Handover date

When is the Vida Residences Hillside handover date?

Updated 11 October 2026 Vida Residences Hillside

Short answer

Vida Residences Hillside has a registered completion date of 31 May 2029, and Property Finder and Propsearch list the same month. The last Dubai Land Department inspection, on 4 May 2026, recorded the project 10% complete. The project has three buildings under one registration, so the date for a given unit is the one in its SPA.

Registered completion date

31 May 2029

DLD project register via Continental Club

Latest construction progress

10%

DLD inspection, 4 May 2026

Portal date

May 2029 (Q2 2029)

Property Finder, Propsearch, Metropolitan, accessed 11 Oct 2026

Construction start

30 Jun 2025

DLD project register via Continental Club

Vida Residences Hillside handover date: the latest position

Vida Residences Hillside is registered with the Dubai Land Department (DLD) for completion on 31 May 2029. At the last DLD inspection, on 4 May 2026, the project was 10% complete, about ten months after construction started on 30 June 2025. Prices, sizes and the payment plan are on the project page: Vida Residences Hillside.

Portals and the register agree on the date. Property Finder lists 31 May 2029, and Propsearch and Metropolitan give May 2029 or Q2 2029. The project is registered as “Vida Residences Hillside” (DLD project 3534) under Dubai Hills Estate L.L.C, Emaar’s development company for the community.

Vida Residences Hillside handover date by building

The DLD register lists three buildings and 500 homes under one project number, with a single completion date. Propsearch describes Tower A at 22 storeys and Tower B at 21, and Continental Club’s description adds 8 townhouses.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Vida Residences Hillside, all three buildings (500 homes) 10% (4 May 2026) 31 May 2029 31 May 2029 (Property Finder); May 2029 (Propsearch); Q2 2029 (Metropolitan)
Tower A (about 184 homes, 22 storeys) Not reported separately Same registration Not stated separately
Tower B (about 308 homes, 21 storeys) Not reported separately Same registration Not stated separately
Townhouses (8 homes) Not reported separately Same registration Not stated separately

The DLD reading covers the whole registration. A buyer cannot tell from the public register how far one tower is ahead of the other.

How the Vida Residences Hillside handover date has changed

Date Event Source
Jan 2025 Project first traced Propsearch
4 Feb 2025 First DLD inspection: 0% DLD via Continental Club
11 Feb 2025 Launch date given by fäm Properties fäm Properties
30 Jun 2025 Sales start (Property Finder) and construction start (DLD); completion registered for 31 May 2029 Property Finder; DLD via Continental Club
10 Sep 2025 DLD inspection: 0.57% DLD via Continental Club
14 Jan 2026 DLD inspection: 5.01% DLD via Continental Club
4 May 2026 DLD inspection: 10% DLD via Continental Club
Oct 2026 Register still shows 31 May 2029; portals list May 2029 Continental Club; Property Finder; Propsearch

The date has not moved since launch. Sources differ only on when sales opened, February or June 2025. Between January and May 2026 progress rose by about five points in under four months. Continental Club’s straight-line projection from the readings so far gives July 2032, but that projection is based on the slow foundation stage and is not a developer date.

What the Vida Residences Hillside handover date means for payments

Under the 10/70/20 plan, 10% is paid on booking and 70% during construction, which Property Finder says is split into seven instalments. The final 20% is due on handover. Because 80% is paid before completion, most buyers will have paid the bulk of the price well before May 2029. A later handover would delay only the last 20% and the keys, not the construction instalments already scheduled.

What to check before relying on the Vida Residences Hillside date

  1. Which building the unit is in. Tower A, Tower B and the townhouses share one registration, and the SPA may set a date for the specific building.
  2. The SPA completion date and grace period, against the registered 31 May 2029.
  3. How the construction instalments are triggered. If they are tied to dates rather than progress stages, payments can run ahead of the site.
  4. The next DLD inspection. The latest published reading is from 4 May 2026, more than five months old by October 2026.

Questions buyers also ask

Is Vida Residences Hillside finished?

No. The DLD inspection of 4 May 2026 recorded it 10% complete, and the registered completion date is 31 May 2029.

What is the Vida Residences Hillside completion date?

31 May 2029 on the DLD register (via Continental Club). Property Finder gives the same date, and Propsearch and Metropolitan list May 2029 or Q2 2029.

Has the Vida Residences Hillside handover date been delayed?

No change has been recorded. The register date of 31 May 2029 matches the date portals have listed since sales, and no revised date has been filed. Progress of 10% in May 2026 is early, so the next inspections will show whether the pace supports that date.

How much is due on handover at Vida Residences Hillside?

20% of the price under the 10/70/20 plan published by Property Finder and Propsearch. The other 80% is paid on booking and during construction.

Sources

  1. DLD project register via Continental Club, Vida Residences Hillside (opens in a new tab)continentalclub.ae · inspection 4 May 2026; registry updated 8 Oct 2026