Kasco's first Dubai tower, in Business Bay: registered for completion on 31 August 2027 and 61.1% built in August 2026. Prices, payment plan, sizes and DLD sales.

Studios, 1, 2 and 3 bedroom apartments Updated 11 October 2026

Short answer

Onda by Kasco has a registered completion date of 31 August 2027, and portals market a Q3 2027 handover. A DLD inspection on 19 August 2026 recorded the 23 storey Business Bay tower 61.1% complete, up from 35.7% in January 2026. Kasco first promised Q2 2027 at launch in October 2024, so the date has moved back by about one quarter. Prices launched from AED 1,077,777, and most of the price is paid on handover.

Status
under construction
Handover date
Registered completion 31 Aug 2027 (DLD); marketed as Q3 2027
Construction
61.1% complete (DLD inspection, 19 Aug 2026)
Payment plan
20% on booking, 10% during construction, 70% on handover (some agents list 20/20/60)
Starting price
From AED 1,077,777 at launch (Property Finder)

Registered completion date

31 Aug 2027

DLD project register via Continental Club

Construction progress

61.1%

DLD inspection, 19 Aug 2026

Units

352

DLD register; 348 residences at launch

Median registered sale price

AED 2.29 million

AED 1,833 per sq ft, 12 months to Sep 2026, Dubai Data

When will Onda by Kasco be handed over?

The Dubai Land Department (DLD) register gives Onda by Kasco a completion date of 31 August 2027. Property Finder lists a delivery date of August 2027, in Q3 2027, and agents quote the same quarter.

That is later than the first promise. When Kasco Developments launched Onda on 23 October 2024, it said completion and handover were expected in Q2 2027 (Construction Business News Middle East). By 10 January 2025, Kasco gave a planned delivery in Q3 2027 (MEP Middle East). At the DLD inspection on 19 August 2026, the tower was 61.1% complete, with just over 12 months to the registered date.

Building-by-building dates and how the date has changed: Onda by Kasco handover date.

Onda by Kasco construction update

The register records construction starting on 1 September 2024. Progress has been steady since mid 2025, averaging about 3.2 points a month between May 2025 and August 2026 (Dubai Data).

DLD inspection Recorded progress
12 Feb 2025 8.6%
28 May 2025 14.2%
15 Sep 2025 20.5%
29 Jan 2026 35.7%
7 May 2026 51.5%
19 Aug 2026 61.1%

Source: DLD register via Dubai Data and Continental Club. The escrow bank is Emirates NBD and the DLD project number is 3052. Kasco said in January 2025 that it would fund Onda without outside finance.

Onda by Kasco homes and sizes

At launch Kasco described a 23 floor freehold building with 348 residences: 85 studios, 190 one bedroom, 69 two bedroom and four three bedroom units with private pools on the top floor. The DLD register lists 352 units in one residential and commercial building with a ground floor, three podium levels and 19 further floors.

Home type Size (DLD floor plans) Size at launch
Studio 416 sq ft From 449 sq ft
1 bedroom 813 to 880 sq ft From 848 sq ft
2 bedroom 876 to 1,475 sq ft From 1,246 sq ft
3 bedroom 1,665 to 5,435 sq ft From 3,025 sq ft

DLD floor plan sizes are from Continental Club; launch sizes are from Kasco’s October 2024 announcement. Amenities include indoor and outdoor pools, a spa with a cold plunge and a running track.

Onda by Kasco prices and resale

Prices launched from AED 1,077,777 (Property Finder, Continental Club). In October 2026, Impala Real Estate listed available homes from AED 1.19 million to AED 2.96 million.

The DLD has recorded 304 sales in the building, almost all from the developer. Across all sales, the median was about AED 1.06 million for a studio of around 420 sq ft, AED 1.64 million for a 1 bedroom of around 850 sq ft and AED 2.29 million for a 2 bedroom of around 1,270 sq ft (Continental Club). In the 12 months to September 2026, 71 sales had a median of AED 2.29 million, or AED 1,833 per sq ft, which was 10.4% lower per sq ft than the year before (Dubai Data). Sales have slowed: from April to September 2026, no month recorded five or more sales. A 1 bedroom of 880 sq ft sold for AED 1.67 million on 18 August 2026.

Onda by Kasco payment plan

Sources disagree on the split. Continental Club, Impala and several agents list 20% on booking, 10% during construction and 70% on handover. Property Finder lists 20% on booking, 20% during construction and 60% on handover. One agent’s schedule shows 20% plus the 4% DLD fee on booking, then 10% in December 2025, 5% in March 2026 and 5% in October 2026, with 60% on completion and no post-handover plan (Offplans.com). In every version, at least 60% of the price is paid on handover.

Onda by Kasco developer and delivery record

Onda is the first project of Kasco Developments, part of the Kasco Group. Its second Dubai project, Val in Al Jaddaf Waterfront, is a 13 floor building of 121 units that Kasco expected to complete in Q4 2026 (MEP Middle East, January 2025). Kasco had no completed Dubai project to point to at launch.

What to check before buying at Onda by Kasco

  1. Whether 60% or 70% is due on handover, since sources give both and the amount may need a mortgage or cash at completion.
  2. The completion date in the SPA. Early buyers may have contracts dated to the Q2 2027 launch promise rather than 31 August 2027.
  3. Recent registered prices for the same layout, given that the price per sq ft fell 10.4% in the year to September 2026.

Onda by Kasco location: Business Bay, Dubai

Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.

Questions buyers also ask

What is the Onda by Kasco handover date?

The DLD register gives a completion date of 31 August 2027, and Property Finder lists August 2027, or Q3 2027. The tower was 61.1% complete at the DLD inspection on 19 August 2026.

What is the Onda by Kasco completion date?

The registered completion date is 31 August 2027. At launch in October 2024, Kasco said completion and handover were expected in Q2 2027; by January 2025 it gave Q3 2027.

What is the Onda by Kasco price?

Prices launched from AED 1,077,777 (Property Finder). Agents listed homes from about AED 1.19 million to AED 2.96 million in October 2026. DLD medians across all sales were about AED 1.06 million for studios, AED 1.64 million for 1 bedrooms and AED 2.29 million for 2 bedrooms (Continental Club).

What is the Onda by Kasco payment plan?

Most sources list 20% on booking, 10% during construction and 70% on handover. Property Finder and some agents list 20% on booking, 20% during construction and 60% on handover. The split in the SPA is the one that applies.

How many floors and units does Onda by Kasco have?

Kasco announced a 23 floor building with 348 residences in October 2024. The DLD register lists 352 units in a building of ground floor, three podium levels and 19 further floors.

Sources

  1. DLD project register via Continental Club, Onda by Kasco (opens in a new tab)continentalclub.ae · inspection 19 Aug 2026, registry updated 30 Sep 2026
  2. Impala Real Estate, Onda by Kasco (opens in a new tab)impalarealestate.com · checked 8 Oct 2026