Handover date

When is the Wadi Hills handover date?

Updated 11 October 2026 Wadi Hills

Short answer

Wadi Hills has a registered completion date of 31 January 2028 on the Dubai Land Department (DLD) register, and HRE Development gives Q1 2028. The DLD inspection of 14 September 2026 recorded 7.72% progress, up from 2.61% on 4 June 2026. The date has not changed, but the building needs about 5.6 points a month to meet it, against about 1.5 points a month over the summer of 2026.

Registered completion date (DLD)

31 Jan 2028

DLD register via Continental Club, updated 7 Oct 2026

Latest construction progress

7.72%

DLD inspection, 14 Sep 2026

Developer's stated date

Q1 2028

Developer-supplied, Continental Club; Binayah

Portal date

Jan 2028

Property Finder, accessed 11 Oct 2026

Wadi Hills handover date: the latest position

Wadi Hills, DLD project 4100 in Dubailand Residence Complex, has a registered completion date of 31 January 2028. HRE Development gives Q1 2028 and Property Finder lists January 2028, so the sources agree. Prices, sizes and the payment plan are on the Wadi Hills page.

The DLD inspection of 14 September 2026 recorded 7.72% progress (Continental Club, registry updated 7 October 2026). The building is a single B+G+11 block, so all 131 units share one date. Construction was registered as starting on 1 November 2025, and Sharjah Islamic Bank holds the escrow account.

Wadi Hills handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Wadi Hills (131 units) 7.72%, 14 Sep 2026 31 Jan 2028 Q1 2028 (developer); Jan 2028 (Property Finder)

The DLD register names the developer as Wadi Hills City Real Estate Development, while portals list the project under HRE Development or Hijazi Real Estate. Property Finder lists 140 homes against 131 on the register.

How the Wadi Hills handover date has changed

Date Event Source
21 Sep 2025 Construction start shown on Property Finder Property Finder
22 Sep 2025 First DLD inspection: 0% DLD register via Continental Club
1 Nov 2025 Registered construction start; completion set for 31 January 2028 DLD register via Continental Club
24 Feb 2026 DLD inspection: 0.04% DLD register via Continental Club
4 Jun 2026 DLD inspection: 2.61% DLD register via Continental Club
14 Sep 2026 DLD inspection: 7.72% DLD register via Continental Club

The registered date has not moved. Progress rose 5.11 points between June and September 2026, about 1.5 points a month. Meeting 31 January 2028 needs about 5.6 points a month from mid-September 2026. Continental Club’s own projection at the pace of the past year runs far past 2028, though it labels this an estimate and not a developer commitment.

What the Wadi Hills handover date means for payments

The published plan is 10% down payment, 50% during construction, 10% on handover and 30% after handover (Property Finder, Binayah). Only 10% is tied to the handover date itself. The 30% post-handover balance starts after that, so a later handover pushes the end of the plan back too. On a studio at the DLD median of AED 726,000, that is AED 72,600 at handover and about AED 217,800 afterwards.

What to check before relying on the Wadi Hills date

  1. Progress at the next DLD inspection, against the 5.6 points a month needed. The last three inspections came three to four months apart.
  2. The SPA completion date and grace period, and whether the construction instalments are tied to dates or to progress milestones.
  3. The start and length of the post-handover instalments, which neither portal sets out.

Questions buyers also ask

When will Wadi Hills be completed?

The registered completion date is 31 January 2028 and the developer gives Q1 2028. The building was 7.72% complete on 14 September 2026 (DLD register via Continental Club).

Is Wadi Hills finished?

No. It is in the early stages of construction, at 7.72% on 14 September 2026.

Has the Wadi Hills handover date been delayed?

No. The registered date of 31 January 2028 has stayed the same in the sources checked, and the developer's Q1 2028 matches it. Progress so far is behind the pace needed to meet it.

How much is paid at Wadi Hills handover?

10% is due on handover and 30% after handover, following 10% down and 50% during construction (Property Finder, Binayah).

Sources