Handover date

When is the Wellington Ocean Walk handover date?

Updated 11 October 2026 Wellington Ocean Walk

Short answer

Wellington Ocean Walk has a registered completion date of 16 December 2028, while the developer's stated handover is Q4 2027. The last Dubai Land Department inspection, on 27 July 2026, recorded the building 15.9% complete. At the pace recorded between April and July 2026, the Q4 2027 date would need much faster progress, so the date written into each SPA is the one to rely on.

Registered completion date

16 Dec 2028

DLD project register via Continental Club

Latest construction progress

15.9%

DLD inspection, 27 Jul 2026

Developer's stated date

Q4 2027

Continental Club (developer supplied); Metropolitan; Driven Properties

Portal date

16 Dec 2028

Property Finder, accessed 11 Oct 2026

Wellington Ocean Walk handover date: the latest position

Wellington Ocean Walk is registered with the Dubai Land Department (DLD) for completion on 16 December 2028. The developer’s stated handover is Q4 2027, a year earlier. At the last DLD inspection, on 27 July 2026, the building was 15.9% complete. Prices, sizes and the payment plan are on the project page: Wellington Ocean Walk.

Property Finder lists the registered date of 16 December 2028. Metropolitan and Driven Properties quote Q4 2027, which is also shown as the developer date on Continental Club. No source reports a revision to either date.

Wellington Ocean Walk handover date by building

Ocean Walk is one building with 79 homes, registered as “Wellington Ocean Walk” (DLD project 4026) on Dubai Islands.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Wellington Ocean Walk (79 units, G + 2 podium + 8 floors + roof) 15.9% (27 Jul 2026) 16 Dec 2028 Q4 2027 (developer, via Continental Club, Metropolitan, Driven Properties); 16 Dec 2028 (Property Finder)

How the Wellington Ocean Walk handover date has changed

Date Event Source
19 Aug 2025 First DLD inspection: 0% DLD via Continental Club
16 Sep 2025 Sales launch Property Finder
16 to 17 Sep 2025 Construction start; completion registered for 16 Dec 2028 DLD via Continental Club; Property Finder
26 Jan 2026 DLD inspection: 3.98% DLD via Continental Club
29 Apr 2026 DLD inspection: 12.93% DLD via Continental Club
27 Jul 2026 DLD inspection: 15.9% DLD via Continental Club
Oct 2026 Register still shows 16 Dec 2028; developer still quotes Q4 2027 Continental Club; Metropolitan; Driven Properties

The date has not moved. What differs is the source: the developer markets Q4 2027, while the register and Property Finder carry 16 December 2028. Progress ran at about three points a month from January to April 2026, then slowed to about one point a month from April to July. To finish by 31 December 2027 the building would need about five points a month from August 2026. Continental Club’s straight-line projection from recent readings gives 9 July 2031, a calculation rather than a developer date.

What the Wellington Ocean Walk handover date means for payments

Both published plans put 45% of the price after handover. Property Finder lists 10% at launch and 45% during construction in seven instalments. Metropolitan lists 10% on booking, 40% during construction and 5% on handover, then 1% a month for 45 months after handover. That makes the handover date the start of almost four years of instalments. If the building completes in December 2028 rather than late 2027, the post-handover schedule would start about a year later and run to around September 2032.

What to check before relying on the Wellington Ocean Walk date

  1. Which date the SPA states. A contract with Q4 2027 and one with 16 December 2028 give a buyer different rights if the building is late.
  2. The grace period the SPA allows after that date, before any delay remedy applies.
  3. How the construction instalments are triggered. Seven instalments tied to dates could run ahead of a site that was 15.9% built in July 2026.
  4. The next DLD inspection, to see whether progress picks up from the slower April to July 2026 rate.

Questions buyers also ask

Is Wellington Ocean Walk finished?

No. The DLD inspection of 27 July 2026 recorded the building 15.9% complete. Its registered completion date is 16 December 2028.

What is the Wellington Ocean Walk completion date?

16 December 2028 on the DLD register (via Continental Club), the same date Property Finder lists. The developer gives Q4 2027.

Has the Wellington Ocean Walk handover date been delayed?

No revision has been recorded. The DLD date of 16 December 2028 has been on the register since construction started in September 2025. The gap is between that date and the developer's marketing date of Q4 2027, not a change over time.

How much is due after handover at Wellington Ocean Walk?

45% of the price under both published plans. Metropolitan says it is paid at 1% a month for 45 months after handover, plus 5% on handover itself.

Sources