Samana's 198 unit Greek style building in Dubai Studio City. Promised for July 2025, past its 30 April 2026 completion date at 91% built, and now set for February 2027. Prices and plan.

Studio, 1, 2 and 3 bedroom apartments with private pools Updated 11 October 2026

Short answer

Samana Mykonos, a 198 unit building in Dubai Studio City, is not yet handed over. The DLD inspection of 29 September 2026 put it at 91.12% complete, and its registered completion date of 30 April 2026 has passed. Samana Developers now gives February 2027. At launch in February 2023 Samana promised July 2025. Studios launched from about AED 614,000, and the DLD median for a studio is about AED 713,000.

Status
under construction
Handover date
Samana now states February 2027; registered completion date of 30 Apr 2026 has passed
Construction
91.12% complete (DLD inspection, 29 Sep 2026)
Payment plan
15% on booking, 52% during construction, 1% on handover, 32% after handover
Starting price
From about AED 614,000 at launch (Feb 2023); AED 999,000 on Samana's page now

Construction progress

91.12%

DLD inspection, 29 Sep 2026

Registered completion date

30 Apr 2026 (passed)

DLD project register via Continental Club

Developer's stated date

February 2027

Samana Developers, accessed 11 Oct 2026

Date promised at launch

July 2025

Khaleej Times, 20 Feb 2023

When will Samana Mykonos be handed over?

Samana Developers’ project page now says Samana Mykonos is scheduled for handover in February 2027 (accessed 11 October 2026). The Dubai Land Department (DLD) project register, project number 2561, still shows a completion date of 30 April 2026, which has passed (via Continental Club). When Samana launched the building on 20 February 2023, it gave July 2025 (Khaleej Times).

Other sources show a spread of dates. Property Finder still lists June 2025 and labels the project ready. Data Habibi shows Q2 2026 and JRE Dubai 30 November 2026. The DLD register shows the building as active and under construction.

Building-by-building dates and how the date has changed: Samana Mykonos handover date.

Samana Mykonos construction update

The DLD inspection of 29 September 2026 recorded 91.12% complete, up 10.15 points from about 81% on 20 May 2026 (DLD register via Continental Club). Property Finder carried a figure of 65.04% on 24 November 2025. At the pace recorded between May and September 2026, about 2.4 points a month, the remaining 8.88 points would take about four months from late September, which fits Samana’s February 2027 date.

The register gives a construction start of 30 June 2023. Propsearch names Al Milad Engineering Construction as main contractor and Arec Engineering Consult as architect. Escrow is held at Emirates NBD.

Samana Mykonos homes and sizes

The DLD register describes a single G+4 building of 198 units; Samana’s launch release described it as G+5, and Propsearch counts six storeys. Samana lists every apartment type with a private pool, while Data Habibi says selected apartments have one. The design follows the white Cycladic style of the Greek island.

Home type Units Size
Studio 143 412 to 474 sq ft
1 bedroom 35 768 to 916 sq ft
2 bedroom 16 1,437 to 1,771 sq ft
3 bedroom 4 About 1,466 sq ft

Unit counts and the middle 90% of sizes are from the DLD register via Continental Club.

Samana Mykonos prices and resale

Data Habibi gives a launch price of about AED 614,000, and Property Finder a current lowest price of AED 640,000. Samana’s page now shows a starting price of AED 999,000. Property Finder lists the project as sold out.

The DLD register shows 217 sales, all from the developer, with a median of AED 16,630 per square metre, about AED 1,545 per sq ft (Continental Club, transactions to 3 October 2026). Medians by type:

  • Studio, about 420 sq ft: AED 713,459 (155 sales).
  • 1 bedroom, about 840 sq ft: AED 1,068,737 (40 sales).
  • 2 bedroom, about 1,744 sq ft: AED 1,581,000 (17 sales).

The latest registered sales were a 415 sq ft studio at AED 728,992 on 25 September 2026 and a 1,748 sq ft 2 bedroom at AED 2.2 million on 24 September 2026 (Propsearch). Continental Club records the median price per square metre up 4% over the past year.

Samana Mykonos payment plan

Property Finder lists the plan as 15% at booking, 52% during construction, 1% on handover and 32% after handover. Data Habibi shows the same booking and handover shares. On a AED 713,000 studio, the post-handover share is about AED 228,000, paid after the keys. With the building not yet complete, the 1% handover payment and the post-handover instalments have not yet started.

Samana Mykonos developer and delivery record

Samana Developers registers Samana Mykonos through Samana International Real Estate Development. It launched the building on the same day as Samana Santorini, also in Dubai Studio City. Santorini was promised for April 2025 and handed over on 16 April 2026, when Samana said it had delivered more than 1,300 units (Business Today Middle East). Mykonos, promised for July 2025, is running later than its twin.

What to check before buying at Samana Mykonos

  1. The completion date and grace period in the SPA, since both the July 2025 launch date and the 30 April 2026 registered date have passed.
  2. Off-plan or ready status. Sales are still registered as off-plan, despite one portal showing the project as ready.
  3. The post-handover balance, 32% of the price, and when its instalments start.
  4. The next DLD inspection, to confirm completion before a February 2027 handover.

Samana Mykonos location: Dubai Studio City, Dubai

Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.

Questions buyers also ask

What is the Samana Mykonos handover date?

Samana Developers' page says February 2027 (accessed 11 October 2026). The DLD register still lists 30 April 2026, which has passed. At launch in February 2023, Samana gave July 2025.

What is the Samana Mykonos completion date?

The registered completion date is 30 April 2026 (DLD project number 2561), now passed. The DLD inspection of 29 September 2026 recorded 91.12% complete.

Is Samana Mykonos ready?

No. Property Finder labels it ready, but the DLD register lists it as under construction at 91.12% on 29 September 2026, and sales in September 2026 were still registered as off-plan pre-registration sales (Propsearch).

What is the Samana Mykonos price?

Launch prices started from about AED 614,000 (Data Habibi). Samana's page now starts at AED 999,000. DLD medians are about AED 713,000 for a studio and AED 1.07 million for a 1 bedroom (Continental Club).

Is Samana Mykonos the same as Samana Mykonos Signature?

No. Samana Mykonos is a 198 unit building in Dubai Studio City. Samana Mykonos Signature is a separate 300 unit building in Arjan.

Sources

  1. Continental Club, Samana Mykonos (DLD project register and transactions) (opens in a new tab)continentalclub.ae · inspection 29 Sep 2026, register updated 4 Oct 2026
  2. Samana Developers, Samana Mykonos (opens in a new tab)samanadevelopers.com · accessed 11 Oct 2026
  3. Property Finder, Samana Mykonos project page (opens in a new tab)propertyfinder.ae · progress update 24 Nov 2025, accessed 11 Oct 2026
  4. Propsearch, Samana Mykonos (opens in a new tab)propsearch.ae · updated 6 Apr 2026, transactions to 25 Sep 2026
  5. Data Habibi, Samana Mykonos (opens in a new tab)datahabibi.ae · accessed 11 Oct 2026
Request a Unit Review