Handover date

When is the Wellington Grand Villas handover date?

Updated 11 October 2026 Wellington Grand Villas

Short answer

Wellington Grand Villas has a registered completion date of 24 January 2028, and the developer's handover target is Q4 2027. The last Dubai Land Department inspection, on 27 July 2026, recorded the 22 villas 50.91% complete, up from 37.78% on 23 April 2026. The developer's quarter is earlier than the registered date, so the SPA date for each villa is the one that applies.

Registered completion date

24 Jan 2028

DLD project register via Continental Club

Latest construction progress

50.91%

DLD inspection, 27 Jul 2026

Developer's handover target

Q4 2027

Augusta Properties, 23 Sep 2026; 21st Century Real Estate, Jul 2025

Change since launch

None so far

Q4 2027 given in July 2025 and September 2026

Wellington Grand Villas handover date: the latest position

Wellington Grand Villas is registered with the Dubai Land Department (DLD) for completion on 24 January 2028. Brokers selling for Wellington Developments give a handover target of Q4 2027, a quarter earlier. Prices, sizes and the developer’s record are on the project page: Wellington Grand Villas.

The last DLD inspection, on 27 July 2026, recorded the 22 villas 50.91% complete. That was 13.13 points higher than the inspection of 23 April 2026, a pace of about 4.4 points a month. At that pace the remaining work would take about a year from July 2026, which fits within both the Q4 2027 target and the registered January 2028 date.

Wellington Grand Villas handover date by building

The project is one registration covering all 22 villas (DLD project number 3518, Wadi Al Safa 3). DLD does not publish separate progress for each villa.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Wellington Grand Villas (22 villas) 50.91% (27 Jul 2026) 24 Jan 2028 Q4 2027 (Augusta Properties, OffPlanVilla, 21st Century Real Estate)

How the Wellington Grand Villas handover date has changed

Date Event Source
Jun and Oct 2023 Plot registered at AED 48.6 million, then AED 64.5 million DLD via Mitchells
25 Mar 2025 Construction start recorded; registered completion 24 January 2028 DLD via Continental Club
Jul 2025 Brochure released; handover given as Q4 2027 Wellington Developments; 21st Century Real Estate
18 Aug 2025 First villa sale registered DLD via Mitchells
23 Apr 2026 DLD inspection: 37.78% DLD via Continental Club
27 Jul 2026 DLD inspection: 50.91% DLD via Continental Club
23 Sep 2026 Handover still given as Q4 2027 Augusta Properties

The date has not moved since launch. Continental Club labels the project Q1 2028, matching the registered date rather than the developer’s quarter.

What the Wellington Grand Villas handover date means for payments

Under the published 35/65 plan, 65% of the price falls due on handover, with no post-handover instalments listed. Continental Club gives 10% down and 25% during construction; Augusta Properties gives 20% on booking and 15% during construction. On a villa at the AED 18 million starting price, the handover payment is about AED 11.7 million. The handover notice therefore sets the date for most of the price.

What to check before relying on the Wellington Grand Villas date

  1. Which date the SPA uses. The developer’s Q4 2027 and the registered 24 January 2028 differ by up to a quarter.
  2. The next DLD inspection. The April to July 2026 pace needs to continue for Q4 2027 to hold.
  3. Whether all 22 villas hand over together. DLD tracks the project as one registration, so the developer’s handover notice is the only place a villa-by-villa schedule would appear.

Questions buyers also ask

When will Wellington Grand Villas be completed?

The registered completion date is 24 January 2028 (DLD project register). The developer's target is Q4 2027.

Is Wellington Grand Villas finished?

No. The villas were 50.91% complete at the DLD inspection of 27 July 2026, and the register listed the project as under construction on 4 October 2026 (Mitchells).

Has the Wellington Grand Villas handover date been delayed?

Not so far. Brokers gave Q4 2027 in July 2025 and again in September 2026, and the registered date of 24 January 2028 has not changed.

How much is due at Wellington Grand Villas handover?

65% of the price is due on handover under the published 35/65 plan, about AED 11.7 million on an AED 18 million villa.