027 given in July 2025, Q4 2027 on current listings
Construction
20.05% complete (DLD inspection, 1 Sep 2026)
Payment plan
60/40: 10% down, 50% in instalments during construction, 40% on handover
Starting price
From AED 7.24 million for a townhouse (launch price list)

Registered completion date

31 Dec 2027

DLD project register via Continental Club

Construction progress

20.05%

DLD inspection, 1 Sep 2026

Homes

77

DLD project description and Taraf, Aug 2025; 84 announced at launch

Price range on launch list

AED 7.24m to AED 20.0m

Kredium price list

When will Terra Golf Collection be handed over?

Terra Golf Collection has a registered completion date of 31 December 2027 at the Dubai Land Department (DLD), under project number 2877. Current listings give Q4 2027 (JRE Dubai; Projects Scout). Earlier dates were sooner: a launch-era listing gave June 2027 (Kredium), and Propsearch recorded a Q2 2027 handover when Taraf appointed its main contractor in July 2025.

The DLD inspection on 1 September 2026 recorded 20.05% complete (DLD project register via Continental Club, inspection 1 September 2026). About 80% of the work, on DLD’s figure, remained with 16 months to the registered date.

Building-by-building dates and how the date has changed: Terra Golf Collection handover date.

Terra Golf Collection construction update

The DLD register gives a construction start of 31 March 2024 and lists the project as under construction (Mitchells, registry as at 4 October 2026). DLD’s filed description is 77 units on 18 plots, with villas of basement, ground and two floors and townhouses of ground and two floors. Al Firas General Contracting was appointed main contractor in July 2025 (Propsearch). The developer’s estimated project value filed with DLD is AED 331,211,000.

Terra Golf Collection homes and sizes

Every home has six bedrooms. Taraf’s August 2025 guide gives these sizes:

Home type Built-up area Plot area
Golf facing standalone villa (Type 1) 8,034 to 8,700 sq ft 4,564 to 4,763 sq ft
Golf facing townhouse 4,773 to 4,836 sq ft 2,439 to 3,687 sq ft

The launch price list also shows villa Types 2, 3 and 4 at 6,434, 6,921 and 8,028 sq ft (Kredium). DLD sale records use the plot figure: a 6 bedroom sold on 14 July 2026 is recorded at 2,439 sq ft, which matches the smallest townhouse plot.

Terra Golf Collection prices and resale

Taraf launched the project on 14 December 2023. The launch price list ran from AED 7.24 million for a 4,671 sq ft townhouse to AED 20,005,000 for an 8,034 sq ft Type 1 villa, with Type 2 villas at AED 14,541,000 and Type 3 at AED 15,643,000 (Kredium). A phase 2 release of 20 furnished villas of 6,921 to 8,700 sq ft is listed from AED 18,805,500 to AED 21,261,450 (JRE Dubai).

DLD has registered 125 sales against the project, the latest on 14 July 2026 at AED 10.95 million for a 6 bedroom on a 2,439 sq ft plot (Mitchells; Propsearch).

Terra Golf Collection payment plan

Taraf describes a 60/40 plan: 60% during construction and 40% on handover (Taraf, 21 August 2025). The launch schedule was:

  • 10% down payment
  • 10% two months later and 10% six months later
  • 10% each at 30%, 40% and 50% construction
  • 40% on handover

(Kredium). The phase 2 release is listed with 10% on booking, 40% during construction and 50% on handover (JRE Dubai).

Terra Golf Collection developer and delivery record

Taraf is the real estate arm of Yas Holding and started selling homes in 2023. Terra Golf Collection was its third project, after Luce on Palm Jumeirah and Terrazzo Residences in JVC; CELLO in JVC followed in January 2024 (Taraf). The DLD register lists the developer entity as Taraf Development, with escrow at Emirates NBD.

What to check before buying at Terra Golf Collection

  1. The SPA date. Listings moved from June 2027 and Q2 2027 to Q4 2027, and DLD holds 31 December 2027.
  2. Which release the unit belongs to. Phase 2 villas carry a 50% handover payment, against 40% on the launch plan.
  3. Built-up area against plot area. DLD records show the plot, so price per sq ft from the register is not comparable with list prices.
  4. The unit count. Sources give 84, 77 and 66 homes, so the plot and unit number in the SPA should match the DLD record.

Terra Golf Collection location: Jumeirah Golf Estates, Dubai

Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.

Questions buyers also ask

What is the Terra Golf Collection handover date?

The registered completion date at DLD is 31 December 2027. Earlier listings gave June 2027, and when Taraf appointed its contractor in July 2025 the handover was Q2 2027 (Propsearch). The DLD inspection on 1 September 2026 recorded 20.05% complete.

What is the Terra Golf Collection completion date?

31 December 2027, as filed with DLD under project number 2877. The registered construction start is 31 March 2024.

What is the Terra Golf Collection price?

The launch price list ran from AED 7.24 million for a 4,671 sq ft townhouse to AED 20,005,000 for an 8,034 sq ft standalone villa (Kredium). A phase 2 release of 20 furnished villas is listed from AED 18,805,500 to AED 21,261,450 (JRE Dubai).

What is the Terra Golf Collection payment plan?

Taraf describes a 60/40 plan, with 60% paid during construction and 40% on handover (Taraf, 21 Aug 2025). The launch schedule was 10% down, 10% after 2 months, 10% after 6 months, then 10% each at 30%, 40% and 50% construction, and 40% on handover (Kredium).

How many homes are in Terra Golf Collection?

Taraf announced 84 homes at launch in December 2023. Its August 2025 guide and the DLD project description give 77 units, and the DLD register counts 66 homes (Mitchells, registry as at 4 October 2026).

Sources

  1. Propsearch, Terra Golf Collection (opens in a new tab)propsearch.ae · updated 26 Mar 2026
  2. Projects Scout, Terra Golf Collection (opens in a new tab)projectsscout.com · accessed 11 Oct 2026