Illustration: aerial view of a villa community with green spaces
Emaar Properties · Dubai South

Emaar South

A Dubai South golf community with villas, townhouses and apartments. Early phases handed over from 2020; new releases began construction in April 2026.

3 to 5 bedroom villas and townhouses, and apartments Updated 28 September 2026

Short answer

Emaar has not published one payment plan for the whole of Emaar South. Plans differ by release. A payment schedule published for one Emaar South release ran 10% at booking, 30% in three instalments to August 2024, 50% during construction to October 2026 and a final 10% at completion in August 2027 (off-planproperties.ae, accessed 28 Sep 2026). Newer releases, including Golf Acres, Golf Dale, Golf Meadows, Golf Verge and Golf Hills, which started construction in April 2026, are not covered by that example. Check the exact plan for your release before booking.

Status
partly handed over
Handover
Early phases from 2020; newer releases under construction from Apr 2026
Payment plan
Varies by release, typically staged to completion
Starting price
From AED 1.8M for a 3 bedroom villa (listed, Sep 2026)

New releases, construction started

Apr 2026

Golf Acres, Golf Dale, Golf Meadows, Golf Verge, Golf Hills. Propsearch

Golf club opening

Q4 2026

Scheduled. Propsearch

3 bedroom villa, current

From AED1.8M

Propsearch, Sep 2026. Listed price

2 bedroom apartment, current

From AED1.44M

Propsearch, Sep 2026. Listed price

When will Emaar South be handed over?

Emaar South has been handed over and built out in phases since 2020. The table below shows what Propsearch reports for each release.

Release Status Date
Golf Links, Golf Views Handed over Around mid-2020
Urbana I Handed over March 2020
Urbana II and III Handed over Later in 2020
Golf Acres, Golf Dale, Golf Meadows, Golf Verge, Golf Hills Under construction Construction started April 2026
Emaar South Golf Club Scheduled Q4 2026

No single completion date covers the whole community. Emaar South is a large masterplan and Emaar continues to launch new releases within it, each on its own construction and handover schedule.

What is the Emaar South payment plan?

Emaar has not published one payment plan for Emaar South as a whole. Its own material on the community’s plans says each release has its own terms, and that these can change between releases.

One published example, for an earlier Emaar South release, ran as follows.

Stage Share Due
Booking 10% At booking
Pre-construction instalments 30% Three instalments to Aug 2024
Construction instalments 50% Five instalments to Oct 2026
Completion 10% Aug 2027

As an example only, applying that structure to a 3 bedroom villa listed from AED 1.8 million: 10% at booking is AED 180,000, plus the 4% Dubai Land Department registration fee of AED 72,000, for AED 252,000 due at booking. The 80% due during construction comes to AED 1,440,000, and the final 10% at completion is AED 180,000. This is illustrative. The plan for a specific release, including Golf Acres, Golf Dale, Golf Meadows, Golf Verge and Golf Hills, may differ.

What do homes at Emaar South cost?

Home type Price from (listed, Sep 2026)
3 bedroom villa AED 1.8 million
2 bedroom apartment AED 1.44 million

Propsearch lists villas up to AED 2.6 million and apartments up to AED 1.79 million within the community, depending on release and size. Launch prices for the newest releases have not been published.

What to check before booking

  1. The payment plan for your specific release, since Emaar has said plans differ across Emaar South and are not fixed community wide.
  2. The construction start date for your release, given several, including Golf Acres and Golf Hills, only started in April 2026.
  3. The DLD project status for your building or plot, through the Dubai Land Department’s project status enquiry service.
  4. The handover date in your sale and purchase agreement, rather than a date for the wider Emaar South masterplan.

Questions buyers also ask

Has any part of Emaar South already been handed over?

Yes. Golf Links and Golf Views were handed over around mid-2020, and Urbana's three phases were handed over across 2020, according to Propsearch.

What is the newest release at Emaar South?

Golf Acres, Golf Dale, Golf Meadows, Golf Verge and Golf Hills all started construction in April 2026, per Propsearch. None has a published handover date yet.

Is there one payment plan for all Emaar South releases?

No. Emaar's own material on Emaar South's payment plans says terms are set release by release and can change between releases.

When does the Emaar South Golf Club open?

Propsearch lists a scheduled opening in the fourth quarter of 2026. Emaar has not published a firm date on its own project page.

What is the current price of a villa at Emaar South?

Propsearch lists 3 bedroom villas from AED 1.8 million up to AED 2.6 million, as listed prices in September 2026.

Sources