Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Windsor House handover date?

Updated 11 October 2026 Windsor House

Short answer

Windsor House has a registered completion date of 31 July 2029 in the DLD project register, and Bayut and developer data give Q3 2029. The DLD inspection on 17 June 2026 recorded 3.08% complete. Broker pages published after the July 2025 launch said Q3 2028, so older sales material is a year earlier than the current date.

Registered completion date (DLD)

31 Jul 2029

DLD project register via Continental Club, accessed 11 Oct 2026

Latest construction progress

3.08%

DLD inspection, 17 Jun 2026

Developer's stated date

Q3 2029

Developer supplied via Continental Club; Bayut, 17 Feb 2026

Date in launch listings

Q3 2028

Proptz, OPR and Binayah, after the July 2025 launch

Windsor House handover date: the latest position

Windsor House is registered with the Dubai Land Department for completion on 31 July 2029. Continental Club lists the developer’s date as Q3 2029, and Bayut’s building guide gives the same quarter. Full project details are on the Windsor House page.

The DLD inspection on 17 June 2026 recorded 3.08%, up from 0% at the first inspection on 10 September 2025. Most of the structure is still to be built, with just under three years to the registered date.

Windsor House handover date by building

The DLD register holds Windsor House as one project, so one date applies to all 424 units. The register describes two residential buildings of two basements, ground and 10 floors. Continental Club’s summary counts three buildings, and Proptz describes the 424 units as the first phase of a larger plan, so sources differ on the building count.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Windsor House (DLD project 4035) 3.08% (17 Jun 2026) 31 Jul 2029 Q3 2029 (developer via Continental Club; Bayut)

How the Windsor House handover date has changed

Date Event Source
31 Jul 2025 Ellington announces Windsor House, its first Dubai South project Ellington
31 Jul 2025 Launch report says first residents expected by late 2026 Abu Dhabi Week
After launch (undated) Broker pages list handover as Q3 2028 Proptz, OPR, Binayah
1 Aug 2025 Registered construction start DLD register via Continental Club
10 Sep 2025 First DLD inspection, 0% DLD register via Continental Club
17 Feb 2026 Bayut lists handover as Q3 2029 Bayut
17 Jun 2026 DLD inspection, 3.08% DLD register via Continental Club
Oct 2026 Register shows completion on 31 July 2029 Continental Club, updated 4 Oct 2026

The late 2026 figure in the Abu Dhabi Week report does not appear anywhere else and does not match the register. The Q3 2028 date was common in broker material but does not appear on Ellington’s own project page. The date that is on record, both at DLD and with Bayut, is Q3 2029.

What the Windsor House handover date means for payments

Windsor House is sold on a 70/30 plan with no post-handover instalments. According to the schedule on Offplans.com, buyers pay 20% on booking, then fixed instalments at 60, 120, 180, 240 and 360 days, which together bring the total to 40% within a year. Four 5% instalments fall due when construction reaches 20%, 30%, 40% and 50%. The final 30% is due on completion.

At 3.08% progress, the construction-linked instalments have not started. For a 1 bedroom at the DLD median of AED 1,157,828, the completion payment is about AED 347,000, due on or after 31 July 2029.

What to check before relying on the Windsor House date

  1. The completion date printed in the SPA, since early contracts and brochures may carry Q3 2028.
  2. The grace period in the SPA after the completion date, which applies before any late delivery claim.
  3. Progress before each construction-linked instalment. The Dubai REST app shows the DLD percentage for project 4035.

Questions buyers also ask

When will Windsor House be ready?

The DLD register sets 31 July 2029 as the completion date, and Bayut lists Q3 2029. The building was 3.08% complete on 17 June 2026.

What is the Windsor House completion date?

31 July 2029, as filed with DLD under project number 4035 (Continental Club, registry updated 4 Oct 2026).

Has the Windsor House handover date been delayed?

Broker pages published after the July 2025 launch quoted Q3 2028. By February 2026 Bayut listed Q3 2029, and the DLD register shows 31 July 2029. Ellington has not published a quarter on its own project page, so it is not clear whether Q3 2028 was ever the developer's date.

Will Windsor House be ready in 2026?

No. One launch report (Abu Dhabi Week, 31 July 2025) said Ellington expected first residents by late 2026, but no other source repeats this, and the DLD register shows 3.08% progress in June 2026 and a 31 July 2029 completion date.

Sources

Request a Unit Review