Kyoto by ORO24
ORO24's 708-unit, 39-storey tower in Arjan. The registered completion date of 20 September 2026 has passed with the tower 16.96% built. Prices, sizes and payment plans.
Short answer
Kyoto by ORO24, a 708-unit tower in Arjan, had a registered completion date of 20 September 2026, and that date has passed. The tower was 16.96% complete at a Dubai Land Department (DLD) inspection on 11 September 2026. Sales opened in June 2023, and Data Habibi records a first promise of Q4 2025. Studios have sold for a median of AED 591,850, and the launch plans spread 35% to 40% of the price over the months after completion.
- Status
- under construction
- Handover date
- DLD registered completion 20 Sep 2026 (passed; still on the register on 10 Oct 2026)
- Construction
- 16.96% complete (DLD inspection, 11 Sep 2026)
- Payment plan
- 20% on booking, 37% during construction, 3% on completion, 40% over 40 months after completion (launch plan)
- Starting price
- Studios from about AED 610,000 (Property Finder); median studio sale AED 591,850
Registered completion date
20 Sep 2026 (passed)
DLD project register via Continental Club
Construction progress
16.96%
DLD inspection, 11 Sep 2026
Units
708
DLD project register
Median studio sale
AED591,850
258 DLD sales, Continental Club
When will Kyoto by ORO24 be handed over?
There is no valid date at the moment. The Dubai Land Department (DLD) register, where the tower is listed as Kyoto By ORO24 (project number 2702), gave a completion date of 20 September 2026. Nine days before that date, on 11 September 2026, a DLD inspection recorded the tower 16.96% complete. The date has now passed with most of the building still to be built.
Sources disagree on the first promise. Data Habibi records a delivery promise of Q4 2025 and Propsearch estimated December 2025, while the launch payment plans published by Bayut set completion in September 2026. One tracker of the register forecasts completion around 30 May 2028 based on the pace so far, and the register itself still showed the expired 20 September 2026 date on 10 October 2026 (Dubai Handover).
Building-by-building dates and how the date has changed: Kyoto by ORO24 handover date.
Kyoto by ORO24 construction update
Construction started on 20 June 2023 (DLD). Progress was 5.4% in July 2025 (Property Finder), 7.70% at an inspection on 2 March 2026 and 16.96% on 11 September 2026 (DLD project register via Continental Club). The September reading was the largest jump so far, 9.26 points in about six months. ORO24 published a December 2025 construction update on LinkedIn in January 2026.
The tower has a basement, ground floor, three podium levels and 35 residential floors, 39 storeys in all (Real Estate Club Dubai). The architect is National Engineering Bureau and the foundation contractor Atlas Foundations. The Land Department valued the project at AED 237 million (Propsearch). The escrow account is held at Zand Bank.
Kyoto by ORO24 homes and sizes
| Home type | Units | Size range |
|---|---|---|
| Studio | 303 | 376 to 437 sq ft |
| 1 bedroom | 336 | 533 to 773 sq ft |
| 2 bedroom | 67 | 986 to 1,246 sq ft |
| 3 bedroom | 2 | 1,375 sq ft |
Unit counts and sizes are from the DLD register via Continental Club. Nine in ten units are studios or 1 bedrooms. Amenities planned include a 40 metre infinity pool, a bowling alley, a padel court and virtual golf.
Kyoto by ORO24 prices and resale
Property Finder lists a launch price of AED 610,000, while one broker brochure gives AED 500,000, so sources disagree on the starting figure. The DLD register shows 592 sales since launch, only two of them resales. Median prices are AED 591,850 for studios of about 388 sq ft, AED 864,500 for 1 bedrooms of about 657 sq ft and AED 1,326,200 for 2 bedrooms of about 990 sq ft (Continental Club, September 2026). Recent sales include a 376 sq ft studio at AED 610,000 on 9 June 2026 and a 986 sq ft 2 bedroom at AED 1,360,400 on 16 July 2026. Continental Club records prices down 1% over the past year, against a 1% rise in Arjan.
Kyoto by ORO24 payment plan
Bayut’s building guide sets out the two launch plans:
- Option 1: 20% on booking, 1% a month from August 2023 to August 2026 (37%), 3% on completion in September 2026, then 1% a month from October 2026 to January 2030 (40%).
- Option 2: 15% on booking, 5% every four months from October 2023 to June 2026, 5% on completion in September 2026, then 1% a month from October 2026 to August 2029 (35%).
Property Finder now lists a 20/40/40 plan with 40% on handover. The launch plans fix instalments by calendar month, with the construction instalments ending in August 2026, when the tower was under 17% built.
Kyoto by ORO24 developer and delivery record
ORO24 was founded in 2021 by Atif Rahman, previously a director and partner at Danube Properties (Real Estate Club Dubai). Its first completed project is Torino, a gated community also in Arjan. Buyer reviews cited by Real Estate Club Dubai describe a handover delay of more than six months at Torino after the completion certificate. ORO24 is building several other towers at the same time.
What to check before buying at Kyoto by ORO24
- How the SPA ties payments to completion. The launch plans list dates in 2026, so it matters whether the completion and post-completion instalments follow the calendar or the actual completion.
- The grace period in the SPA after the 20 September 2026 registered date.
- Any revised date from ORO24 in writing, since the register still showed the expired date on 10 October 2026.
- The next DLD inspection figure, to see whether the March to September 2026 pace holds.
Kyoto by ORO24 location: Arjan, Dubailand, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Kyoto by ORO24 handover date?
No revised date had appeared in the DLD register by 10 October 2026. The register gave a completion date of 20 September 2026, which has passed with the tower 16.96% complete at the 11 September 2026 inspection. One tracker forecasts completion around 30 May 2028 at the current pace (Dubai Handover).
What is the Kyoto by ORO24 completion date?
The registered completion date was 20 September 2026. Data Habibi records a first promise of Q4 2025 and Propsearch estimated December 2025, while the launch payment plans set completion in September 2026 (Bayut). All of these dates have passed.
What is the Kyoto by ORO24 price?
Property Finder lists a launch price of AED 610,000. DLD sales have a median of AED 591,850 for studios, AED 864,500 for 1 bedrooms and AED 1,326,200 for 2 bedrooms (Continental Club, Sep 2026). In July 2026 a 565 sq ft 1 bedroom sold for AED 800,850.
What is the Kyoto by ORO24 payment plan?
The launch plan took 20% on booking, 1% a month during construction for 37%, 3% on completion and 40% at 1% a month for 40 months after completion. A second option took 15% on booking, 35% in instalments, 5% on completion and 35% over 35 months after (Bayut). Property Finder now lists 20/40/40.