When is the VOI Residence by HVM Living handover date?
Short answer
VOI Residence by HVM Living had a registered completion date of 30 September 2026, which passed without the building being finished. The latest DLD inspection, on 6 July 2026, recorded 15.62% complete. Listings now show Q1 2027 to June 2027, but no revised date had been registered with DLD by 11 October 2026, and the pace since January 2026 has been under one point a month.
Registered completion date (DLD)
30 Sep 2026 (passed)
DLD project register via Continental Club
Latest construction progress
15.62%
DLD inspection, 6 Jul 2026
Listed handover
Q1 to Q2 2027
JRE, Palmera, Ezre, accessed 11 Oct 2026
Progress, Jan to Jul 2026
+5.75 points
DLD inspections via Continental Club
VOI Residence by HVM Living handover date: the latest position
VOI Residence by HVM Living had a registered completion date of 30 September 2026 in the DLD register, and that date has passed. The building was 15.62% complete at the last DLD inspection, on 6 July 2026. Prices, sizes and payment plans are on the VOI Residence by HVM Living page.
The register had not been given a new date by 11 October 2026. Listings show Q4 2026 (Propsearch), Q1 2027 (JRE, Palmera), Q2 2027 (Ezre) and 30 June 2027 (DubaiHaus). These are portal and broker dates, not filed dates.
VOI Residence by HVM Living handover date by building
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| VOI Residence by HVM Living (DLD project 3234, 68 units) | 15.62%, 6 Jul 2026 | 30 Sep 2026 (passed) | Q4 2026 (Propsearch); Q1 2027 (JRE, Palmera); Q2 2027 (Ezre); 30 Jun 2027 (DubaiHaus) |
VOI Residence is a single building of ground, six floors and a roof, so all 68 homes, 6 studios, 26 one bedroom and 36 two bedroom apartments, share the one date.
How the VOI Residence by HVM Living handover date has changed
| Date | What happened | Source |
|---|---|---|
| 20 Aug 2024 | First DLD inspection records 0% | Dubai Handover |
| 1 Oct 2024 | Construction start registered; completion registered for 30 Sep 2026 | DLD register |
| Oct 2024 | HVM Living publishes the project page | HVM Living |
| 27 May 2025 | First registered sale | Mitchells |
| 15 Jan 2026 | DLD inspection records about 9.9% | Continental Club |
| 6 Jul 2026 | DLD inspection records 15.62% | DLD register |
| 30 Sep 2026 | Registered completion date passes | DLD register |
| Oct 2026 | Listings show Q1 to Q2 2027 | JRE; Palmera; Ezre |
The January 2026 figure is derived from Continental Club’s note that progress rose 5.75 points between the 15 January and 6 July 2026 inspections. The registered date allowed two years for the build. After 21 months, about a sixth of the work was recorded.
What the VOI Residence by HVM Living handover date means for payments
On the most widely listed plan, 7% is due on handover and 48% over the two or three years after it (Alnair; Palmera; JRE). A later handover therefore pushes back the final instalments as well. On a 2 bedroom registered at AED 1,300,000 in September 2026, 48% is about AED 624,000. Buyers on the 20/32/48 plan pay that 48% in one sum at handover instead.
What to check before relying on the VOI Residence by HVM Living date
- The SPA completion date and grace period, now that 30 September 2026 has passed.
- Whether HVM Living has applied to DLD for a new date, through the DLD project status service.
- The next DLD inspection, the first since July 2026, to see whether the pace has risen above about one point a month.
Questions buyers also ask
Is VOI Residence finished?
No. The last DLD inspection, on 6 July 2026, recorded 15.62% complete.
Has the VOI Residence handover date been delayed?
Yes. The registered completion date of 30 September 2026 has passed, and listings now show Q1 2027 (JRE, Palmera), Q2 2027 (Ezre) or 30 June 2027 (DubaiHaus). HVM Living had not registered a new date by 11 October 2026.
When will VOI Residence be completed?
No official revised date has been filed. At the pace recorded between January and July 2026, about one point a month, the building would need far longer than the 2027 dates on listings, unless work speeds up.
When did construction start at VOI Residence?
The register dates the construction start to 1 October 2024. The first DLD inspection, on 20 August 2024, recorded 0% (Dubai Handover).